1. Southern California Edison Company's Advice Letter 1479-E is approved as modified in the body of this Resolution.
2. To the extent that the Commission adopted modifications to Advice Letter 1479-E correspond to the protest of Premier Utility Consultants, Inc, the protest is granted
3. Should Southern California Edison Company choose to implement Advice Letter 1479-E as modified by this resolution, it shall: 1) provide written notice to each customer on Schedules D-APS and GS-APS of the present and modified terms and conditions of the tariff schedules, a brief explanation of the change, and a brief explanation of the procedure for changing to a different tariff schedule as modified by this resolution; and 2) file revised tariff sheets within 10 days specifically allowing customers to change rate schedules without penalty for 30 days from the date of notice of the tariff change. The tariff sheets shall become effective when filed, provided the Energy Division staff determines they comply with this Resolution.
4. The Director of the Energy Division's suspension of the tariff sheets attached to Advice letter 1479-E is ratified.
5. The 30-day review and comment period is reduced.
6. This Resolution is effective today.
I certify that the foregoing resolution was duly introduced, passed and adopted at a conference of the Public Utilities Commission of the State of California held on October 5, 2000; the following Commissioners voting favorably thereon:
_____________________
WESLEY M. FRANKLIN
Executive Director