| Word Document PDF Document |
COM/SK1/cvm* ALTERNATE DRAFT Agenda ID # 4235
Alternate to Agenda ID # 3929
Ratesetting
Item 28a
1/27/05
ALTERNATE OF COMMISSIONER KENNEDY (Mailed 1/13/2005)
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of Southern California Edison Company (U 338-E) For Approval of its 2004 Revenue Requirement and Related Estimates Under the Energy Resource Recovery Account (ERRA); And For a Commission Finding that its Procurement-Related and Other Operations were Reasonable for the Record Period September 1, 2001 Through June 30, 2003. |
Application 03-10-022 (Filed October 3, 2003) |
Daniel W. Douglass, by Gregory S.G. Klatt, Attorney at Law,
Alcantar & Kahl LLP, by Nora Sheriff, Attorney at Law,
and Robert B. Keeler, Attorney at Law, for
Southern California Edison Company, applicant.
William H. Booth, Attorney at Law, interested party.
Regina DeAngelis, for Office of Ratepayer Advocates, protestant.
.
OPINION RESOLVING THE REASONABLENESS PHASE OF
SOUTHERN CALIFORNIA EDISON COMPANY'S
ENERGY RESOURCE RECOVERY ACCOUNT APPLICATION
3. SCE's Showing 33
5. Scope of Review for Least Cost Dispatch under SOC 4 44
6. Standard of Review for Least Cost Dispatch under SOC 4 1010
7. Forum for Review of Spot Market Transactions 1717
8. Other Least Cost Dispatch Issues 1818
9. Contract Administration and Costs 2121
10. Cogeneration QFs and Renewable Contract Administration and Costs 2323
12. Audit Issues 2626
12.1. CDWR Settlement Payment Authorization 2626
12.2. ISO Expense Adjustment 2828
14. Confidential Information 3333
15. Comments on Proposed Decision 3434
16. Comments on the Alternate Decision 3535
17. Assignment of Proceeding 3535
18. Findings of Fact 3535
OPINION RESOLVING THE REASONABLENESS PHASE OF
SOUTHERN CALIFORNIA EDISON COMPANY'S
ENERGY RESOURCE RECOVERY ACCOUNT APPLICATION
This decision adopts a joint Southern California Edison Company (SCE) and Office of Ratepayer Advocates (ORA) recommendation to reduce the Energy Resource Recovery Account (ERRA) by a net amount of $3,574,000 to reconcile certain audit issues. In all other respects, the decision finds SCE's procurement related and other operations were reasonable for the record period September 1, 2001 through June 30, 2003.
The scope of least-cost dispatch review in the ERRA is defined to include SCE's decisions to dispatch the resources under its control in the daily, hourly and real-time markets. The standard of review for least-cost dispatch is compliance with Standard of Conduct #4 (SOC 4), which is an element of SCE's procurement plan.
SCE and ORA are ordered to develop and implement a master data request process to be used in future SCE ERRA filings.