Rate Path

Line 400/2

Line 401

Line 300

Gathering

Total

Redwood Vintage

615.5

     

615.5

Redwood

405.6

870.1

   

1,281.1

Baja

   

1,101.3

 

1,101.3

Silverado

     

197.4

197.4

Mission

         

Subtotal

1,021.1

870.1

1,101.3

197.4

3,195.3

G-XF Contracts

 

91.8

     

Total

1,021.1

961.9

1,101.3

197.4

3,195.3


"only because noncore representatives have agreed to it.... Therefore, our finding that the Gas Accord is in the public interest is predicated on the fact that the core retail and core wholesale end users will continue to benefit from low, vintaged rates on Line 400 and will not have to pay for Line 401 costs. We would strongly disfavor any future PG&E request for a full roll-in of Line 401 costs if such roll-in would increase either core or noncore rates (absent an all-party settlement), whether such request occurred before or at the expiration of the Gas Accord." (73 CPUC2d at 782.)


"allowing rolled-in ratemaking could undermine future market tests for new capacity in the gas pipeline industry and perhaps in other industries. To weaken `let the market decide' policies after construction of utility expansions could harm the Commission's credibility. If PG&E is now allowed to roll the cost of unnecessary assets into original system rates, then future market players might be tempted to deter competition by overbuilding new capacity, hoping the Commission will later shift the risks of undersubscription or underutilization back to captive customers. Utilities and their competitors would question the Commission's resolve in enforcing the assignment of risks and costs to the sponsors of new capacity." (73 CPUC2d at 773)


"Second, rolled-in rate treatment for Line 401 and the proposed path-specific unbundling scheme would be inefficient and contrary to incremental ratemaking principles. Loss of economic inefficiency is built into the averaging process because shippers would not face the costs of individual pipeline assets. In A.89-04-033, PG&E promised to insulate original system ratepayers from any risks and costs of Line 401. The Commission confirmed that none of the costs of Line 401 would be allocated to original system ratepayers. When PG&E determined the scale and timing of the expansion project, it took advantage of the Commission's `let the market decide' policy for new pipeline capacity, in exchange for assuming responsibility for associated costs and risks. We are obligated to defend those customer protections vigorously. Only a showing of substantial customer benefits can overcome the allocation of Line 401 costs to customers that do not need or desire Line 401 capacity. Path-specific unbundling would further obscure the incremental nature of Line 401." (73 CPUCd 772-773, footnotes omitted.)


"We are also concerned that the Gas Accord has not provided enough unbundling and that parties may attempt to improperly cite our approval of the Gas Accord as a precedent in favor of rolled-in rates (when our policies continue to be in favor of incremental rates) or that parties will claim that the Gas Accord resolved numerous issue which were never specifically addressed by the Gas Accord. Rather than reject the Gas Accord in light of these concerns, we believe that the much better course is to approve the Gas Accord in light of its improvement over PG&E's present rates, to narrowly interpret the Gas Accord and our order approving the Gas Accord so that it will not limit our ability to further address PG&E's conflicts of interest and unbundling issues, to clarify our policies and various ambiguities in the Gas Accord so that parties will not misinterpret this decision...." (73 CPUC2d 774.)


"Although we are approving the Gas Accord, we remain concerned that the partially rolled-in rates for Line 400 and Line 401 are contrary to our incremental ratemaking principles. PG&E was authorized to build Line 401 based upon its pledge to utilize incremental rates, and PG&E assured us at that time that PG&E's existing customers would not have to pay for Line 401 costs. Approval of partially rolled-in rates for noncore customers is reasonable here, but only because noncore representatives have agreed to it in the Gas Accord, presumably in return for other benefits. Full roll-in of Line 401 costs would increase core rates and would significantly conflict with our policies. However, the Gas Accord does not provide for fully rolled-in rates; it protects core retail and core wholesale ratepayers from the unjustifiable increase in rates which would result from the rolled-in rates. Therefore, our finding that the Gas Accord is in the public interest is predicated on the fact that the core retail and core wholesale customers will continue to benefit from low, vintaged rates on Line 400 and will not have to pay for Line 401 costs. We would strongly disfavor any future PG&E request for full roll-in of Line 401 costs if such roll-in would increase either core or noncore rates (absent an all-party settlement), whether such a request occurred before or at the expiration of the Gas Accord." (73 CPUC2d at 782, original italics.)


"Until further Commission action, we find that the project sponsors are PG&E's shareholders, and it is PG&E's shareholders and Expansion shippers, not the existing ratepayers, that bear the risk of the Expansion Project's failure to recover its revenue requirement. The shift of risk to existing ratepayers may occur, if at all, only if the Commission finds that the Expansion Project's contribution to margin would constitute a financial benefit sufficient to overcome the Project's potential burden of revenue underrecovery. However, we conclusively find that none of the costs of the Expansion Project may be recovered in any non-Expansion Project rate proceeding, advice letter or accounting mechanism." (39 CPUC2d at 81.)


"We note that PG&E has affirmatively stated that it will not seek to recover any Expansion Project costs (other than transportation costs) from its existing ratepayers. Such assurance is also implied from the applicant's intent to collect Expansion costs from only the project sponsors and Expansion shippers. We confirm as a condition of issuance of this CPCN that PG&E's existing ratepayers should not bear any of the cost of the Expansion. This segregation of costs, risk, and benefit is appropriate at this time, particularly since PG&E has not yet executed Firm Transportation Agreements with the Expansion shippers. ... We will revisit this issue in the Expansion Project's first general rate case, when concrete evidence of shipper participation, the Expansion's costs and rates, and the potential contribution to margin will be available. (39 CPUC2d at 120.)

65 This includes being at risk for throughput and revenues on the backbone transmission system. (See 73 CPUC2d at 821, Balancing Account Treatment; Ex. 3 at 14-15.) 66 The capacity sold to SMUD has been excluded from Table 5. 67 The local transmission rate for core retail in 2003 was $ 0.287 per dth. 68 The local transmission rate for core wholesale in 2003 was $ 0.149 per dth. 69 The local transmission rate for noncore in 2003 was $ 0.149 per dth. 70 Unless otherwise stated, all code section references are to the Public Utilities Code. 71 The CDR has historically required cogeneration customers to receive any rate discount granted to a UEG customer. 72 Once this proposal is adopted, PG&E will update the customer class charges to reflect the allocation of Commission fees and franchise fees to all G-EG customer volumes in the first BCAP or true-up rate change. 73 The incremental ratemaking treatment adopted in D.90-12-119 was affirmed in D.92-10-056. (46 CPUC2d 199, 204-205.) 74 On rehearing, the Commission affirmed the use of this incremental ratemaking approach. (D.94-12-058 [58 CPUC2d at 420-421].) 75 We note that the core is not getting a free ride on Line 401. To the extent core customers require service over Line 401, the core pays the associated costs for transporting the gas over Line 401. 76 CAPP's position on the roll-in of costs is set forth in that section. 77 To the extent that the underlying demand forecast is modified, this percentage would change. 78 If CAPP's demand forecast of 2367 is divided by PG&E's denominator of 3195.292, the load factor would be 74.1%. 79 The Line 401 net firm capacity number of 875.463 is derived from using the firm delivery capacity of 1003.606 minus 86.424 for G-XF off-system contracts and 41.719 of SMUD's equity interest in Line 401. (See Ex. 43, p. 10; Ex. 3, Table 14-6.) 80 For example, we could, as suggested by several parties, increase the electric generator demand forecast to reflect the postponement of new combined cycle plants, which should increase gas usage at existing gas-fired plants. This would result in a higher load factor. 81 CAPP's path specific rates would cause the firm Baja usage charge to increase by $0.23 to $0.278 per Dth over 2003 rates, and the firm Redwood usage charge to increase by $0.106 to $0.214 per Dth. 82 The load factors shown in Table 8 (page 2 of 2) of Exhibit 6, the testimony of CCC/Calpine's witness, are slightly higher in four of the five years as compared to the CAPP table. 83 The 70.85% load factor is calculated by adding the additional 79 MDth/d of off-system deliveries to PG&E's demand forecast as shown on Table 14-6 of Exhibit 3, resulting in an adjusted demand forecast of 2263.926 MDth/d. The adjusted demand forecast is then divided by the net firm capacity of 3195.292.

84 One of PG&E's arguments regarding the roll-in of Line 401 is if an alternate pipeline had been built, it is unlikely that as much capacity as Line 401 would have been built because "there was a considerable amount of slack capacity on PG&E's system until mid-2000...." (Ex. 4, p. 3-9.) This statement about slack capacity supports TURN's argument that PG&E faced the risk that the Line 401 would be underutilized, which in turn supports the use of TURN's load factor adjustment to Line 401.

85 The effect of PG&E's local transmission proposal on core wholesale customers was mentioned briefly in Chapter 14 of PG&E's application, where it stated in part that "the core retail local transmission rate will also apply to core wholesale customers because they are provided the same level of reliability." (Ex. 3, p. 14-22.) 86 According to PG&E's Rule 1, Palo Alto's wholesale load is classified as a noncore customer, and not as a core customer. Palo Alto points out that under PG&E's definition of a core customer, the core customer must be physically connected to the local distribution system. None of Palo Alto's core loads are physically connected to PG&E's local distribution system. 87 Palo Alto points out that in PG&E's 1995 BCAP decision, D.95-12-053, and SoCalGas's 2000 BCAP decision, D.00-04-060, the gas transportation rates and revenue requirements for wholesale core customers were not included as part of core rates and revenues. Instead, wholesale core customers' rates and revenues are reflected in noncore rates and revenues. (Ex. 54.) 88 As a wholesale customer, Palo Alto is required to execute a Natural Gas Service Agreement (NGSA). Core customers do not execute an NGSA. Wholesale customers are also required to have meters which are capable of measuring flow on a daily basis. PG&E's core customers are not required to have daily metering. PG&E's Core Procurement Department, and core transport groups, must balance to a forecasted usage. Palo Alto and other wholesale customers do not have to balance to forecasted usage. 89 Palo Alto asserts that PG&E's subsidy argument is wrong. As PG&E acknowledged, in the Gas Accord and continuing in 2003, wholesale customers have paid the local transmission rate for the noncore class and contributed to the revenue requirement for the noncore class. (Ex. 3, p. 14-22; Ex. 4, p. 14-14; RT 1114-1115.) In order for retail core customers to have subsidized wholesale customers, revenue would have to shift from Palo Alto and Coalinga, the only wholesale customers when the Gas Accord was adopted. Exhibits 54 and 55 clearly demonstrate that there was no shifting of local transmission revenue from wholesale or other noncore customers to retail core customers. 90 Palo Alto points out that there are major cost differences between retail core customers and wholesale customers. The average throughput per wholesale customer is much greater than the average retail core throughput per customer. In addition, many of PG&E's retail core customers are connected to distribution feeder mains (DFMs), which are part of PG&E's local transmission system. Wholesale customers, such as Palo Alto, are served by local transmission pipelines that are connected to PG&E's backbone transmission system and no DFMs are required to serve them. (Ex. 1, pp. 2-5; 7 RT 763.) Palo Alto also receives gas at a much higher pressure than retail core customers. Also, the balancing requirements for noncore customers, including wholesale customers, is much stricter than the balancing requirement for core procurement. 91 CCC/Calpine disagree with PG&E's estimate of how much load will be a backbone-only rate. CCC/Calpine estimate that, at most, 199 MDth/d of load might directly connect to the backbone. 92 Although some of this cost shift might be recovered from a stranded cost charge imposed on customers who migrate to a backbone-only rate, none of the parties have developed concrete suggestions for determining how much such a charge should be. 93 PG&E's proposal for a single electric generation class would allocate distribution costs equally to all cogeneration and electric generation end-users. 94 In DGS' opening brief, DGS takes issue with the customer access charge shown in Table 14.1-12 of Exhibit 3. DGS, however, did not present any witnesses or ask any questions of the available witnesses about the development of the customer access charges. The customer access charges, and the expenses which feed into the charges, has been addressed earlier.

Previous PageTop Of PageNext PageGo To First Page