Cogeneration Parity

If PG&E's Utility Electric Generation (UEG) department chooses to participate in the open season, the UEG must submit its request for firm transmission service by July 25, 2001, six days before the close of the open season, and any UEG request will be posted on the Pipe Ranger web site by the next business day, July 26, 2001. Other cogenerators will then have until the close of the open season, July 31, 2001, to match UEG's request if they so choose.