Word Document

STATE OF CALIFORNIA GRAY DAVIS, Governor

PUBLIC UTILITIES COMMISSION

505 VAN NESS AVENUE

SAN FRANCISCO, CA 94102-3298

July 9, 2001

TO: ALL PARTIES OF RECORD IN RULEMAKING 99-11-022

Attached is the Revised Draft Decision of Commissioner Lynch, H-22 on the Commission's Agenda for July 12, 2001. Comments on the Revised Draft Decision should be submitted by July 11, 2001. In addition, comments should also be emailed to Commissioner Lynch's office at gig@cpuc.ca.gov by July 11, 2001.

Very truly yours,

/s/ LYNN T. CAREW

Lynn T. Carew, Chief

Administrative Law Judge

LTC:abw

COM/LYN/abw * H-22

Draft DRAFT DECISION OF COMMISSIONER LYNCH

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Order Instituting Rulemaking into Implementation of Public Utilities Code Section 390.

Rulemaking 99-11-022

(Filed November 18, 1999)

ORDER CLARIFYING DECISION 01-06-015

Summary

In this decision the Commission clarifies its intent regarding the conclusions reached in Decision (D.) 01-06-015 of the reasonableness of various amendments proposed by Southern California Edison Company (SCE) to its contracts with qualifying facilities (QFs). In that decision, the Commission pre-approved three voluntary QF contract amendments for Southern California Edison Company (SCE), San Diego Gas & Electric Company (SDG&E), and Pacific Gas and Electric Company (PG&E) that address the special circumstances presented by the dysfunctional wholesale market in California. We also found reasonable proposed amendments presented by SCE and by the California Cogeneration Council (CCC).

In today's decision, we acknowledge several recent filings by SCE and CCC submitting various agreements and amendments for approval and we reiterate and clarify that in finding such amendments and agreements reasonable, the Commission believes that the terms and conditions contained in those amendments and agreements taken together are reasonable. This includes but is not limited to the provisions calling for both SCE and QFs to suspend or withdraw pending litigation. The specific findings regarding reasonableness requested by SCE are approved with respect to each of the amendments and agreements submitted for approval. SCE will be allowed to recover the costs it incurs under these agreements and amendments, subject to continued Commission review regarding the utility's future administration of those contracts.

Need for Expedited Consideration

Rule 77.7(f)(9) of the Commission's Rules of Practice and Procedure provides in relevant part that:

We balance the public interest in quickly resolving QF pricing and payment issues against the public interest in having a full 30-day comment cycle on the proposed amendment. We conclude that the former outweighs the latter. We must respond quickly to provide additional assurance that as much QF generation is available as possible this summer. Comments on the revised draft decision should be submitted by July 11, 2001.

Discussion

On June 1, 2001, Commissioner Lynch issued a Draft Decision providing guidance concerning three types of contract amendments that the Commission would deem reasonable. The Draft Decision also indicates that the utilities should submit a report to the commission concerning contract amendments made or rejected by July 31, 2001.

On June 13, 2001, SCE filed a Motion Submitting For Commission Approval (1) Executed Long-Term Amendments With Certain Gas-Fired Cogenerators; (2) Executed Short-Term "Bridge" Amendments With Certain Gas-Fired Cogenerators; (3) Standardized Form Amendment Providing For Five-Year Alternative "Fixed" SRAC Price Of 5.37 (the "June 13 Motion")1 In the June 13 Motion, SCE sought reasonableness approval of certain long-term and short term amendments to power purchase agreements between SCE and gas-fired QFs.2

On June 26, 2001, SCE filed a Motion For Commission Approval Of Additional QF Contract Amendments And Revised "Excess Energy" Amendments, And For Additional Commission Findings Re Previously Submitted Form and Executed QF Agreements (the "June 26 Motion"). The June 26 Motion indicate that SCE had executed numerous "generic" fixed rate agreements with renewable QFs and also tendered sixteen non-standard renewable agreements for review.

One June 28, 2001, SCE filed a Motion for Approval of Additional Gas Amendments And Bridge Amendments With Berry Petroleum And Of Extension Of Bridge Amendments With Certain Gas-Fired Cogenerators (the "June 28 Motion").

The long-term and short-term amendments to power purchase agreements between SCE and gas-fired cogenerators (the "Gas Amendments") submitted for approval by SCE with its June 13, 26 and 28 Motions reasonable. This decision is not intended to modify the prior determination or reasonableness made in D.01-06-015, but to clarify for parties the Commission's intent. Thus, the 30-day statutory appeal period for D.01-06-016 runs from the date of issuance of that decision and is not affected by the issuance of this clarifying order.

Findings of Fact

1. The Commission has a long-standing policy of supporting beneficial non-standard contract provisions.

2. CCC and SCE presented proposed contract amendments and agreements that the Commission found reasonable in D. 01-06-015.

3. SCE has subsequently submitted for approval additional agreements and amendments based substantially on those approved by the Commission in D.01-06-015.

4. By finding those proposed amendments reasonable, the Commission finds that all the terms and conditions contained therein taken together are reasonable, including the suspension or elimination of pending litigation.

5. SCE's entry into the Gas Amendments and into agreements based substantially on the Fixed Energy Rate Agreement with specific QFs is reasonable and prudent.

6. All terms and conditions of the executed Gas Amendments and the Fixed Energy Rate Agreement submitted with SCE's Motions of June 13, 26 and 28, as to which Commission approval is required, as defined in such agreements, are reasonable and prudent for all purposes, including recovery through rates of any payments made pursuant to such terms, subject only to review for reasonableness of SCE's administration of the submitted agreements.

7. The releases contained in the Gas Amendments and the Fixed Energy Rate Agreement are reasonable and prudent for all purposes, and SCE shall not be subject to further reasonableness review with respect to the administration of power purchase agreements insofar as claims with respect to such agreements are released in accordance with the terms of the Gas Amendments and the Fixed Energy Rate Agreement.

8. The terms and conditions of the Gas Amendments and executed Fixed Energy Rate Agreement will supersede any prior decision, ruling or order of the Commission pertaining to the subject matter of such agreements, and that no further Commission order, decision or ruling will alter, amend or increase the obligations and corresponding benefits created by such terms and conditions.

9. Insofar as terms and conditions of the Gas Amendments, Fixed Energy Rate Agreement and the Bridge amendments do not expressly require Commission approval, as defined in those agreements or otherwise, such agreements are nevertheless in all respects prudent and reasonable, and any payments made pursuant to such agreements shall be fully recoverable in rates, subject only to review (unless otherwise noted above) for reasonableness of administration of such agreements.

Conclusion of Law

SCE should be authorized to recover all costs associated with payments made under the Gas Amendments and the Fixed Rate Agreements submitted by SCE with its June 13, 26 and 28 motions, subject only to Commission review of the reasonableness of future administration of the amendments.

ORDER

Therefore, IT IS ORDERED that:

1. SCE's June 13 Motion, June 26 Motion and June 28 Motion are granted.

2. The Gas Amendments and Fixed Rate Agreements submitted for approval by the Commission with SCE's June 13 Motion, its June 26 Motion and its June 28 motion are approved, in their entirety, as reasonable.

3. SCE shall be authorized to recover all payments made under the Gas Amendments and the Fixed Rate Agreements subject to Commission review of the reasonableness of future administration of the amendments.

This order is effective today.

Dated ____________________, at San Francisco, California.

1 SCE served the June 13 motion as "Supplemental Comments" concerning the Draft Decision, electronically on the service lists for both R.99-11-022 and I.01-04-027 on June 12, 2001. The Commission's Docket Office has since advised SCE that the filing should be recaptioned as a motion and that it should be filed only in the R.99-11-022 docket. 2 These executed amendments are substantially the same as the generic long-term amendment submitted by the California Cogeneration Council (CCC) with its Comments on the June 1, 2001 Draft Decision.

Previous PageTop Of PageGo To First PageNext Page