BACKGROUND

SCE's Air Conditioning Cycling Program (also known as the Summer Discount Plan) is part of SCE's three-year (2006-2008) demand response budget application which the Commission approved recently in D.06-03-0241 in A. 05-06-008.

The Air Conditioner Cycling Program (AC Cycling Program) is available for individually-metered residential, commercial and industrial customers with central air conditioning, where the air conditioner's electrical load is subject to temporary disconnection through automatic load control devices. Currently, there are two AC Cycling Program options in which customers may enroll: the Base program and the Enhanced program. The Base program is limited to 15 events during the summer months, with a maximum duration of six hours per event, for a total of 90 hours of interruption. The Enhanced program has an unlimited number of events, for a maximum of 720 hours of interruption during the summer months. An event may be called when the CAISO requests load reductions during the summer or when SCE calls a local event. The incentive credits are based on the installed air conditioner tonnage and the participating customer's elected cycling strategy, which currently includes 50%, 67%, and 100% for residential customers and 30%, 40%, 50%, and 100% for commercial and industrial customers. Customers enrolled in the Base program receive an average of $100 per summer, and those enrolled in the Enhanced program received an average of $200 per summer. 2

In the August 15, 2006 Assigned Commissioner's Ruling3 Addressing Electric Reliability Needs in Southern California for Summer 2007 ("Electric Reliability ACR"), Commissioner President Peevey directed SCE to target an additional 300 megawatts (MW) of AC Cycling program capacity for summer 2007. This ruling is in response to the growth in electricity demand throughout the state and the July 2006 heat storm which had exposed certain vulnerabilities in the electric generation and transmission infrastructure. To expand the AC Cycling program, the Electric Reliability ACR directed SCE to determine if shifting the existing demand response funds can cover the costs of the additional 300 MWs or if additional funds (incremental to those previously approved in D.06-03-024) are necessary, and to provide this information to the Commission via the process outlined in ACR issued August 9, 2006.

Under the existing AC Cycling program, SCE is authorized to install 60,000 devices each year in order to enroll 84 MW annually over the 2006-2008 program cycle. SCE is currently authorized to spend $51.4 million on AC Cycling during the 2006-2008 program cycle between the amount authorized in D.06-03-024 and in the SCE's 2006 General Rate Case. The $54.1 million funding was expected to be spent over the three year period for a total of 180,000 devices.

Accordingly, SCE filed advice letter 2034-E on August 29, 2006 to request an additional $37.03 million to accelerate and expand AC Cycling program by an additional 300 MW by summer 2007. SCE's strategy to reach the 300 MW by summer 2007 is to accelerate the planned installation of devices by more than one year to July 2007. SCE states it has already installed 16,000 devices (~25MW) in August 2006. In addition, SCE proposes to accelerate the installation of the remaining 136,000 approved devices (equivalent to about 190 MW) by July 2007, which brings the total added MW since July 2006 to 215 MW. To reach the 300 MW goal by summer 2007, SCE needs to install 62,000 more devices that would add another 85 MW.

SCE states that this acceleration and expansion effort will require the following:

In addition, SCE proposes to streamline its program implementation and simplify customers' choices for enrollment by making the following modifications to its AC Cycling program design:

1 The decision adopted an amended settlement which reduced SCE's original budget proposal.

2 The average incentive is based on a customer with a 4.5 ton air conditioner selecting the 100% cycling option.

3 R.05-12-013 and R.06-02-013.

Top Of Page