Procedural Schedule
The Commission will allocate and award program funding annually beginning for year 2002 and continuing through at least 2011 (when the legislative authorization for the electric PGC sunsets). Unlike previous practice, however, each program will be authorized to run for two years instead of only one. Therefore, to avoid confusion about calendar years vs. funding years, the programs years will be referred to as Year 1, Year 2, etc. of continued PGC funding authorized by AB995 of September 2000. The table below clarifies this naming convention.
Table 7.1. Program Year Nomenclature
Year Name
Calendar year in which funding is collected by utility
Calendar years during which programs will operate
Year 1
2002
2002 and 2003
Year 2
2003
2003 and 2004
Year 3
2004
2004 and 2005
Year 4
2005
2005 and 2006
Year 5
2006
2006 and 2007
Year 6
2007
2007 and 2008
Year 7
2008
2008 and 2009
Year 8
2009
2009 and 2010
Year 9
2010
2010 and 2011
Year 10
2011
2011 and 2012
The following table summarizes the schedule associated with one complete program cycle.
Table 7.2. Scheduling Cycle
#
Item
Timing
Year 2 Example Date
1
Program Proposals for Calendar Year X Funding
October 1, Year X-1October 1, 2002
2
Commission Decision Approving Programs for Calendar Year X Funding
December 1, Year X-1
December 1, 2002
3
Contracts Signed and Programs Begin
January 1, Year X
January 1, 2003
4
Program Implementation Plan Finalized
January 31, Year X
January 31, 2003
5
Evaluation, Measurement and Verification Plans Finalized
April 15, Year X
April 15, 2003
6
Quarterly Report Due Covering First Quarter of Year X
May 1, Year X
May 1, 2003
7
Quarterly Report Due Covering First Half of Year X
August 1, Year X
August 1, 2003
8
Quarterly Report Due
November 1, Year X
November 1, 2003
9
Quarterly Report Due Covering First Full Year
February 1, Year X+1
February 1, 2004
10
Quarterly Report Due
May 1, Year X+1
May 1, 2004
11
Quarterly Report Due
August 1, Year X+1
August 1, 2004
12
Quarterly Report Due
November 1, Year X+1
November 1, 2004
13
Final Report Due (includes evaluation, measurement and verification report)
February 1, Year X+2
February 1, 2005
14
Evaluation Proceeding Begins
February 1, Year X+2
February 1, 2005
15
Decision on Final Payments
June, Year X+2
June, 2005
16
Final Payments Made
June, Year X+2
June, 2005