Appendices

Appendix A: How the Transmission/Distribution System Operates

Appendix B: Methodology / Limitations of this Report

Appendix C: Constraint Summaries

Section 1 - Transmission Constraints on PG&E's System

Section 2 - Transmission Constraints on SCE's System

Section 3 - Transmission Constraints on SDG&E's System

Section 4 - Economic Constraints Under the Control of The California ISO

Appendix D: Project Summaries

Appendix E: Electrical Glossary

Appendix A

HOW THE TRANSMISSION/DISTRIBUTION SYSTEM OPERATES

Appendix B

METHODOLOGY / LIMITATIONS OF THIS REPORT

Because this report depends on deterministic planning studies, its conclusions are based on a number of assumptions:

· Demand forecasts are based on California Energy Commission demand forecasts and current trends. An unexpected slowdown in demand due to increased prices or a severe economic recession would reduce the need for many of the projects identified here.

· Weather - the ISO and utility studies assume 1-in-10 year or 1-in-5 year temperatures (see Appendix A). Therefore, there is a 10-20 percent chance that any particular year will be hotter than these studies assume. Because the system is generally designed conservatively, utilities will be able to squeeze by most of the time even if temperatures are higher. However, in near-record or record heat, outages may occur, particularly if unusual numbers of lines and generators are out of service at those times (such as occurred on June 14 in the Bay Area).

Appendix C

CONSTRAINT SUMMARIES

Section 1 - TRANSMISSION CONSTRAINTS ON PG&E's SYSTEM

19 California and the rest of the Western Interconnection operate at 60 cycles per second (as does the rest of the US). 20 Turning some generators up at one end of a power line and turning others down at the other end (see below). 21 Transformers work because changes in electric flow in one coil of the transformer induce changes in magnetic fields, which in turn induce changes in electric flow in the other coil of the transformer. Steady flows do not induce such changes. Thus a changing , alternating current is required. 22 Electrical voltage is analogous to the "pressure" in a water pipe. 23 Or when the object is to link two AC Systems and have them remain separate. Direct Current (DC) can carry power in only one direction between two specific points (that is, they cannot connect with loads or generators along the way). Further, they require expensive equipment at both termini. They are therefore economic only for very large power flows over long distances. Two such lines connect California to other states; one from Pacific Northwest, the other from the Intermountain Power Project in Utah. Both lines terminate near Los Angeles 24 Some "weak" power lines run between the different interconnections. Some are DC lines (see the previous footnote) which allow the systems to remain electrically separate since power flows can be controlled. Others are low-voltage, low-power AC lines. 25 For example, equations predicting the need for reactive power use the square root of -1, also called "i." That number does not exist in normal arithmetic, since there is no number that can be squared to yield a negative result. Mathematicians call "i" an "imaginary" number. 26 That is, they must operate at the same frequency. 27 In most power plants, turbines (driven by water, steam, or combusted gas) turn a drive shaft that turns the electric generator itself. The speed of the rotor determines the frequency of generated power. If the system frequency changes suddenly, the magnetic field in the generator will change the speed of the generator and drive shaft, while the turbines tend to stay at the same speed as before, due to mechanical inertia. This conflict can literally tear turbine blades apart. 28 Condensers and capacitors (in the simplest form, two parallel electrical plates separated by a non conductor) can, under the right circumstances, correct the divergence of frequency and voltage caused by coils (such as those in large motors). They are therefore a source of "reactive power." 29 Or more technically, impedance. 30 Due to heavy rains and hot weather, trees along transmission lines had grown unexpectedly high. Heavy power flows and high temperatures also caused transmission lines to sag enough to contact trees and create an electrical "short." Protective equipment at either end of the lines picked up the power surge, and shut the lines down automatically. 31 The utility chooses generation with the lowest marginal cost, in terms of price, operational cost, and/or the cost of alternatives. This calculation can be complicated; for example, while hydroelectric power generally has the lowest operating costs, its output can be adjusted very quickly and finely, and is often saved to meet peak loads. Because of this complexity, utilities typically use computers to dispatch generation. The ISO took over this function from PG&E, SDG&E, and Southern California Edison when it began operations in 1998. 32 When many generators are offering power at exactly equal prices, it may be possible to find alternative generation at the same cost. 33 Each scheduling coordinator is responsible for a group of customers, and must find generation to meet those customer's needs. Thus, schedules submitted to the ISO must balance demand and supply. Until recently, the Power Exchange acts as the exclusive scheduling coordinator for the three large distribution utilities, PG&E, SDG&E, and Southern California Edison. 34 California's distribution utilities, for example, offer discounted "interruptible" tariffs to large commercial and industrial customers who agree to curtail usage when power is in short.

35 Wind cools equipment and increases capacity.

36 WSCC is the western affiliate of the North American Electric Reliability Council (NERC). Both organizations were formed in the 1960's after a major blackout affected most of the Northeastern United States. First composed of regulated electric utilities, the organizations have recently expanded their membership to include regulators, marketers, generators, and others; they also plan further changes in their governance structure. Under NERC's general framework, WSCC issue planning and operating criteria for use in the Western Interconnection. All criteria and rules were initially voluntary, with no enforcement system. In the past few years, with encouragement from the Federal Energy Regulatory Commission (FERC), WSCC has converted a number of its rules into a "mandatory" program which levies (arguably nominal) fee on violators; provided those violators have signed up for the program. 37 The system is assumed to be operating normally, when one or two (and sometimes more) contingencies occur. Thus, a single contingency is called "N-1" for "Normal minus one"; a double, simultaneous contingency is called "N-2"; etc. WSCC and ISO standards determine which contingencies utilities must model. 38 For example, on June 14, 2000, record high temperatures caused record demand in the Bay Area. In response to low voltages in the Bay Area, the ISO had to institute rotating outages to reduce Bay Area electricity demand by about 1 percent. 39 In practice, WSCC grants exceptions where project costs clearly exceed benefits. In some cases, WSSC allows more minor modifications (which, for example, reduce the probability that a problem will occur), or approves "remedial action schemes," generally automated equipment which drops load in response to the problem. 40 By CPUC order, California utilities survey customers who are asked one of three questions: 41 In practice, WSCC grants exceptions where project costs seem likely to exceed benefits.

Previous PageNext PageGo To First Page