XII. Ratemaking Treatment for Generation Procurement

As set forth in the ACR dated April 2, 2002, the objectives in developing an interim cost recovery procurement mechanism are to:

· improve the ability of the respondent utilities to meet their obligation to serve their customers' electric loads;

· assure just and reasonable electricity rates;

· enhance the financial stability and creditworthiness of respondent utilities;

· diminish the need for after-the-fact reasonableness reviews of procurement purchases;

· ensure the timely recovery in rates of procurement costs in order to support the credit of the utilities that function as load serving entities; and

· pursue our mandate to promote the development of renewable generation in California.

The ACR finds that "Edison's proposal is generally consistent with prior cost recovery mechanisms for PPs and it is therefore a familiar and understood approach to industry, advocates, and the financial community." The respondent utilities propose various cost recovery mechanisms to comply with the objectives and the preferred method. They indicate that a quick review and timely cost recovery process are critical to their financial stability and creditworthiness that would avoid any accumulation of large under-collections of purchased power costs.

The purpose of balancing accounts and timely recovery of procurement costs are intertwined in the AB 57. Proposed Section 454.5 (d) (3) contains certain procurement cost recovery objectives and provisions for the Commission to implement. The relevant part states that the Commission shall:


Ensure timely recovery of prospective procurement costs incurred pursuant to an approved procurement plan. The Commission shall establish rates based on forecasts of procurement costs adopted by the Commission, actual procurement costs incurred, or combination there of, as determined by the commission. The Commission shall establish power procurement balancing accounts to track the differences between recorded revenues and costs incurred pursuant to an approved procurement plan. The Commission shall review the power procurement balancing accounts, not less than semiannually, and shall adjust rates or order refunds, as necessary, to promptly amortize a balancing account, according to a schedule determined by the Commission. Until January 1, 2006, the commission shall ensure that any overcollection or under-collection in the power procurement balancing account does not exceed five percent of the electrical corporation's actual recorded generation revenues for the prior calendar year excluding revenues collected for the DWR. The Commission shall determine the schedule for amortizing the overcollection or undercollection in the balancing account to ensure that the five percent threshold is not exceeded. After January 1, 2006, this adjustment shall occur when deemed appropriate by the commission consistent with the objectives of this section.

Parties also state that their proposals are in harmony with the intent of proposed AB 57. The cost recovery mechanism proposals from PG&E, Edison, SDG&E, ORA and TURN are enumerated below.

A.

B. Parties Proposals

9. Parties Balancing Account Proposals

PG&E

SDG&E

EDISON

ORA

TURN

Purchased ElectricCommodity Account (PECA)18

Consisting of two sub-accounts:(1) It tracks monthly PG&E's costs and associated revenues and (2) It tracks DWR's revenues and costs.

Procurement Cost Adjustment Mechanism (PCAM) that tracks actual monthly energy procurement commitments and ancillary services costs and related revenues except for URG19 costs.

Existing Settlement Rates Balancing Account (SRBA) 20 that tracks the difference between "Settlement Rates"21 revenues and "Recoverable Costs."

Energy Cost Adjustment Clause (ECAC)22 Type balancing account that tracks billed revenues from established fuel and purchased power forecast rate and actual costs.

Balancing Account for fuel and procurement related costs including operations and maintenance (O&M)23 and capital costs for power from URG.

10. Scope of Included Expenses24

11. Edison Treatment of Pre and Post December 31, 2003

Edison proposes three approaches to record and recover costs associated with its RNS. Prior to its 2003 GRC decision, RNS costs would be recorded in the SRBA until new revenue requirements are established by the GRC decision to recover base costs and F&PP costs. Base costs include distribution, generation O&M, administrative and general (A&G), depreciation, return and taxes. After the GRC decision but before the PROACT Repayment Period (September 1,2001 to December 31, 2003), the authorized revenue requirements would be recorded in the SRBA as Recoverable Costs. After the Repayment Period, Edison proposes that new revenue requirements be established for the base and F&PP costs and their associated rates. An F&PP balancing account would be created to track procurement rate revenues based on the established F&PP rate and recorded actual costs.

12. Rate Adjustments and Amortization Periods

Utility

Rate Adjustment and Amortization Period Proposals

PG&E

Proposed to establish the initial PECA rate by advice letter based on costs associated with the approved procurement plan. Proposed to adjust rates monthly based on changes between monthly forecast of procurement costs and prior month's balancing account balance. Monthly rate adjustments will be by advice letter process similar to current core gas procurement charge (CGPC).

SDG&E

Proposed to establish PCAM rate29 by advice based on procurement costs associated with its approved procurement plan. Proposed to adjust rates to reflect changes between monthly forecast of procurement costs and prior month's balancing account balance. Edison also proposed to adjust rates by advice letter if the balance in the PCAM reaches 5%30 of the combined revenues in the PCAM and URGRA in view of proposed AB 57 trigger mechanism.

EDISON

Proposed to adjust Settlement Rates if at the end of any month the balance in its approved Rate Change Tracking Account (RCTA)31 reaches the 5% (trigger) of its prior year recorded generation revenues excluding DWR revenues or $280 million and reflect an updated procurement cost estimates by advice letter filing.32 Edison states that its proposal reflects the Agreement33 with the Commission and AB 57 proposed trigger mechanism. Edison proposes to establish Fuel and PP rate 34 and terminate the Settlement Rates after the Repayment Period.

ORA

Proposed that procurement cost forecasts be established annually by expedited application to be approved within 75 days of filing. ORA would adjust rates when the balancing account balance exceeds the 5% trigger proposed by AB 57 and amortized at a balancing rate.

C. Discussion

13. Balancing Account and Related Issues

There are several ratemaking issues raised by parties. These include a process to establish a procurement rate for fuel and purchased power-related costs, tracking procurement cost rate revenues against actual recorded costs in a balancing account, adjusting procurement rates based on monthly procurement forecasts and prior balancing account's balance or according to a balancing account balance threshold or specific amount, and adjusting Edison's Settlement Rates based on the language in the Settlement Agreement between Edison and the Commission. We have strong concerns with utilities' proposals to set rates beginning January 1, 2003 and to institute monthly rate adjustments.

First, Edison proposes to adjust Settlement Rates in this proceeding. The major factor contributing to Edison's proposal for a rate increase or decrease effective January 1, 2003 is not before us in this proceeding but in the DWR revenue requirement proceeding in A.00-11-038 et al. As a threshold issue, we do not know the magnitude of the change in DWR's revenue requirement for 2003 compared to 2002 that would be allocated to Edison. In addition, this proceeding focuses solely on RNS that DWR would not be able to procure in 2003 because of prohibition by law and not on the rate impact due to an increase in DWR's overall revenue requirement. We also do not consider here the operation of the SRBA35 and the related PROACT. Thus, we will not grant Edison's request for a rate increase or decrease effective January 1, 2003 because this proceeding is not the appropriate forum to set rates. Edison's request is denied without prejudice.

Second, we will not adopt a process to establish procurement rates by January 2003 at this time. We recognize that we must establish rates, but there are many factors that we must consider and not all of these are determined at this time. We do not yet know the size of RNS energy the utilities will need to procure in 2003 and their associated costs. In addition, existing rates collected from customers include surcharges. The embedded energy rate and the surcharges are used to determine whether end-use customer retail rates must be increased because of the impact of DWR's revenue requirements and the rate remittances to DWR for power charges, which customers do not see on their bills. In addition, in A.00-11-038 et al. we are establishing a bond charge for the costs of issuing bonds related to DWR's purchase power. We must determine whether existing rates and surcharges contain enough "headroom" as the Commission has used this term to absorb the expected RNS costs, the DWR charges, and any other provisions established by this Commission. Until the Commission considers the impact of all of these rate elements, we cannot determine the current allocated specific components of present rates for fuel and purchased power rates for PG&E, SDG&E, and Edison. Therefore, we deny the utilities' requests for fuel and purchased power rates at this time. However, we firmly intend to establish a process to track all necessary costs and to make the utilities whole, as appropriate. We now turn our attention to the remainder of the ratemaking issues raised by parties.

The procurement cost recovery proposals by PG&E, SDG&E, Edison, and ORA reflect many aspects of the provisions of AB 57 to achieve the objective of timely recovery of procurement costs incurred for an approved procurement plan. The parties agree that a balancing account is needed to track procurement costs. They differ however, as to when and how often rates should change, what should trigger or be included in rate changes, the time period during which rate adjustments should be amortized, and what process should be used. PG&E, Edison, and ORA agree there should be a balancing account to track fuel and purchased power revenues against actual recorded costs. They also agree on the types of cost to be included in the account. SDG&E, however, proposes to exclude URG costs from its account. Edison proposes to delay its F&PP balancing account until after the Repayment Period or December 31, 2003. PG&E wants to establish its PECA by the beginning of 2003. The three utilities have different names for their balancing accounts. For the sake of uniformity and clarity, PG&E, SDG&E, and Edison should refer to their new balancing accounts as the Energy Resource Recovery Account (ERRA) instead of the names they have proposed. We adopt ERRA because it would account for the cost of different types of energy resources. In addition, a common account name for tracking energy costs would allow for different types of comparisons among utilities in the area of types of cost inclusion, tariff language, and filings with the Commission, similar to the ECAC proceedings, which were used for this purpose prior to electric restructuring.

A comparison of the ECAC and the recommended ERRA follows:

DESCRIPTION

ECAC

PROPOSED ERRA

Major Cost Items Provisions Recorded or now Proposed

Gas, oil, coal, nuclear fuels36, and their inventory carrying costs, and water for power. Purchased power and Department of Energy (DOE) fees.

URG fuels; QF, Bilateral, Irrigation Districts, and Inter utility, Contracts. Power Purchases, ISO, Credit/Collateral, and Other Items approved

When Set Rates Adjust

Annual Revision of Forecasts including balancing account amortization

Semiannual Revision of Forecasts and Specific Amount Trigger Filing

Balancing Account Amortized Length

12 Months

12 Months and 90 Days for triggers

Rate Adjustment Triggers and Review

Annual Revision of Forecasted Costs and Review

Semiannual Revision of Forecasted Costs and Review.

Process

Application

Application

PG&E, Edison and ORA want similar types of cost items to be included in their balancing account proposals or the new ERRA. TURN supports the concept of a balancing account for fuel and purchased power costs and also suggests that O&M and capital costs for power produced from URG should be tracked with these for ease of comparison between costs of different resources and different ownership. We find merit in TURN's proposal, but we do not adopt it at this time. We should revisit this proposal when the Commission addresses whether the respondent utilities should build or operate new generation resources.

We adopt the ECAC type-balancing account proposed by PG&E, Edison, and ORA. Edison should not delay establishing its new ERRA proposal because of its existing ratemaking structure. Edison's ERRA should eliminate the need for the ISO and purchase power balancing accounts. The Native Load balancing account should be amended to exclude all URG fuel costs since they are now to be included in the ERRA. ERRA should therefore be a line item in the SRBA. We reject SDG&E's proposal to exclude URG costs from its new ERRA and agree with ORA that these should be included. Accordingly, SDG&E should modify its proposal to include URG costs for the new ERRA. We support this approach since it would facilitate energy cost comparison among utilities and assist us to track variable energy related costs, and establish energy revenue requirement and associated rate in the near future.

Below, we describe the semiannual update process that we establish for fuel and purchased power forecasts and the ERRA mechanism.

Date

Description

Beginning January 2003

Track 2002 fuel and purchased power authorized revenue requirements against actual recorded costs in the ERRA.

February 1 SDG&E

April 1 Edison

June 1 PG&E

File applications proposing to establish annual fuel and purchased power forecasts and true up 2002 fuel and purchased costs.

August 1 SDG&E

October 1 Edison

December 1 PG&E#

Review of balancing accounts, contract administration, URG expenses and least-cost dispatch.

We deny PG&E's and SDG&E's proposals to change forecast of procurement costs monthly and adjust rates to reflect the difference in the forecast and prior month's balancing account balance by advice letter process similar to monthly changes to gas core procurement charge because we establish an update process. Edison has not proposed monthly rate changes but would propose a rate change if at any month the balance in its Rate Change Tracking Account reaches a certain threshold. Edison's request is also denied.

We agree with ORA and TURN that we must balance the utilities' need for timely procurement cost recovery with the consequences of frequent rate adjustments on consumer behavior. We recognize PG&E's, SDG&E's and Edison's concern that they can no longer finance a large under-collection for a period of time longer than a month or two and recognize the importance of timely recovery of over-or-under collections of balancing accounts to their financial health and stability. We must, however, balance these concerns with customer interests. Monthly energy rate changes may significantly impact the bills of combined gas and electric customers since gas procurement charges are already being changed monthly. Gas usage is seasonal. The impact of pricing electricity monthly may not be the same as gas and therefore customer reaction may be totally different from prior experience. We have no analysis or information in this proceeding to allay our concerns.

14. Balancing Account Trigger Mechanism

We adopt ORA's balancing account trigger proposal with the following modifications. PG&E, SDG&E and Edison are to file applications in 2003 to establish fuel and purchase power rates based on their 2003 fuel and purchase power forecasted costs and these should be done semiannually thereafter. The ERRA proceeding should benefit from the quarterly updated information of the procurement plan. The forecast phase would establish forecast fuel and PP revenue requirements for the three utilities. We recognize that PG&E proposes that 2003 fuel and purchased power revenue requirements be established and approved in its GRCs. That matter is now to be decided in the forecast phase of this proceeding. PG&E's GRC applications should be correspondingly amended. The 2003 filings should include a true -up of actual recorded costs to adopted 2002 revenue requirements.

Prior to these filings, PG&E, SDG&E and Edison are to track the difference between recently approved fuel and purchased power revenue requirements37 by the Commission38 and actual recorded costs in their ERRA. We recognize that the ERRA will capture additional costs incurred for RNS procurement.

We will also establish a "minimum balance" approach for rate adjustments. Instead of changing rates when the recorded balance in the ERRA exceeds or reaches five percent of prior year recorded generation revenues excluding revenues collected for DWR, we direct PG&E, SDG&E and Edison to file expedited applications for approval in 60 days from the filing date when the new ERRA balance reaches four percent.39 The application will include a projected account balance in 60 days or more from the date of filing depending on when the balance will reach the five percent threshold. The application will also propose an amortization period for the five percent of not less than 90 days to ensure timely recovery of the projected ERRA balance. It should also include allocation of the over-and-under collection among customers for rate adjustment based on existing allocation methodology recognized by the Commission. Customer notice should be sent as soon as the application is filed for a rate increase or decrease.

We do not expect our four percent threshold trigger filing to require immediate revenue requirement adjustment in 2003 because gas prices have stabilized in 2002 compared to 2001 and we expect this trend to continue in 2003. Since revenue collected for DWR is excluded from the calculation of AB 57 trigger mechanism, we are also excluding it for the purpose of determining the trigger filing discussed above.

We will use the semiannual applications filed in mid-2003 to review the reasonableness of URG expenses, contract administration, and least-cost dispatch operations and to verify the entries in the ERRA.40

Comments on the Proposed Decision

This proceeding is assigned to Commissioner Lynch and ALJ Walwyn. The proposed decision of ALJ Walwyn in this matter was mailed to the parties in accordance with Public Utilities Code § 311(d) and Rule 77.1 of the Rules and Practice and Procedure.

The major changes to this decision are that it: incorporates Sections IV-X of Commissioner Peevey's alternate decision that was mailed on October 10, 2003; adopts the utilities' procurement plans filed on May 1, 2002 as modified by later utility filings and this decision; revises the proposed decision's standards of conduct; sets a procedural schedule for the long-term planning phase; adopts more streamlined regulatory processes; states our preference to adopt an incentive mechanism; and makes other changes in response to parties' comments.

Findings of Fact

1. Edison, PG&E, and SDG&E are the respondent utilities in this proceeding.

2. Both the Commission and the Legislature have clearly expressed the intent to return the respondent utilities to full procurement on January 1, 2003.

3. This decision adopts the regulatory framework under which Edison, PG&E, and SD&GE shall resume full procurement responsibilities on January 1, 2003.

4. Today, in excess of 90% of bundled service energy requirements are provided by existing DWR and utility contracts as well as utility retained generation.

5. In D.02-08-071, the Commission recently granted PG&E and Edison authority to enter contracts through DWR to cover their projected procurement needs in 2003-2007.

6. While we share the goal of Edison and PG&E regaining an investment grade rating, this is not a necessary precondition to their resumption of their procurement responsibilities. SDG&E was and always has been an investment grade utility.

7. Many companies in the energy industry today do not have an investment grade credit rating and are able to conduct business.

8. Several companies state they would enter contracts with Edison and PG&E.

9. Both Edison and PG&E have strong cash positions and cash flow, arising from current rates being above current operating costs. Edison and PG&E will be operating in a regulated environment with ratemaking mechanisms that ensure timely and stable cost recovery.

10. Edison currently meets the rating agencies' criteria for an investment grade utility and is on the verge of regaining its investment grade rating. The ratemaking treatment adopted here supports that effort.

11. PG&E is presently in bankruptcy but under the Commission's proposed Plan of Reorganization, PG&E will be able to quickly emerge from bankruptcy as a creditworthy entity, because it will meet the rating criteria for investment grade.

12. Aglet provides convincing evidence that Edison's and PG&E's recent recorded earnings, cash positions, and anticipated cash flows compare favorably with the collateral and procurement amounts required, even using the high estimates of Exhibits 139C and 140C.

13. We find Edison's and PG&E's procurement needs in 2003 are well within their ability to finance.

14. The remaining residual net short requirements of Edison and PG&E for 2003 can be met through a combination of directly contracting with wholesale energy suppliers, purchases in the energy markets administered by the ISO, and purchases of demand-side resources, including distributed and self-generation.

15. Collateral, in the form of bank letters of credit or other financial instruments are currently available to both companies.

16. The Legislature has passed, and Governor Davis has signed, two pieces of legislation with significant implications for renewable generation procurement by the utilities. These measures are SB 1078 and SB 1038.

17. We should direct the utilities to submit, with their short-term procurement plan on November 12, 2002, a report on the status of their procurement under the renewable generation mandate of our previous order. Utilities should document their plan for meeting the 1% procurement required in D.02-08-071, including what has been accomplished and what remains to be done. Commission staff is available to facilitate compliance with this direction.

18. Interested parties should address in comments on January 6, 2003 and reply comments on January 13, 2003, their recommendations on the procedural process and schedule for implementing SB 1078.

19. It is reasonable to require the utilities to meet a reserve requirement, as part and parcel of their obligation to serve.

20. Though we state a preference for the adoption of an incentive mechanism to allow utilities to balance procurement risks and rewards, we do not have enough information to adopt such a mechanism at this time.

21. It is reasonable to place a moratorium on Edison, PG&E, or SDG&E dealing with their own affiliates in procurement transactions, beginning January 1, 2003, to allow for completion for a careful reexamination and appropriate modification of our affiliate rules. This moratorium will continue until we complete our rulemaking to modify affiliate rules, or for two years, whichever date is first. Utilities may propose to include specific affiliate transactions in their procurement plans but these proposals cannot be implemented until the end of moratorium. Based on comments, we are persuaded that transactions through the ISO that can be demonstrated to include multiple and anonymous bidders are permissible.

22. We will not adopt a process to establish procurement rates by January 2003 as there are many factors that must first be considered and not all of these are determined at this time. Until the Commission determines whether existing rates and surcharges contain enough "headroom," as the Commission has used this term, to absorb the expected RNS costs, the DWR charges, and any other provisions established by the Commission, we cannot determine the current allocated specific components of present rates for fuel and purchased power rates for Edison, PG&E, and SDG&E.

23. We should establish a balancing account for Edison, PG&E, and SDG&E to track energy costs, excluding existing DWR contracts, that includes URG fuels, QF contracts, inter-utility contracts, ISO charges less reliability must-run revenues, irrigation district contracts, bilateral or forward market purchases, credit and collateral for procurement purchases, and ancillary services. For the sake of clarity and uniformity each utility should refer to this balancing account as the ERRA.

24. We find that a semiannual schedule for procurement rate adjustments and a 4% balancing account trigger mechanism properly balance the utilities need for timely cost recovery and the consequences of frequent rate adjustments on consumer behavior.

25. We should adopt an annual update process for fuel and purchased power forecasts and another proceeding to again review balancing accounts and rewrite review URG expenses, contract administration and least-cost dispatch. Each utility should file applications on a semiannual basis, as specified in Section XII.

26. Beginning January 1, 2003, the utilities should track 2002 URG fuel and purchased power authorized revenue requirements against actual recorded costs in the ERRA. In their first billings, utilities should file applications that true-up 2002 actual URG fuel and purchased power costs with authorized revenue requirements.

27. The PRG process is an interim one-year measure while the Commission augments its staff and hires an independent consultant or advisory service, pursuant to the contracting authority and $600,000 appropriated to the Commission for the purposes of implementing AB 57.

28. Participation in the procurement review group makes a significant contribution to effective implementation of this decision and parties eligible to receive intervenor compensation awards in this proceeding should be eligible to seek compensation for their work in these groups and in the on-going review of procurement advice letters and expedited applications.

29. No other price benchmark generated by a utility for its own internal use alters in any way the per se reasonableness of the 5.37 cents per kWh price adopted in D.02-08-071.

Conclusions of Law

1. We hereby adopt the utilities' May 1, 2002 procurement plans, as modified by later utility filings and this decision. The utilities shall resume procurement no later than January 1, 2003 pursuant to those plans and the provisions of this decision, subject to the modifications ordered by this decision and subject to any prospective modifications pursuant to Pub. Util. Code Section 454.5(e).

2. Consistent with Pub. Util. Code Sections 451, 761, 762, 768, 770 and proposed 454.5(a), the utilities have an obligation to serve.

3. Electricity procurement is a necessary and normal part of utility operations, conducted in the ordinary course of an electric utility's business. However, if PG&E believes it requires approval of the U.S. Bankruptcy Court to resume its procurement obligations, it should petition the court for approval immediately.

4. Edison and PG&E shall take whatever steps are necessary to post the required ISO collateral in order to resume Scheduling Coordination or procurement of the residual net-short no later than January 1, 2003. The utilities should also post the contract and procurement related collateral required to secure resources to meet their load.

5. Edison and PG&E should update their collateral requirement estimations, specifically accounting for ISO security requirements and other contract and procurement related collateral costs in their short-term procurement plans to be filed on November 12, 2002.

6. We should adopt a reserve requirement of 15% for each utility.

7. The Commission has authority under Section 701.3 to order procurement in 2003 of any unmet amount of renewable energy ordered in D.02-08-071.

8. The utilities should file each quarter's procurement transactions that conform to the approved plan by advice letter. The advice letter should contain all information in the adopted master data request at Appendix B. The Commission's Energy Division should review the transactions to ensure the prices, terms, types of products, and quantities of each product conform to the approved plan. Consistent with AB 57, any transaction submitted by advice letter that is found to not comport with the adopted procurement plan may be subject to further review.

9. The utilities should by expedited application file transactions that do not conform to the adopted procurement plan. The procedures for expedited applications are set forth in Appendix C.

10. This advice letter process does not supplant the need to follow more traditional procedures for actions that would normally require such procedures. For example, proposals that rely on a budget increase, such as new expenditures for energy efficiency, must be advanced through an application. Similarly, new rate design, such as variations on Time-of-Use rates, require an application. New utility capital projects, such as transmission upgrades and power plants, often require a Certificate of Public Convenience and Necessity. These are only examples. The broader point is that the resource plan and advice letter process do not obviate compliance with other legal requirements.

11. The advice letter and expedited application processes adopted here meet the standards of Section 454.5(b)(7).

12. The utilities shall comply with the following minimum standards of conduct:

1. Each utility must conduct all procurement through a competitive process with only arms-length transactions. Transactions involving any self -dealing to the benefit of the utility or an affiliate, directly or indirectly, including transactions involving an unaffiliated third party, are prohibited.

2. Each utility must adopt, actively monitor, and enforce compliance with a comprehensive code of conduct for all employees engaged in the procurement process and ensure all employees with knowledge of its procurement strategies sign and later abide by a noncompetitive agreement covering a one year period after leaving utility's employment.

3. In filing transactions for approval, the utilities shall make no misrepresentation or omission of material facts of which they are, or should be aware.

4. The utilities shall prudently administer all contracts and generation resources and dispatch the energy in a least-cost manner. Our definitions of prudent contract administration and least cost dispatch are the same as our existing standard.

5. The utilities shall not engage in fraud, abuse, negligence, or gross incompetence in negotiating procurement transactions or administering contracts and generation resources.

6. All contracts must contain substantially the following language: "in the event of extraordinary circumstances, this contract shall be subject to such changes or modifications by the CPUC as the CPUC may direct."

7. In order to exercise effective regulatory oversight of the behavior discussed above, all parties to a procurement contract must agree to give the Commission and its staff reasonable access to information within seven working days, unless otherwise practical, regarding compliance with these standards.

13. We should review contract administration and economic dispatch issues on a timely and regular basis. There is no time limitation on our investigation of the violation of any other standard above; the Commission retains full authority to investigate when a violation is discovered and to effect any and all remedies available to the Commission. These standards are consistent with proposed Section 454.5(h).

14. Customer-side distributed generation that utilizes the technologies listed in Section V.B of the decision is eligible for RPS participation. Including renewable DG as part of our definition will serve to encourage its installation, regardless of whether the utility purchases the output or whether it serves to meet on-site load.

15. The full output of renewable DG should be credited to meeting the RPS or D.02-08-071 requirements, but only new renewable DG installations are to be credited (existing renewable DG does not count toward the utility's RPS baseline calculation).

16. Utilities should file by expedited application for approval in 60 days to adjust rates under an AB57 trigger mechanism if the ERRA balance reaches 4% in excess of prior year's annual fuel and purchased power costs. The application should include (1) a projected account balance in 60 days or more from the date of filing depending on when the balance will reach AB 57's five percent threshhold and (2) propose an amortization period for the five percent of not less than 90 days. The application should also include a proposed allocation of the over collection among customers based on our adopted rate design methodology during cost of service regulation.

17. We should not adopt Edison's proposal to adjust Settlement Rates here as the accounts affected are beyond the scope of this proceeding.

18. The ERRA balancing account and the forecast proceedings adopted in this decision comply with the requirements of proposed Section 454.5(d)(3).

19. The AB 57 trigger mechanism application should not be used to refund overcollections until it has been in operation for a full 12 months. Customer notice should be mailed in customers' bills as soon as the application is filed.

INTERIM ORDER

IT IS ORDERED that:

1. Southern California Edison Company (Edison), Pacific Gas and Electric Company (PG&E) and San Diego Gas & Electric Company (SDG&E) shall resume full procurement on January 1, 2003 under their continuing obligation to serve. The utilities shall take all necessary actions to prepare to do this in a timely and an efficient manner.

2. If PG&E believes that it requires approval of the U.S. Bankruptcy Court to resume full procurement, it should immediately petition the court for its approval.

3. The respondent utilities shall submit modifications to their short-term procurement plans on November 12, 2002 as set forth in the body of this decision, and further update the short-term procurement plans in 2003, when they find it necessary by expedited application filing. Before a filing, each utility shall meet and confer with its procurement review group.

4. All interested parties shall file comments on the November 12, 2002 updated plans on December 2, 2002 and all interested parties shall file reply comments on December 6, 2002.

5. The respondent utilities shall file a report on the status of their procurement under the renewable generation mandate of Decision 02-08-071 with their modified short-term procurement plan on November 12, 2002.

6. All interested parties shall file a proposed procedural process and schedule to implement Senate Bill 1078 on January 6, 2002 and reply comments on January 13, 2003.

7. SDG&E shall sponsor, in coordination with the other utilities, an all-party workshop to develop an incentive mechanism proposal. If consensus is reached, the proposal should be filed in each utilities' long-term procurement plan. If consensus is not reached, SDG&E should file a workshop report containing areas of agreement and disagreement by February 15, 2003 for our further consideration.

8. The respondent utilities shall file each quarter's procurement transactions that conform to their adopted procurement plan by Advice Letter within 15 days of the end of the quarter.

9. The respondent utilities shall file long-term procurement plans on April 1, 2003. Those long-term procurement plans should include a mix of all resources contained in Section V of this decision, or explain why reliance on procurement of a particular resource is not appropriate or cost-effective.

10. As discussed above, we require each utility to modify its existing plans. In recognition that there is a pressing need to have plans fully modified and in place by January 1, 2003, we distinguish between what shall be submitted November 12th as immediately necessary modifications to address short-term procurement and what shall be submitted subsequently to address long-term procurement plans. Anything required for the short-term plan shall also be in the long-term plan.

11. The respondent utilities shall file an outline of long-term procurement plan, as detailed in this decision, on February 3, 2002. All interested parties may file written comments on February 10, 2003. A prehearing conference shall be held February 17, 2003.

12. The respondent utilities shall file nonconforming transactions by expedited application.

13. This advice letter process does not supplant the need to follow more traditional procedures for actions that would normally require such procedures. For example, proposals that rely on a budget increase, such as new expenditures for energy efficiency, must be advanced through an application. Similarly, new rate design, such as variations on Time-of-Use rates, require an application. New utility capital projects, such as transmission upgrades and power plants, often require a Certificate of Public Convenience and Necessity. These are only examples. The broader point is that the resource plan and advice letter process do not obviate compliance with other legal requirements.

14. The respondent utilities shall comply with the procedure set forth in this decision for the establishment of the Energy Resource Recovery Account balancing account, and the trigger mechanism and forecast filings.

15. The respondent utilities shall comply with the minimum standards of conduct and restrictions on affiliate transactions set forth in this decisions.

16. Edison and PG&E should take whatever steps are necessary to post the required ISO collateral in order to resume Scheduling Coordination or procurement of the residual net-short no later than January 1, 2003. The utilities shall also post the contract and procurement related collateral required to secure resources to meet their load.

17. Edison and PG&E should update their collateral requirement estimations, specifically accounting for ISO security requirements and other contract and procurement related collateral costs in their short-term procurement plans to be filed on November 12, 2002.

This order is effective today.

Dated , at San Francisco, California.

************ APPEARANCES ************

Kate Poole
Attorney At Law
ADAMS BROADWELL JOSEPH & CARDOZO
651 GATEWAY BOULEVARD, SUITE 900
SOUTH SAN FRANCISCO CA 94080
(650) 589-1660
kpoole@adamsbroadwell.com

For: Coalition of California Utility Employees

James Weil
AGLET CONSUMER ALLIANCE
PO BOX 1599
FORESTHILL CA 95631
(530) 367-3300
jweil@aglet.org

For: Aglet Consumer Alliance

Donald Brookhyser
Attorney At Law
ALCANTAR & KAHL LLP
1300 S.W. 5TH AVENUE, SUITE 1750
PORTLAND OR 97201
(503) 402-8702
deb@a-klaw.com

For: Cogeneration Association of California

Chris King
Executive Director
AMERICAN ENERGY INSTITUTE
842 OXFORD ST.
BERKELEY CA 94707
(510) 435-5189
ckingaei@yahoo.com

For: American Energy Institute

Reed V. Schmidt
BARTLE WELLS ASSOCIATES
1889 ALCATRAZ AVENUE
BERKELEY CA 94703
(510) 653-3399
rschmidt@bartlewells.com

For: California City-County Street Light Association

Roger A. Berliner
BERLINER, CANDON & JIMISON
1225 NINETEENTH ST. N.W. SUITE 800
WASHINGTON DC 20036
(202) 955-6067
rogerberliner@bcjlaw.com

For: County of Los Angeles

Ronald Liebert
Attorney At Law
CALIFORNIA FARM BUREAU FEDERATION
2300 RIVER PLAZA DRIVE
SACRAMENTO CA 95833
(916) 561-5657
rliebert@cfbf.com

For: California Farm Bureau Federation

Emilio E. Varanini Iii
General Counsel
CALIFORNIA POWER AUTHORITY
901 P STREET, SUITE 142A
SACRAMENTO CA 95814
(916) 651-9750
cpacounsel@dgs.ca.gov

For: California Consumer Power & Conserv. Authority

Frederick M. Ortlieb
CITY OF SAN DIEGO
1200 THIRD AVENUE, 11TH FLOOR
SAN DIEGO CA 92101-4100
(619) 236-6318
fmo@sdcity.sannet.gov

For: City of San Diego

William Ahern
Senior Policy Analyst
CONSUMERS UNION
1535 MISSION STREET
SAN FRANCISCO CA 94103
(415) 431-6747
aherbi@consumer.org

For: Consumers Union

Patrick G. Mcguire
CROSSBORDER ENERGY
2560 NINTH STREET, SUITE 316
BERKELEY CA 94710
(510) 649-9790
patrickm@crossborderenergy.com

For: Watson Cogeneration Company

Steven F. Greenwald
Attorney At Law
DAVIS WRIGHT TREMAINE, LLP
ONE EMBARCADERO CENTER, SUITE 600
SAN FRANCISCO CA 94111
(415) 276-6500
stevegreenwald@dwt.com

For: Calpine Corporation







Dan L. Carroll
Attorney At Law
DOWNEY BRAND SEYMOUR & ROHWER, LLP
555 CAPITOL MALL, 10TH FLOOR
SACRAMENTO CA 95814
(916) 441-0131
dcarroll@dbsr.com

For: California Industrial Users

Andrew B. Brown
Attorney At Law
ELLISON, SCHNEIDER & HARRIS
2015 H STREET
SACRAMENTO CA 95814
(916) 447-2166
abb@eslawfirm.com

For: Independent Energy Producers Assoc.

Lynn M. Haug
Attorney At Law
ELLISON, SCHNEIDER & HARRIS, LLP
2015 H STREET
SACRAMENTO CA 95814-3109
(916) 447-2166
lmh@eslawfirm.com

For: Department of General Services

Andrew J. Skaff
Attorney At Law
ENERGY LAW GROUP, LLP
1999 HARRISON STREET, 27TH FLOOR
OAKLAND CA 94612
(510) 874-4370
askaff@energy-law-group.com

For: Dynegy Marketing & Trade

Daniel Kirshner
ENVIRONMENTAL DEFENSE FUND
5655 COLLEGE AVENUE, SUITE 304
OAKLAND CA 94618
(510) 658-8008
dkirshner@environmentaldefense.org

For: Environmental Defense

Steve Ponder
FPL ENERGY, INC., LLC
980 NINTH STREET, 16TH FLOOR
SACRAMENTO CA 95814-2736
(916) 449-9596
steve_ponder@fpl.com

For: FPL Energy, Inc.LLC.

Brian T. Cragg
Attorney At Law
GOODIN, MACBRIDE, SQUERI, RITCHIE & DAY
505 SANSOME STREET, NINTH FLOOR
SAN FRANCISCO CA 94111
(415) 392-7900
bcragg@gmssr.com

For: Caithness Energy, LLC

Anne Selting
GRUENEICH RESOURCE ADVOCATES
582 MARKET STREET, SUITE 1020
SAN FRANCISCO CA 94104
(415) 834-2300
aselting@gralegal.com

For: California/California State University

Jody London
GRUENEICH RESOURCE ADVOCATES
582 MARKET STREET, SUITE 1020
SAN FRANCISCO CA 94104
(415) 834-2300
jlondon@gralegal.com


Michael Mc Cormick
GRUENEICH RESOURCE ADVOCATES
582 MARKET STREET, SUITE 1020
SAN FRANCISCO CA 94104
(415) 834-2300
mmccormick@gralegal.com


Norman A. Pedersen
Attorney At Law
HANNA & MORTON
444 FLOWER STREET, SUITE 2050
LOS ANGELES CA 90071
(213) 430-2510
npedersen@hanmor.com


Daniel W. Douglass
Attorney At Law
LAW OFFICES OF DANIEL W. DOUGLASS
5959 TOPANGA CANYON BLVD., SUITE 244
WOODLAND HILLS CA 91367-7313
(818) 596-2201
douglass@energyattorney.com

For: Alliance for Retail Energy Markets and Western Power Trading Forum

Gregory Klatt
Attorney At Law
LAW OFFICES OF DANIEL W. DOUGLASS
411 E. HUNTINGTON DRIVE, SUITE 107-356
ARCADIA CA 91007
(626) 294-9421
klatt@energyattorney.com

For: Alliance for Energy Markets and Western Power Trading Forum

William H. Booth
Attorney At Law
LAW OFFICES OF WILLIAM H. BOOTH
1500 NEWELL AVENUE, 5TH FLOOR
WALNUT CREEK CA 94596
(925) 296-2460
wbooth@booth-law.com

For: California Large Energy Consumers Assoc.

Seth Hilton
Attorney At Law
MORRISON & FOERSTER LLP
101 YGNACIO VALLEY ROAD, SUITE 450
WALNUT CREEK CA 94596-8130
(925) 295-3371
shilton@mofo.com

For: El Paso Merchant Energy

Sara Steck Myers
Attorney At Law
122 28TH AVENUE
SAN FRANCISCO CA 94121-1036
(415) 387-1904
ssmyers@att.net

For: Energy Efficiency and Renewable Technologies

Sheryl Carter
NATURAL RESOURCES DEFENSE COUNCIL
71 STEVENSON STREET, STE 1825
SAN FRANCISCO CA 94105
(415) 777-0220
scarter@nrdc.org

For: NRDC

Jack F. Fallin
Chief Counsel
PACIFIC GAS AND ELECTRIC COMPANY
B30A
PO BOX 770000
SAN FRANCISCO CA 94177
(415) 973-2883
jff1@pge.com


Shirley Woo
Attorney At Law
PACIFIC GAS AND ELECTRIC COMPANY
PO BOX 7442
SAN FRANCISCO CA 94120
(415) 973-2248
saw0@pge.com

For: Pacific Gas and Electric Company

John J. Prevost
PACIFIC LUMBER COMPANY
125 MAIN STREET
SCOTIA CA 95565
(707) 764-4280
plenv01@northcoast.com

For: The Pacific Lumber Company

Peter Weiner
PAUL HASTINGS LLP
55 SECOND STREET, 24TH FLOOR
SAN FRANCISCO CA 94105
peterweiner@paulhastings.com


Nancy Rader
Consultant
1198 KEITH AVENUE
BERKELEY CA 94708
(510) 845-5077
nrader@igc.org

For: California Wind Energy Association

Daniel V. Gulino
Senior Vice President & General Counsel
RIDGEWOOD POWER, LLC
947 LINWOOD AVENUE
RIDGEWOOD NJ 07450
(201) 447-9000
dgulino@ridgewoodpower.com

For: RIDGEWOOD POWER, LLC

Glen Sullivan
Attorney At Law
SEMPRA ENERGY
101 ASH STREET
SAN DIEGO CA 92101-3017
(619) 699-5027
gsullivan@sempra.com

For: San Diego Gas & Electric Co.

Lisa Urick
Attorney At Law
SEMPRA ENERGY
555 W. FIFTH STREET, SUITE 1400
LOS ANGELES CA 90013-1011
(213) 244-2955
lurick@sempra.com

For: San Diego Gas & Electric Company

Beth A. Fox
Attorney At Law
SOUTHERN CALIFORNIA EDISON COMPANY
2244 WALNUT GROVE AVENUE, RM. 535
ROSEMEAD CA 91770
(626) 302-6897
beth.fox@sce.com

For: SCE

James Paine
Attorney At Law
STOEL RIVES, LLP
900 SW 5TH AVE STE. 2600
PORTLAND OR 97204-1268
(503) 294-9246
jcpaine@stoel.com

For: PacifiCorp

Keith R. Mccrea
SUTHERLAND, ASBILL & BRENNAN LLP
SUITE 800
1275 PENNSYLVANIA AVE., N.W.
WASHINGTON DC 20004-2415
(202) 383-0100
kmccrea@sablaw.com

For: California Manufacturers andTechnology Association

Matthew Freedman
MICHEL PETER FLORIO, RANDY WU
Attorney At Law
THE UTILITY REFORM NETWORK
711 VAN NESS AVENUE, SUITE 350
SAN FRANCISCO CA 94102
(415) 929-8876 EX314
freedman@turn.org

For: TURN

Paul C. Lacourciere
Attorney At Law
THELEN REID & PRIEST LLP
101 SECOND STREET
SAN FRANCISCO CA 94105-3601
(415) 369-7601
placourciere@thelenreid.com

For: Ridgewood Olinda LLC

Julia Levin
STEVEN HAMMOND
UNION OF CONCERNED SCIENTISTS
2397 SHATTUCK AVENUE, SUITE 203
BERKELEY CA 94704
(510) 843-1872
jlevin@ucsusa.org

For: Union of Concerned Scientists

John E. Rosenbaum
WHITE & CASE LLP
THREE EMBARCADERO CENTER, SUITE 2200
SAN FRANCISCO CA 94111-3162
(415) 544-1110
jrosenbaum@whitecase.com

For: California Cogeneration Council

Joseph M. Karp
Attorney At Law
WHITE & CASE LLP
THREE EMBARCADERO CENTER, SUITE 2200
SAN FRANCISCO CA 94111
(415) 544-1103
jkarp@whitecase.com

For: California Cogeneration Council

Jason J. Zeller
Legal Division
RM. 5002
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-4673
jjz@cpuc.ca.gov


********** STATE EMPLOYEE ***********


Dan Adler
Division of Strategic Planning
RM. 5119
505 VAN NESS AVE
San Francisco CA 94102
(415) 355-5586
dpa@cpuc.ca.gov


Peter Arth, Jr.
Executive Division
RM. 5132
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-2576
paj@cpuc.ca.gov


Diana Johnston
CALIF DEPARTMENT OF WATER RESOURCES
3310 EL CAMINO AVENUE ROOM 120
SACRAMENTO CA 95821
(916) 574-0311
djohnsto@water.ca.gov


Jeannie S. Lee
California Energy Resources Scheduling
CALIFORNIA DEPARTMENT OF WATER RESOURCES
3310 EL CAMINO AVENUE, ROOM 120
SACRAMENTO CA 95821
(916) 574-2220
jslee@water.ca.gov

John Pacheco
California Energy Resources Scheduling
CALIFORNIA DEPARTMENT OF WATER RESOURCES
3310 EL CAMINO AVENUE, ROOM 120
SACRAMENTO CA 95821
(916) 574-0311
jpacheco@water.ca.gov


Jonathan M. Teague
CALIFORNIA DEPT. OF GENERAL SERVICES
717 K STREET, SUITE 409
SACRAMENTO CA 95814-3406
(916) 323-8777
jonathan.teague@dgs.ca.gov


Constance Leni
CALIFORNIA ENERGY COMMISSION
MS-20
1516 NINTH STREET
SACRAMENTO CA 95814
(916) 654-4762
cleni@energy.state.ca.us


David Hungerford
CALIFORNIA ENERGY COMMISSION
1516 NINTH STREET, MS-22
SACRAMENTO CA 95814
(916) 654-4906
dhungerf@energy.state.ca.us


Fernando De Leon
Attorney At Law
CALIFORNIA ENERGY COMMISSION
1516 9TH STREET, MS-14
SACRAMENTO CA 95814-5512
(916) 654-4873
fdeleon@energy.state.ca.us


Heather Raitt
CALIFORNIA ENERGY COMMISSION
1516 9TH STREET, MS 45
SACRAMENTO CA 95814
(916) 654-4735
hraitt@energy.state.ca.us


Jennifer Tachera
CALIFORNIA ENERGY COMMISSION
1516 NINTH STREET, MS-14
SACRAMENTO CA 95814-5504
(916) 654-3870
jtachera@energy.state.ca.us

Karen Griffin
Manager, Electricity Analysis
CALIFORNIA ENERGY COMMISSION
MS-20
1516 9TH STREET
SACRAMENTO CA 95184
(916) 654-4833
kgriffin@energy.state.ca.us


Mike Jaske
CALIFORNIA ENERGY COMMISSION
1516 NINTH STREET, MS-22
SACRAMENTO CA 95814
(916) 654-4777
mjaske@energy.state.ca.us


Ruben Tavares
Electricity Analysis Office
CALIFORNIA ENERGY COMMISSION
1516 9TH STREET, MS 20
SACRAMENTO CA 95814
(916) 654-5171
rtavares@energy.state.ca.us

For: California Energy Commission

Kevin P. Coughlan
Executive Division
RM. 5221
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1175
kpc@cpuc.ca.gov


Maryam Ebke
Division of Strategic Planning
RM. 5119
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1112
meb@cpuc.ca.gov


Julie A Fitch
Executive Division
RM. 5203
505 VAN NESS AVE
San Francisco CA 94102
(415) 355-5552
jf2@cpuc.ca.gov


Faline Fua
Office of Ratepayer Advocates
RM. 4209
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-2235
fua@cpuc.ca.gov




Meg Gottstein
Administrative Law Judge
21496 NATIONAL STREET
PO BOX 210
VOLCANO CA 95689
(209) 296-4979
gottstein@volcano.net


David M. Gamson
Executive Division
RM. 5214
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1997
dmg@cpuc.ca.gov


Farzad Ghazzagh
Office of Ratepayer Advocates
RM. 4209
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1694
fxg@cpuc.ca.gov


Meg Gottstein
Administrative Law Judge Division
RM. 5044
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-4802
meg@cpuc.ca.gov


Julie Halligan
Division of Strategic Planning
RM. 5119
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1062
jmh@cpuc.ca.gov


Peter Hanson
Executive Division
RM. 4103
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1053
pgh@cpuc.ca.gov


Trina Horner
Executive Division
RM. 5217
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-5132
tah@cpuc.ca.gov

Aaron J Johnson
Executive Division
RM. 5205
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-2495
ajo@cpuc.ca.gov


Robert Kinosian
Executive Division
RM. 4205
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1500
gig@cpuc.ca.gov


Laura L. Krannawitter
Executive Division
RM. 5210
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-2538
llk@cpuc.ca.gov


James Loewen
Energy Division
AREA 4-A
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1866
loe@cpuc.ca.gov


Jay Luboff
Energy Division
AREA 4-A
505 VAN NESS AVE
San Francisco CA 94102
(415) 355-5531
jcl@cpuc.ca.gov


Lynne McGhee
Executive Division
RM. 5306
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1721
lmc@cpuc.ca.gov


A. Kirk McKenzie
Administrative Law Judge Division
RM. 5115
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-4622
mck@cpuc.ca.gov




Richard A. Myers
Energy Division
AREA 4-A
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1228
ram@cpuc.ca.gov


Wade Mccartney
Regulatory Analyst Iv
PUBLIC UTILITIES COMMISSION
ENERGY DIVISION
770 L STREET, SUITE 1050
SACRAMENTO CA 95814
(916) 324-9010
wsm@cpuc.ca.gov


Edwin Quan
Information & Management Services Divisi
RM. 3016
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-5765
eyq@cpuc.ca.gov


Manuel Ramirez
Executive Division
AREA 4-A
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-1826
mzr@cpuc.ca.gov


David W. Tollen
SIMPSON PARTNERS LLP
900 FRONT STREET, THIRD FLOOR
SAN FRANCISCO CA 94111
(415) 773-1790
davidt@simpsonpartners.com

For: DWR

Maria E. Stevens
Executive Division
RM. 500
320 WEST 4TH STREET SUITE 500
Los Angeles CA 90013
(213) 576-7012
mer@cpuc.ca.gov


Christine M. Walwyn
Administrative Law Judge Division
RM. 5005
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-2301
cmw@cpuc.ca.gov

Steven A. Weissman
Executive Division
RM. 4103
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-5173
saw@cpuc.ca.gov


********* INFORMATION ONLY **********


Marc D. Joseph
Attorney At Law
ADAMS BROADWELL JOSEPH & CARDOZO
651 GATEWAY BOULEVARD, SUITE 900
SOUTH SAN FRANCISCO CA 94080
(650) 589-1660
mdjoseph@adamsbroadwell.com


Michael Alcantar
Attorney At Law
ALCANTAR & KAHL LLP
1300 SW FIFTH AVENUE, SUITE 1750
PORTLAND OR 97201
(503) 402-9900
mpa@a-klaw.com

For: Cogeneration Association of CA

Evelyn Kahl
Attorney At Law
ALCANTAR & KAHL, LLP
120 MONTGOMERY STREET, SUITE 2200
SAN FRANCISCO CA 94104
(415) 421-4143
ek@a-klaw.com

For: Energy Producers & Users Coalition

James H. Caldwell Jr.
Policy Director
AMERICAN WIND ENERGY ASSOCIATION
122 C STREET NW. STE. 300
WASHINGTON DC 20001
(202) 383-2517
jcaldwell@awea.org


Robert E. Anderson
APS ENERGY SERVICES
1500 FIRST AVENUE
ROCHESTER MN 55906
(507) 289-0800
bob_anderson@apses.com









Richard D. Ely
ASSOCIATES, INC.
3239 RAMOS CIRCLE
SACRAMENTO CA 95827-2501
(916) 363-8383
dick@adm-energy.com


Lon W. House
Energy Advisor
ASSOCIATION OF CALIFORNIA WATER AGENCIES
4901 FLYING C ROAD
CAMERON PARK CA 95682-9615
(530) 676-8956
lwhouse@innercite.com


Carolyn A. Baker
Attorney At Law
7456 DELTAWIND DRIVE
SACRAMENTO CA 95831
(916) 399-8611
cabaker906@aol.com


Catherine E. Yap
BARKOVICH & YAP, INC.
PO BOX 11031
OAKLAND CA 94611
(510) 450-1270
ceyap@earthlink.net


Barbara R. Barkovich
BARKOVICH AND YAP, INC.
31 EUCALYPTUS LANE
SAN RAFAEL CA 94901
(415) 457-5537
brbarkovich@earthlink.net

For: Barkovich and Yap, Inc.

Terry J. Houlihan
Attorney At Law
BINGHAM MCCUTCHEN LLP
3 EMBARCADERO CENTER, 18TH FLOOR
SAN FRANCISCO CA 94111
(415) 393-2000
thoulihan@mdbe.com


Thomas S. Hixson
BINGHAM MCCUTCHEN LLP
THREE EMBARCADERO CENTER
SAN FRANCISCO CA 94111
(415) 393-2000
thixson@mdbe.com

Scott Blaising
Attorney At Law
BRAUN & ASSOCIATES, P.C.
8980 MOONEY ROAD
ELK GROVE CA 95624
(916) 682-9702
blaising@braunlegal.com


Maurice Brubaker
BRUBAKER & ASSOCIATES, INC.
1215 FERN RIDGE PARKWAY, SUITE 208
ST. LOUIS MO 63141
(314) 275-7007
mbrubaker@consultbai.com


Lulu Weinzimer
CALIFORNIA ENERGY MARKETS
517B POTRERO AVENUE
SAN FRANCISCO CA 94110
(415) 552-1764
luluw@newsdata.com


Karen Norene Mills
Attorney At Law
CALIFORNIA FARM BUREAU FEDERATION
2300 RIVER PLAZA DRIVE
SACRAMENTO CA 95833
(916) 561-5655
kmills@cfbf.com


Steven S. Schleimer
CALPINE CORPORATION
4160 DUBLIN BLVD.
DUBLIN CA 94568
(415) 276-6553
sschleimer@calpine.com

For: CALPINE CORPORATION

S. Douglas Levitt
CALWIND RESOURCES, INC.
2659 TOWNSGATE ROAD, SUITE 122
WESTLAKE VILLAGE CA 91361
(805) 496-4337
sdl@calwind.com


Karen Cann
3100 ZINFANDEL DRIVE, SUITE 600
RANCHO CORDOVA CA 95670-6026
(916) 631-4055
kcann@navigantconsulting.com










CASE ADMINISTRARION
2244 WALNUT GROVE AVENUE, ROOM 321
ROSEMEAD CA 91770
(626) 302-1711
case.admin@sce.com

For: Southern Californi Edison Company

Rachel Mcmahon
Policy Analyst
CEERT
1031 LEAVENWORTH, 3
SAN FRANCISCO CA 94109
(415) 202-0866
rachel@ceert.org


Joseph P. Como
Deputy City Attorney
CITY AND COUNTY OF SAN FRANCISCO
CITY HALL
1 DR. CARLTON B. GOODLETT PLACE
SAN FRANCISCO CA 94102-4682
(415) 554-4637
joe_como@ci.sf.ca.us


Pamela M. Durgin
CITY AND COUNTY OF SAN FRANCISCO
PUC
1155 MARKET STREET, 4TH FLOOR
SAN FRANCISCO CA 94102
(415) 554-2469
pdurgin@puc.sf.ca.us


Janis Lehman
Principal Integrated Resource Planner
CITY OF ANAHEIM
201 S. ANAHEIM BLVD., SUITE 1101
ANAHEIM CA 92805
(714) 777-9006

Bruno Jeider
CITY OF BURBANK
164 WEST MAGNOLIA BOULEVARD
BURBANK CA 91502
(818) 238-3651
bjeider@ci.burbank.ca.us


Steven G. Lins
CITY OF GLENDALE
OFFICE OF THE CITY ATTORNEY
613 EAST BROADWAY, SUITE 220
GLENDALE CA 91206-4394
(818) 548-2080
slins@ci.glendale.ca.us

Eric Klinkner
CITY OF PASADENA
150 LOS ROBLES AVENUE, SUITE 200
PASADENA CA 91101-2437
(626) 744-4478
eklinkner@ci.pasadena.ca.us


Jack Wood
Trustee, Managing Company, Llc
CLEARWOOD ELECTRIC COMPANY, LLC
21859 ANGELI PLACE
GRASS VALLEY CA 95949
(530) 269-0828
jackwood@gv.net


Virginia Jarrow
HARVEY LARSEN
CONSUMERS COALITION OF CALIFORNIA
PO BOX 5276
TORRANCE CA 90510
(310) 316-3346

Maryanne Mccormick
CSBRT/CSBA
954 CAROL LANE
LAFAYETTE CA 94549
mmcsba@yahoo.com


V. John White
CTR FOR ENERGY EFFNCY & RENEWABLE TECH
1100 - 11TH STREET, SUITE 311
SACRAMENTO CA 95184
(916) 442-7785
vjw@cleanpower.org


David Kates
DAVID MARK & COMPANY
3510 UNOCAL PLACE, SUITE 200
SANTA ROSA CA 95403
(707) 570-1866
dkates@sonic.net


Jeffrey P. Gray
DAVIS WRIGHT TREMAINE LLP
ONE EMBARCADERO STREET, SUITE 600
SAN FRANCISCO CA 94111
(415) 276-6599
jeffgray@dwt.com


Norman J. Furuta
Attorney At Law
DEPARTMENT OF THE NAVY
2001 JUNIPERO SERRA BLVD., SUITE 600
DALY CITY CA 94014-3890
(650) 746-7312
FurutaNJ@efawest.navfac.navy.mil

For: The Federal Executive Agencies



Melanie Gillette
DUKE ENERGY NORTH AMERICA
980 NINTH STREET, SUITE 1540
SACRAMENTO CA 95814
(916) 319-4620
mlgillette@duke-energy.com

Joseph M. Paul
DYNEGY MARKETING & TRADE
5976 WEST LAS POSITAS BLVD., STE. 200
PLEASANTON CA 94588
(925) 469-2355
joe.paul@dynegy.com


Gregory T. Blue
Regulatory Affairs Manager
DYNEGY MARKETING AND TRADE
5976 W. LAS POSITAS BOULEVARD
PLEASANTON CA 94588
gtbl@dynegy.com


Douglas K. Kerner
Attorney At Law
ELLISON, SCHNEIDER & HARRIS
2015 H STREET
SACRAMENTO CA 95814
(916) 447-2166
dkk@eslawfirm.com

For: Independent Energy Producers Association

Diane I. Fellman
Attorney At Law
ENERGY LAW GROUP LLP
1999 HARRISON STREET, 27TH FLOOR
OAKLAND CA 94612
(415) 703-6000
difellman@energy-law-group.com


Regina M. Deangelis
Attorney At Law
ENERGY LAW GROUP LLP
1999 HARRISON STREET, SUITE 2700
OAKLAND CA 94612
(415) 874-4354
rdeangelis@energy-law-group.com


Carolyn Kehrein
ENERGY MANAGEMENT SERVICES
1505 DUNLAP COURT
DIXON CA 95620-4208
(707) 678-9506
cmkehrein@ems-ca.com

Kevin Simonsen
ENERGY MANAGEMENT SERVICES
646 EAST THIRD STREET
DURANGO CO 81301
(970) 259-1748
kjsimonsen@ems-ca.com

Janis C. Pepper
ENERTRON CONSULTANTS
418 BENVENUE AVENUE
LOS ALTOS CA 94024
(650) 949-5719
pepper@enertroncons.com

For: ENERTRON CONSULTANTS

Robert T. Boyd
ENRON WIND CORP.
444 SOUTH FLOWER STREET, SUITE 4545
LOS ANGELES CA 94105
(213) 452-5103
hap.boyd@enron.com


Jeffrey S. Ghilardi
ENRON WIND CORPORATION
13000 JAMESON ROAD
TEHACHAPI CA 93561
(661) 823-6813
jeff.ghilardi@enron.com


Kelly Lloyd
ENXCO INC.
PO BOX 581043
N. PALM SPRINGS CA 92258
kellyl@enxco.com


Steven Hammond
FORESIGHT ENERGY COMPANY
692 HAIGHT STREET, STE. B
SAN FRANCISCO CA 94117
(415) 522-1101
shammond@foresightenergy.com


Renee Guild
2481 PORTERFIELD COURT
MOUNTIAN VIEW CA 94040
GuildRenee@aol.com


John Galloway
Energy Division
AREA 4-A
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-2565
jhg@cpuc.ca.gov




Craig Castagnoli
HENWOOD ENERGY SERVICES
2379 GATEWAY OAK DRIVE, SUITE 100
SACRAMENTO CA 95833
(916) 569-0985
ccastagnoli@henwoodenergy.com


Orlando Foote, Esq.
HORTON, KNOX, CARTER & FOOTE
895 BROADWAY
EL CENTRO CA 92243-2341
John Steffen
IMPERIAL IRRIGATION DISTRICT
333 EAST BARIONI BOULEVARD
IMPERIAL CA 92251
(760) 339-9224
jsteffen@iid.com


Robin J. Walther
INDEPENDENT CONSULTANT
160 FOREST LANE
MENLO PARK CA 94025
(650) 330-0717
rwalther@pacbell.net


Steven Kelly
INDEPENDENT ENERGY PRODUCERS ASSN
1215 K STREET SUITE 900
SACRAMENTO CA 95814-3947
(916) 448-9499
iep@iepa.com


Gayatri Schilberg
JBS ENERGY
311 D STREET, SUITE A
WEST SACRAMENTO CA 95605
(916) 372-0534
gayatri@jbsenergy.com


Dan Peaco
LA CAPRA ASSOCIATES INC.
333 WASHINGTON ST. STE. 855
BOSTON MA 02108
(617) 557-9100
dpeaco@lacapra.com

For: LA CAPRA ASSOCIATES INC.

Mark Bolinger
LAWRENCE BERKELEY NATIONAL LABORATORY
MS 90-4000
ONCE CYCLOTRON ROAD
BERKELEY CA 94720
(510) 495-2881
MABolinger@lbl.gov

Karen Lindh
LINDH & ASSOCIATES
7909 WALERGA ROAD, ROOM 112, PMB 119
ANTELOPE CA 95843
(916) 729-1562
karen@klindh.com

For: California Manufactures & Technology Association




Robert Pettinato
LOS ANGELES DEPARTMENT OF POWER & WATER
ENERGY CONTROL CENTER
PO BOX 51111, ROOM 1148
LOS ANGELES CA 90051-0100
(818) 771-6715
rpetti@ladwp.com


John W. Leslie
Attorney At Law
LUCE FORWARD HAMILTON & SCRIPPS, LLP
600 WEST BROADWAY, SUITE 2600
SAN DIEGO CA 92101-3391
(619) 699-2536
jleslie@luce.com


Richard Mccann
M.CUBED
2655 PORTAGE BAY ROAD, SUITE 3
DAVIS CA 95616
(530) 757-6363
rmccann@cal.net


Jack Mcnamara
Attorney At Law
MACK ENERGY COMPANY
PO BOX 1380
AGOURA HILLS CA 91376-1380
(818) 865-8515
jackmack@suesec.com


Kevin R. Mcspadden
Attorney At Law
MILBANK TWEED HADLEY & MCCLOY
601 SOUTH FIGUEROA, 30TH FLOOR
LOS ANGELES CA 90017
(213) 892-4563
kmcspadden@milbank.com


Robert B. Weisenmiller
Phd
MRW & ASSOCIATES, INC.
1999 HARRISON STREET, STE 1440
OAKLAND CA 94612-3517
(510) 834-1999
mrw@mrwassoc.com


Stephen St. Marie
NAVIGANT CONSULTING, INC.
3100 ZINFANDEL DRIVE, SUITE 600
RANCHO CORDOVA CA 95670-6026
(916) 631-3200
sstmarie@navigantconsulting.com



Kay Davoodi
NAVY RATE INTERVENTION OFFICE
WASHINGTON NAVY YARD
1314 HARWOOD STREET SE
WASHINGTON DC 20374-5018
(202) 685-0130
DavoodiKR@efaches.navfac.navy.mil


Hal Romanowitz
OAK CREEK ENERGY
14633 WILLOW SPRINGS ROAD
MOJAVE CA 93501
(661) 822-6853
rwitz@compuserve.com


Jonathan M. Jacobs
PA CONSULTING SERVICES INC
75 NOVA DRIVE
PIEDMONT CA 94610
jon.jacobs@paconsulting.com


Valerie Winn
PACIFIC GAS & ELECTRIC COMPANY
PO BOX 770000, B9A
SAN FRANCISCO CA 94177-0001
(415) 973-3839
vjw3@pge.com


Cecilia Montana
PACIFIC GAS AND ELECTRIC COMPANY
77 BEALE STREET
SAN FRANCISCO CA 94105
(415) 973-1595
cfm3@pge.com


Bruce H. Hellebuyck
PACIFICORP
LLOYD CENTER TOWER
825 NE MULTNOMAH, SUITE 800
PORTLAND OR 97232
(503) 813-6041



Bob Hoffman
PAUL,HASTINGS,JANOFSKY AND WALKER
1127 11TH STREET, STE. 905
SACRAMENTO CA 95814
(916) 552-2881
bobhoffman@paulhastings.com

George A. Perrault
PERRAULT CONSULTING
1723 FORD AVENUE
REDONDO BEACH CA 90278
(310) 379-0901
perrault@perrcon.net


Eric Eisenman
PG&E NATIONAL ENERGY GROUP
345 CALIFORNIA STREET.
SAN FRANCISCO CA 94104
(415) 288-5630
eric.eisenman@neg.pge.com


Stanley I. Anderson
POWER VALUE INCORPORATED
964 MOJAVE CT
WALNUT CREEK CA 94598
(925) 938-8735
sia2@pwrval.com


Hamid Hazerooni
R. W. BECK, INC.
1851 HERITAGE LANE 200
SACRAMENTO CA 95815
(916) 614-8242
hkazerooni@rwbeck.com

For: R.W. BECK, INC.

Peter Bray
RAY AND ASSOCIATES
SUITE 2
3566 17TH STREET
SAN FRANCISCO CA 94110-1093
(415) 437-1633
petertbray@yahoo.com


Jean Pierre Batmale
REALENERGY, INC.
5957 VARIEL AVE.
WOODLAND HIILS CA 91367
(818) 610-2300
jpbatmale@realenergy.com


Kirby Bosley
RELIANT ENERGY
1050 17TH STREET, SUITE 1450
DENVER CO 80265-1450
(303) 620-9999
kbosley@reliantenergy.com


Kurt W. Bilas
Senior Counsel
RELIANT ENERGY POWER GENERATIONS, INC.
801 PENNSYLVANIA AVE., N.W. SUITE 620
WASHINGTON DC 20004
kbilas@reliant.com



Rob Roth
SACRAMENTO MUNICIPAL UTILITY DISTRICT
6201 S STREET MS 75
SACRAMENTO CA 95817
(916) 732-6131
rroth@smud.org


Joseph R. Kloberdanz
SAN DIEGO GAS & ELECTRIC COMPANY
8315 CENTURY PARK COURT
SAN DIEGO CA 92123
(858) 654-1771
jkloberdanz@semprautilities.com


Kurt Kammerer
SAN DIEGO REGIONAL ENERGY OFFICE
401 B STREET, SUITE 800
SAN DIEGO CA 92101
(619) 595-5630
kkam@sdenergy.org


Tracy Saville
300 CAPITOL MALL STE. 120
SACRAMENTO CA 95814
(916) 325-2500

Michael Rochman
SCHOOL PROJECT UTILITY RATE REDUCTION
1430 WILLOW PASS ROAD, SUITE 240
CONCORD CA 94520
(925) 743-1292
rochmanm@spurr.org


Bruce J. Williams
Manager, Regulatory Affairs Case Mgmt
SEMPRA ENERGY
101 ASH STREET, HQ14A
SAN DIEGO CA 92101
(619) 696-4488
bwilliams@sempra.com


Sharon L. Cohen
Attorney At Law
SEMPRA ENERGY
101 ASH STREET, HQ12
SAN DIEGO CA 92101
(619) 696-4355
scohen@sempra.com

Douglas Mitchell
SEMPRA ENERGY GLOBAL ENTERPRISES
101 ASH STREET, HQ-15G
SAN DIEGO CA 92101
dmitchell@sempraglobal.com




Robert Ellery
Director Of Energy Resources
SIERRA PACIFIC INDUSTRIES
19794 RIVERSIDE AVE.
ANDERSON CA 96007
(530) 378-8179
bellery@spi-ind.com


Andrew Ulmer
Attorney At Law
SIMPSON PARTNERS LLP
900 FRONT STREET, THIRD FLOOR
SAN FRANCISCO CA 94111
(415) 773-1791
andrew@simpsonpartners.com


Leon Bass
Attorney At Law
SOUHTERN CALIFORNIA EDISON COMPANY
2244 WALNUT GROVE AVENUE, SUITE 353
ROSEMEAD CA 91770
(626) 302-6897
leon.bass@sce.com


Bruce Foster
Regulatory Affairs
SOUTHERN CALIFORNIA EDISON COMPANY
601 VAN NESS AVENUE, SUITE 2040
SAN FRANCISCO CA 94102
(415) 775-1856
fosterbc@sce.com

For: SOUTHERN CALIFORNIA EDISON

Bob Finklestein
Staff Attorney
THE UTILITY REFORM NETWORK
711 VAN NESS AVE., STE. 350
SAN FRANCISCO CA 94101
(415) 929-8876
bfinkelstein@turn.org


Alex A. Goldberg, Esq.
THE WILLIAMS COMPANIES, INC.
ONE WILLIAMS CENTER
SUITE 4100, MS41-3
TUSLA OK 74172
Alex.Goldberg@williams.com




Michael Shames
Attorney At Law
UTILITY CONSUMERS' ACTION NETWORK
3100 FIFTH AVENUE, SUITE B
SAN DIEGO CA 92103
(619) 696-6966
mshames@ucan.org




Patricia Vanmidde
Consultant
22006 N 55TH ST.
PHOENIX AZ 85054
(480) 515-2849
pvanmidde@earthlink.net


Mark Albert
VULCAN POWER COMPANY
1183 NW WALL STREET, STE. G
BEND OR 97701
(541) 317-1984
malbert@vulcanpower.com


Enoch H. Chang
WHITE & CASE LLP
THREE EMBARCADERO CENTER, SUITE 2200
SAN FRANCISCO CA 94111
(415) 544-1100
echang@whitecase.com

For: California Cogeneration Council

Roger T. Pelote
WILLIAMS ENERGY SERVICES
12731 CALIFA STREET
VALLEY VILLAGE CA 91602
(818) 761-5954
Roger.Pelote@williams.com


Tim Muller
Legal Department
WILLIAMS ENERGY SERVICES
ONE WILLIAMS CENTER, MD 41-3
TULSA OK 74172
(918) 573-1480
tim.muller@williams.com

For: WILLIAMS ENERGY SERVICES

Bradford Wetstone
Energy Division
AREA 4-A
505 VAN NESS AVE
San Francisco CA 94102
(415) 703-2826
bxw@cpuc.ca.gov

Julie Blunden
Vice President
XENERGY INC.
492 9TH ST., STE. 220
OAKLAND CA 94607
(510) 891-0446
jblunden@xenergy.com


   

Appendix B

Adopted Master Data Request for Monthly Advice Letters

The utilities shall file each month's transactions that conform to the approved procurement plan by advice letter. The Advice Letters must contain the following information:

(END OF APPENDIX B)

APPENDIX C

 

Procurement Contract Review Process

 

 

Day

Days to Complete Task

Tasks

   

Days in advance of Application Filing Date

No Limit

Utility internally develops risk management plans for transitional procurement. Utility also meets with Procurement Review Group (PRG) recommended in the Joint Principles. This group would meet prior to the application being filed and should be convened early on to assess any proposed RFP process before it is implemented. The PRG would meet again to assess the resulting bids, the winning procurement contracts, and reasonableness criteria with each respondent utility. The group would be open to parties designated under our Protective Order to review confidential information and would include representatives of the Commission's Energy Division and ORA as ex officio members.

   

0

0

Edison, PG&E, or SDG&E file a complete application that conforms to the quantities, products, terms and conditions we discuss earlier for transitional procurement. The application should demonstrate it meets our standard for approval by a showing that entering into the contract(s) should result in favorable and stable rates for ratepayers relative to alternative options. An application may contain all winning contracts from a single RFP solicitation. The application shall include information responsive to the adopted master data request.

   

30

30

Protests due within 30 days of Application filing.

   

35

5

Replies to protests due within five business days of protest. (See rules of pp

   

40

1

A workshop will be held approximately 40 days after the application is filed.

   

41+

As required

After the workshop, the assigned administrative law judge (ALJ), in consultation with the assigned Commissioner, shall issue a ruling designating whether there are issues of substantial controversy or importance to require the scheduling of hearings. The ruling shall also state whether the ALJ intends to prepare a draft decision which meets the criteria set forth in Public Utilities Code Section 311(g)(2) of being an uncontested matter in which the decision grants the relief requested, a criteria that allows the 30 day public review period to be reduced or waived.

   

41-59

Less than 20

If the ruling states that the ALJ intends to prepare a draft decision which meets the requirements of Section 311(g)(2), the decision when drafted will be placed on the next Commission agenda.

   

60+

30+

If the ruling states that the application does not meet the criteria of Section 311(g)(2), a draft decision will be served on parties and subject to at least 30 days public review and comment prior to a PUC vote. If the ruling states that there are issues of substantial controversy or importance to require the scheduling of hearings, such hearings will be held and a proposed decision served on parties and subject to at least 30 days review and comment prior to a PUC vote.

   

Note: Approval of the contracts will also contain a decision on reasonableness, with prudency of contract administration being at issue over the life of the contract. During the transitional period, if the Commission rejects a proposed contract, it will not designate any alternative procurement choices.

   

(END OF APPENDIX C)

APPENDIX D

Page 1

APPENDIX D

Page 2

APPENDIX D

Page 3

END OF APPENDIX D

18 The Commission adopted PECA in the Post-Transition Period Electric Ratemaking (PTER) decisions D.99-10-057 and D.00-06-034. 19 SDG&E has proposed in Application (A.) 02-01-015 to establish Utility Retained Generation Recovery Account (URGRA) required by D.01-12-015 for a permanent cost recovery mechanism. (SDG&E's Supplemental Testimony Exhibit 70) 20 Resolution E-3765, dated January 23, 2002 established the SRBA after Edison filed Advice Letter 1586-E, dated November 14, 2001 to implement the Agreement provisions. 21 "Settlement Rates" is defined in the Agreement approved by the United States District Court on October 5,2001 (Exhibit 10,p. 9, ¶ (w) and for "Recoverable Costs" see p. 8). 22 ECAC where fuel and purchased power costs used to be tracked prior to the electric deregulation. 23 TURN would still want O&M and capital costs to be set in the general rate case (GRC) but tracked with fuel and procurement costs for ease of comparison between costs of different resources with different ownership possibly in sub-accounts of the balancing account. 24 The cost items proposed by PG&E, SDG&E and Edison for their procurement balancing accounts shown below are currently recorded in various Commission authorized balancing accounts that track energy related costs and their fixed costs. 25 PG&E proposes to establish PECA rate based on monthly forecast of these costs similar to core gas procurement rate approved in D.97-10 065 26 In A.02-01-015, SDG&E has requested a new Electric Energy Commodity Charge (EECC) or rate, based on majority of those costs excluded from the PCAM. SDG&E requests two annual adjustments to EECC rate, a self adjust "balancing rate" and "energy rate adjustment component" that reflects the difference between the annual succeeding forecast and prior forecast of costs. Id. 27 Edison currently records these costs in the Power Purchased Balancing Account (PPBA), ISO Balancing account, Net Short Procurement Cost Account, and Native Load Balancing Account (fuel costs). These are part of the SRBA that calculates monthly "Surplus" allowed by the Agreement and being applied to the PROACT. Edison further proposes to change the ratemaking for these costs by establishing a Fuel and Purchased Power (F&PP) balancing account and an F&PP rate, based on annual forecast of these costs after December 2003 or the "Repayment Period." 28 Reliability Must- Run (RMR) revenues from plants required by the ISO for reliability. 29 SDG&E proposed that this rate be a part of its total EECC rate. It plans to modify its EECC tariffs at the time the initial PCAM rate is established by advice letter. The PECA rate will consist of an energy rate and a balancing rate. Each will adjust monthly. 30 Proposed Section 454.5 (d)(3) states in part that until 2006, the Commission shall ensure that any undercollection or overcollection in the power procurement balancing account does not exceed 5 percent of the electric corporation's actual recorded generation revenues for the prior calendar year excluding revenues collected for the DWR. 31 RCTA tracks the difference between Stabilized DWR charges and the sum of Edison's Net Short Procurement Costs and current DWR charges. 32 Edison is proposing that the filing be effective 60 days after the advice letter is filed. 33 Edison plans to increase or decrease Settlement Rates effective January 1, 2003 consistent with the language in the Agreement and the outcome of forecast revenue requirements adopted in this proceeding and the concurrent DWR revenue requirement proceeding. 34 The rate revenues and actual costs are tracked in the F&PP balancing account. Edison proposed that the balance in the account be trued up annually but its review takes place semi-annually by filing an application. Edison requests a similar rate adjustment trigger mechanism during the Repayment Period to apply after Settlement Rates termination. 35 Edison requests the Commission to rule in this proceeding where and when the entries in its SRBA and PROACT should be reviewed. We deny Edison's request without prejudice. Edison is free to choose an appropriate vehicle after the recovery of its PROACT for the Commission to review these entries. 36 For PG&E the total amount for owning and operating Diablo Canyon (DC) was included in its ECAC in D.88-03-067. 37 For 2003, Edison and SDG&E should breakout the full ICIP rate into fuel and non-fuel so that fuel related expense is separated from non-fuel in the ERRA and tracked against actual recorded for accounting purposes. 38 See Appendix D. 39 By the time rates are adjusted under Edison proposal the ERRA balance may exceed the five percent trigger in violation of proposed AB 57. The minimum balance approach allows for processing time and insures compliance with the proposed law. 40 In D.02-04-016 issued April 4, 2002, the Commission directed that Edison's and SDG&E's purchased power costs and PG&E's nuclear generation costs should be subject to reasonableness review. (See Conclusions of Law 15, 25, and 28.)

Previous PageTop Of PageGo To First Page