Word Document PDF Document

PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

ENERGY DIVISION RESOLUTION E-3920

RESOLUTION

Resolution E-3920. San Diego Gas and Electric Company (SDG&E) submits a revision to the Transmission Revenue Balancing Account Adjustment (TRBAA) rate. This Resolution approves the rate change proposed by SDG&E pursuant to FERC's approval of this rate.

By SDG&E Advice Letter 1671-E filed on February 25, 2005.

_____________________________________________________________

SUMMARY

SDG&E is revising its electric transmission rates to reflect a slight increase to the Transmission Revenue Balancing Account Adjustment (TRBAA) rate to correct an error discovered in the account balance as of September 30, 2004. This Resolution approves the rate change proposed by SDG&E pursuant to FERC's approval of this rate, subject to refund.

The California Public Utilities Commission (CPUC or Commission) finds that the Advice Letter filing is in accordance with SDG&E's FERC filing on February 17, 2005 in FERC Docket ER05-411-000 for revision to its TRBAA rate. SDG&E corrected an error discovered in the account balance as of September 30, 2004, from which the TRBAA rate is derived. The Commission previously approved the TRBAA rate in Resolution E-3908 on January 17, 2005, for rates effective February 1, 2005.

The Commission finds that the TRBAA revenue requirements and associated rate are just and reasonable, and fully recoverable from SDG&E's applicable customers, subject to refund to the same extent as authorized by the FERC.

SDG&E Advice Letter 1671-E was not protested.

This resolution approves the advice letter.

BACKGROUND

On February 17, 2005, SDG&E filed with the FERC, in FERC Docket No. ER05-411-000, an erratum to the Transmission Revenue Balancing Account Adjustment rate, to be effective as requested in the initial filing in Docket No. ER05-411-000.

On November 5, 2004, SDG&E filed Advice Letter 1636-E to update its Reliability Services (RS), TRBAA, and Transmission Access Charge Balancing Account Adjustment (TACBAA) rates to be effective January 1, 2005, in conformance with SDG&E's Transmission Owner Tariff filed with the FERC. These rates became effective February 1, 2005 as authorized by the CPUC in Resolution E-3908.

Subsequently, SDG&E discovered a slight error in deriving its September 30, 2004 balancing account from which the TRBAA rate is derived. The revised balance ending September 2004 was corrected to -$10.002 million (-$0.00164 per kWh) as compared to the initial filing balance equal to -$10.460 million (-$0.00166 per kWh).

On February 17, 2005, SDG&E filed an erratum to its December 28, 2004 filing with the FERC in Docket No. ER05-411-000. Additionally, SDG&E filed with the CPUC Advice Letter 1671-E to revise the TRBAA rate from -$0.00166 per kWh to -$0.00164 per kWh, effective on a prospective basis upon approval by the Commission.

The difference between the TRBAA rate effective February 1, 2005, as approved by the CPUC in Resolution E-3908 on January 13, 2005, and the effective date of the revised rate will be recovered through SDG&E's December 2005 TRBAA filing with the FERC for rates effective January 1, 2006.

NOTICE

Notice of SDG&E AL 1671-E was made by publication in the Commission's Daily Calendar. SDG&E states that a copy of the Advice Letter was mailed and distributed in accordance with Section III-G of General Order 96-A.

PROTESTS

SDG&E Advice Letter 1671-E was not protested.

DISCUSSION

Energy Division has reviewed SDG&E AL 1671-E. Discussion of the relevant facts that lead to the approval of this advice letter is below.

The revised balance in the TRBAA account as of the end of September 2004 is corrected to $10.002 million as compared to the initial filing balance equal to $10.460 million.

After SDG&E filed its annual update to its RS, TRBAA, and TACBAA rates with the FERC and the CPUC at the end of 2004, SDG&E discovered an error in the TRBAA account for the period ending September 2004, from which the TRBAA rates are derived.

The revised balance is now corrected to $10.002 million as compared to the initial filing balance of $10.460 million.

Because the balance in the TRBAA account acts as a transmission credit to customers, a smaller balance results in a lesser amount being credited to transmission customers.

SDG&E's TRBAA rate would increase from -$0.00166 per kWh, which is the rate currently in effect, to -$0.00164 per kWh.

The revised TRBAA rate applicable to SDG&E's end-use customers is -$0.00164 per kWh. This revision represents an increase of approximately 1.2% from the -$0.00166 per kWh TRBAA rate currently in effect.

The revised rate was developed by combining the TRBAA balance of $10.002 million as of September 30, 2004, the forecast of transmission revenue credits for 2005 of $21.109 million, plus an adjustment for uncollectible account expenses of $0.83 million, for a total TRBAA of $31.194 million, divided by SDG&E's historical gross load, which is 19,079 million kWh for the twelve-month period ending September 30, 2004.

The TRBAA cost of service credit change is a $0.306 million decrease from $31.500 million as initially filed to a corrected total of $31.194 million for end-use transmission customers.

The forecast annualized transmission revenue change resulting from the implementation of the revised TRBAA rate by customer rate group is shown below.

Class

Current

Total Rate

Effective 2/1/05

(¢/kWh)

Proposed

Total Rate

(¢/kWh)

Total

Rate Change

(¢/kWh)

Total

Rate Change

%

         

Residential

14.902

14.903

0.001

0.00%

Small Commercial

16.884

16.886

0.002

0.01%

Med and Large Commercial

11.633

11.635

0.002

0.02%

Agriculture

15.229

15.231

0.002

0.01%

Street Lighting

16.137

16.139

0.002

0.01%

         

System TOTAL

13.537

13.538

0.001

0.01%

Implementing the full TRBAA rate change will not increase residential Tier 1 and Tier 2 rates above Assembly Bill (AB) 1X limitations.

Consistent with D.04-02-057 and AB 1X, total energy charges for residential usage up to 130% of the authorized baseline quantity are limited to levels in effect on February 1, 2001. In the event a rate change would otherwise result in exceeding the AB 1X limitations, the commission authorized SDG&E to establish an account to track revenue under-collections resulting from the AB 1X limit to increases to Tier 1 and Tier 2 charges.

Accordingly, SDG&E made a change to its commodity rates so that the total residential rates for usage up to 130% of baseline remain unchanged. The commodity shortfall resulting from this rate adjustment will be recorded in the AB 1X shortfall sub-account of the Energy Resource Recovery Account (ERRA) for future recovery.

In AL 1671-E, SDG&E requested that the advice letter become effective upon approval by the Commission.

As requested by SDG&E in AL 1671-E, the difference between the TRBAA rate effective February 1, 2005 through the effective date of the revised rate will be recovered through SDG&E's December 2005 TRBAA filing with the FERC for rates effective January 1, 2006.

The revised TRBAA cost of service requirement requested in AL 1671-E and the rate underlying this cost of service requirement are just and reasonable.

SDG&E has documented its revision to the TRBAA cost of service requirement and associated rate, which we approve. The method that SDG&E proposes to allocate those costs and the revised TRBAA cost of service requirements to customer classes are reasonable. Energy Division recommends that these rates be adopted.

Filed rate doctrine provides for a pass through of FERC-approved rates.

Under the filed rate doctrine applicable to these federally-approved rates, the CPUC is obligated to pass through this FERC-authorized cost of service requirement to SDG&E's applicable customers. The passing through of this cost of service requirement to SDG&E's applicable customers does not involve the promulgation of "general rates," or the establishment of a new general rate structure. Rather, the rates involved here pass through an adjustment to an existing category of costs. Accordingly, we conclude that we should authorize SDG&E to recover this revised cost of service requirement, which is permitted by both state and federal law.

The FERC-jurisdictional rate changes as requested by SDG&E are subject to refund.

In the event that FERC authorizes a different TRBAA rate than requested, SDG&E will adjust its rate prospectively as ordered by the FERC. If a refund is in order, SDG&E will file an advice letter with the Commission addressing the disposition of over-collected revenues concurrent with the refund report that would be filed with the FERC.

COMMENTS

Public Utilities Code section 311(g) (1) generally requires resolutions to be served on all parties and subject to at least 30 days public review and comment prior to a vote of the Commission. Section 311(g) (3) provides that this 30-day period may be reduced or waived pursuant to Commission adopted rule.

The 30-day comment period for this Resolution has been reduced in accordance with the provisions of Rule 77.7(f) (2). Rule 77.7(f) (2) provides that the Commission may reduce or waive the comment period for a decision in an uncontested matter where the decision grants the relief requested.

FINDINGS

1. SDG&E filed Advice Letter 1671-E on February 25, 2005 to revise its TRBAA rate effective upon approval by the Commission. No party protested SDG&E's advice letter.

2. SDG&E filed an erratum with the FERC on February 17, 2005 for a revision to its TRBAA rate, subject to refund.

3. The 2005 TRBAA rate is revised to $0.00164 per kWh to reflect a change (decrease) in the TRBAA cost of service credit by approximately $0.306 million from the current rates in effect February 1, 2005.

4. The system total class average rate increase is 0.01%.

5. The CPUC is obligated to pass through FERC-authorized revenue requirements to SDG&E's applicable customers.

6. Consistent with Commission Decision 04-02-057, SDG&E made a change to its commodity rates so that the total residential rates for usage up to 130% of baseline remain unchanged.

7. The commodity shortfall resulting from this rate adjustment will be recorded in the AB 1X shortfall sub-account of the ERRA for future recovery.

8. The Commission finds the revised TRBAA cost of service requirement and the attendant rate are just and reasonable, and fully recoverable from SDG&E's applicable customers.

9. In the event FERC authorizes a different rate than requested, SDG&E will file an advice letter to immediately adjust its rates on a prospective basis.

10. If a refund is in order, SDG&E will file an advice letter with the CPUC to return over-collected revenues in accordance with an order issued by the FERC.

11. In this case, the comment period has been reduced.

THEREFORE IT IS ORDERED THAT:

This Resolution is effective today.

I certify that the foregoing resolution was duly introduced, passed and adopted at a conference of the Public Utilities Commission of the State of California held on April 7, 2005; the following Commissioners voting favorably thereon:

            _________________

Jerry Royer

J. Steve Rahon

San Diego Gas & Electric Company

8330 Century Park Court

San Diego, CA 92123

srahon@semprautilities.com

   
     

Top Of Page