A preliminary schedule for this proceeding is given below. This schedule will be discussed and further refined after the first prehearing conference (PHC) on June 17 at 10:00 a.m., in the Commission Courtroom, 505 Van Ness Avenue, San Francisco. Consistent with Rule 6(e), we expect this proceeding to be concluded within 18 months.
Item |
Strategic Planning |
Metering Policies |
Program/ Pricing Options | ||
Objections to proceeding categorization required to be filed |
May 13, 2002 | ||||
Prehearing conference statements filed, including any comments on the scope of the proceeding as outlined in this order |
June 7, 2002 | ||||
First prehearing conference |
June 17, 2002 | ||||
Workshops on strategic planning for demand response development (potentially jointly, with CEC and/or CPA) |
June and July 2002 |
NA |
NA | ||
Parties file details of existing demand-response programs and pricing options |
NA |
NA |
July 10, 2002 | ||
Opening comments filed |
August 1, 2002 |
July 1, 2002 |
October 15, 2002 | ||
Reply comments |
August 15, 2002 |
July 15, 2002 |
November 1, 2002 | ||
Testimony and new proposals of respondents served |
September 16, 2002 |
September 2, 2002 |
December 2, 2002 | ||
Testimony of interested parties served |
October 1, 2002 |
September 16, 2002 |
December 16, 2002 | ||
Evidentiary hearings (if necessary) |
October 2002 |
January 2003 | |||
Opening briefs filed |
November 15, 2002 |
February 2003 | |||
Reply briefs filed |
December 2, 2002 |
March 2003 | |||
Proposed Decision mailed |
January 2003 |
April 2003 | |||
Final Commission decision |
February 2003 |
May 2003 |