6. Summary of SDG&E's Community Fire Safety Program

Santa Ana winds occur annually in Southern California during the fall and early winter. These strong, dry, offshore winds have led to some of California's largest and most damaging fires. Over the past decade, wildfires fanned by Santa Ana winds have burned hundreds of thousands of acres in San Diego County, caused billions of dollars of damage, and killed numerous people. In October 2003 and 2007, wildfires driven by Santa Ana winds spiraled out of control to become devastating firestorms.

SDG&E is currently implementing a multi-pronged program to reduce the likelihood of strong winds causing power-line fires. The major elements of the program, which SDG&E calls the Community Fire Safety Program, are summarized below. SDG&E represents that it developed its Community Fire Safety Program after consulting with local governments, public safety agencies, the Red Cross, various community groups, and other stakeholders.

6.1. Hardening of Facilities

SDG&E uses the term "hardening of facilities" to describe physical improvements to its overhead electric transmission and distribution system in areas that are prone to wildfires. SDG&E states the hardened facilities will be better able to withstand Santa Ana winds, which should lessen the risk of keeping power on during windy conditions. The hardened facilities will also be more resistant to damage from wildfires, potentially reducing the time needed to restore power after a fire.

The steps SDG&E is taking to harden its overhead power lines include the replacement of wood poles with steel poles, use of heavier wire conductors, increased spacing between conductors, and expanded use of conductor spacers. The hardened facilities are designed to withstand wind gusts of 85 miles per hour (mph). SDG&E is also implementing limited conversion of overhead power lines to underground lines in order to make the electric service provided to some essential public service infrastructure, such as selected water utility pump stations, less susceptible to outages from Santa Ana winds and wildfires. Because placing facilities underground is quite expensive, this form of hardening will be implemented sparingly.

The hardening of facilities will have little effect on SDG&E's Power Shut-Off Plan. Areas served by hardened above-ground facilities will remain subject to the Plan, even though such facilities will be better able to withstand high winds and fires. Only the few areas that are served by newly undergrounded facilities will be removed from the Power Shut-Off Plan.

6.2. Power Line Re-Closers

Many of SDG&E's power lines have switches known as "re-closers" that automatically de-energize circuits if unusually high electric currents are detected, and then automatically restore power. Under the Community Fire Safety Program, SDG&E will modify the operation of re-closers for overhead power lines in the areas of high fire risk. When an Elevated Fire Condition10 is present, SDG&E will adjust the operation of re-closers to allow either one or two re-energization attempts, depending on the location. If a circuit fails to re-close following the specified one or two attempts, the re-closer will be turned off remotely until the line is inspected and the re-closer is manually reset. Re-closers that cannot be monitored remotely will be turned off.11

SDG&E will turn off re-closers when a Red Flag Warning is declared by the National Weather Service for high winds and/or low humidity. When an outage occurs due to the operation of a re-closer, there will be a visual patrol of the line to ensure that it is safe to restore power. Although inspecting the line will increase the duration of the outage, SDG&E believes this step is warranted by the heightened fire risk conditions, especially since high-wind conditions increase the likelihood of damage to overhead facilities.12

6.3. Inspection of Overhead Power Lines

As part of its Community Fire Safety Program, SDG&E has implemented expanded inspections of overhead power lines and associated facilities in areas of high fire risk. The expanded inspections exceed current regulatory requirements.

6.4. Vegetation Management

SDG&E maintains clearance for approximately 72,000 trees located near overhead power lines in areas of high fire risk. SDG&E is working with local governments, public safety agencies, the Commission, and the legislature to modify laws and regulations to allow for increased vegetation management.

6.5. Staging Personnel

As part of its Community Fire Safety Program, SDG&E will stage personnel in or near Power Shut-Off Areas 13 when an Elevated Fire Condition is present or a Red Flag Warning for high winds and/or low humidity is declared.14 The purpose of staging personnel is to improve response times.

6.6. Emergency Power Shut-Off Plan

The final element of SDG&E's Community Fire Safety Program is the Power Shut-Off Plan. The purpose of this Plan is to de-energize overhead power lines when certain criteria are met in order to eliminate power lines as an ignition source when fire risks are high. SDG&E intends to implement its Plan on September 1, 2009. Power shut-off events will most likely occur during the September - December fire season in Southern California, but power will be shut off whenever the criteria are met.

    6.6.1. Power Shut-Off Criteria

SDG&E's Power Shut-Off Plan calls for power to be shut off in certain areas when all five of the following criteria are met in those areas.

Criterion 1: Live Fuel Moisture. The less moisture in living plants, the higher the fire risk. SDG&E intends to use a live fuel moisture level of 75% or less as one of the five criteria for initiating a power shut-off event.15 SDG&E will obtain measurements of live fuel moisture from Cal Fire and the United States (U.S.) Forest Service.

Criterion 2: Non-Living Fuel Moisture. The less moisture in dead vegetation, the higher the fire risk. SDG&E intends to use a non-living fuel moisture level of 10% or less as the second criterion for initiating a power shut-off event.16 Measurements of this criterion are made hourly at Remote Automatic Weather Stations (RAWS) operated by Cal Fire, the U.S. Forrest Service, and the U.S. Bureau of Land Management.

Criterion 3: Relative Humidity. The risk of wildfires is inversely proportional to the amount of moisture in the air, also known as relative humidity.17 The lower the relative humidity, the higher the fire risk. SDG&E intends to use a relative humidity of 20% or less as the third criterion for initiating a power shut-off event. Measurements of relative humidity are readily available from RAWS.

Criterion 4: Red Flag Warning. The risk of wildfires increases when there is low humidity, high winds, and/or dry lightning. The National Weather Service declares a "Red Flag Warning," its highest fire alert, when any of the following conditions are forecasted:

· Relative Humidity is 10% or less (for a duration of 10 hours or more) with no associated wind criteria.

· Relative Humidity is 15% or less, with sustained winds of 25 mph or more and/or frequent gusts of 35 mph or more (for duration of 6 hours or more).

· Dry lightning that is not accompanied by enough precipitation to significantly wet fuels that are critically dry.

SDG&E plans to use Red Flag Warnings for low humidity and/or high winds, but not dry lightning, as the fourth criterion for initiating a power shut-off event.

Criterion 5: High Winds. High winds are a significant fire hazard for power lines. High winds can topple utility poles, detach power lines, blow flammable debris onto power lines, and cause trees to fall onto power lines. Power-line fires that occur during high winds spread faster and are more difficult to extinguish.

SDG&E intends to use wind speed as the final criterion for initiating a power shut-off event. The criterion is sustained winds of 35 mph, or gusts of 55 mph accompanied by sustained winds of 30 mph.18 These wind speeds are at 10 meters above ground level, which corresponds to the top of utility poles. However, the actual measurements of wind speeds will be made by the RAWS at six meters above ground level. SDG&E estimates that wind speeds at 6 meters are 15% less than wind speeds at 10 meters. The wind-speed criterion at 6 meters, where the actual measurements will be made, is sustained winds of 30 mph, or gusts of 48 mph accompanied by sustained winds of 25 mph.

    6.6.2. Re-Energization of Power Lines

After SDG&E shuts off power, SDG&E will not re-energize until sustained winds drop to 25 mph or less for two hours and the affected power lines have been visually inspected to ensure that it is safe to re-energize. SDG&E will monitor weather data to determine when inspections can begin.

If requested by an outside agency, SDG&E will re-energize prior to sustained winds staying at 25 mph or less for two hours, but only after SDG&E has deemed it safe to re-energize. SDG&E anticipates the process of re-energizing its lines, including inspections, could take up to two hours.

    6.6.3. Power Shut-Off Areas

SDG&E's Power Shut-Off Plan applies to all circuits with overhead facilities that pass through regions designated by SDG&E as "Highest Risk Fire Areas." In general, these are areas with a high fuel load and strong winds. The geographic areas served by the circuits that are included in the Power Shut-Off Plan are called "Potential De-Energization Areas" (referred to hereafter as "Power Shut-Off Areas"). The Power Shut-Off Areas extend beyond the Highest Risk Fire Areas because circuits do not stop at the boundaries of these regions.

There are 17 Power Shut-Off Areas. Each Area is associated with its own RAWS that is located in or near the Area, for a total of 17 RAWS.19 Appendix A of today's decision contains a map that shows the 17 Power Shut-Off Areas and the 17 RAWS. There is some overlap of Power Shut-Off Areas. Thus, individual customers may be in two or more Power Shut-Off Areas.

SDG&E will be able to turn off power in each Power Shut-Off Area individually.20 SDG&E believes it is extremely unlikely there will be a need to shut off power to all 17 Areas simultaneously. Should the need to shut off power occur, SDG&E believes it will be limited to only a few Areas, which will minimize the number of people affected by an outage.

    6.6.4. Number of Affected People and Customers

SDG&E estimates there are 59,130 electric customers (meters) and 129,976 people living in the Power Shut-Off Areas, or about 4% of the total electric customers and population served by SDG&E. In addition, there are approximately 160 SCE customers served by SDG&E "fringe area circuits" who may be subject to SDG&E's Power Shut-Off Plan. SDG&E and SCE are taking steps to ensure inter-utility coordination on this matter.

The following table shows the estimated number of customers (meters) and people (residents) subject to the Power Shut-Off Plan in 2009, broken down by the 17 Power Shut-Off Areas.

Number of Meters and Residents in Power Shut-Off Areas

Area by

RAWS Name

Total

Meters

Residential

Meters

Commercial

Meters

Industrial

Meters

Residents

Alpine

18,566

15,615

2,943

8

42,205

Ammo Dump

1,736

1,139

597

0

3,289

Bell Canyon

68

7

56

5

81

Cameron

4,231

3,363

865

3

7,908

Camp Elliott

2,882

2,565

317

0

8,199

Descano

8,436

6,806

1,624

6

17,089

Goose Valley

18,027

15,136

2,885

5

45,580

Julian

3,294

2,393

901

0

4,001

Mount Laguna

286

226

60

0

391

Oak Grove

640

394

246

0

1,272

Palomar

1,310

885

424

1

1,126

Pine Hills

2,387

1,659

728

0

3,706

Potrero

2,471

1,890

581

0

5,423

Ranchita

1,116

747

369

0

1,802

San Miguel

2,298

1,977

321

0

6,119

Talega

19

0

17

2

19

Valley Center

13,886

10,815

3,062

9

29,932

Total 1

81,653 1

65,617

15,996

39

178,142 1

Note 1: Due to overlapping Areas, the sum of the meters in individual Areas (81,653) is greater than the total meters (59,130), and the sum of the residents in individual Areas (178,142) is greater than the total residents (129,976).

SDG&E has identified approximately 902 Medical Baseline customers in the Power Shut-Off Areas. Of these, 590 require life support equipment. There are also approximately 5,700 customers in the Power Shut-Off Areas who participate in the California Alternative Rates for Energy (CARE) program.

Some customers will be removed from the Power Shut-Off Plan in 2009 due to a project that is currently underway to place certain overhead power lines underground. When the project is complete, it will remove approximately 2,300 customers from the Power Shut-Off Plan, including 14 water pumping stations, leaving 56,830 customers affected by the Plan.

SDG&E estimates that the duration of power shut-off events will range from 12 to 72 hours, and that the average number of residents affected by each event will be 18,600. This estimate of residents excludes approximately 160 SCE customers (meters) subject to SDG&E's Power Shut-Off Plan.

    6.6.5. Customer Education

SDG&E believes it is important for customers to understand the Power Shut-Off Plan so they can prepare for power shut-off events before they occur. To this end, SDG&E has mailed information packets to all customers in the Power Shut-Off Areas. The package included a cover letter, program fact sheet, list of frequently asked questions, map of the impacted areas, a guide for developing an emergency plan, an unplanned outage fact sheet, a portable generator fact sheet, and a customer contact form. SDG&E will continue to mail a package annually to customers in Power Shut-Off Areas that contains the previously identified information.

SDG&E will survey its Special Needs Customers21 to ascertain each customer's readiness for a power shut-off event and any transportation needs they may have. Special Needs Customers with mobility restrictions who cannot remain in their homes without electricity (as identified through customer surveys) will be provided round trip transportation to appropriate facilities. Similarly, customers with special needs for diet, medication, and medical equipment will be provided round trip transportation to acute care facilities or hospitals in accordance with their needs and insurance restrictions. All transportation will be at SDG&E's expense.

SDG&E has made significant outreach efforts to Essential Customers, i.e., customers who provide services that are essential to public health, safety, and welfare. SDG&E defines Essential Customers as including the following:

A. Fire, police, and prison facilities.

B. Lighting for streets, highways, and other public areas.

C. National defense agencies.

D. Hospitals and convalescent homes.

E. Public, private, and municipal utilities that provide services that are essential for public health and safety (i.e., electric, gas, water, communication, and sewage disposal utilities).

F. Public transportation.

G. Radio and broadcasting stations that transmit emergency information.

H. Residential customers who use medical life support equipment.

I. Schools K-12.22

Essential Customers are not exempt from the Power Shut-Off Plan. Due to the nature of their loads, most Essential Customers are prepared to operate during outages. For example, hospitals and skilled nursing facilities have back-up generation to support critical load for 12 to 72 hours.

SDG&E has contacted all Essential Customers in the Power Shut-Off Areas to discuss the Power Shut-Off Plan. SDG&E will continue to contact all Essential Customers prior to each fire season to help them plan for power shut-off events.

    6.6.6. Customer Notice of Power Shut-Off Events

SDG&E will attempt to provide all customers with two notices when a power shut-off event appears likely. The first notice will occur at approximately four to six hours prior to the forecasted shut-off event. SDG&E will use its outbound dialer system to send telephone alerts to affected customers. The outbound dialing system can make more than 20,000 calls per hour, including calls to communications devices commonly used by persons with hearing, speech, and/or vision disabilities. The first notice will indicate that high fire risk conditions are forecast to occur, that SDG&E may shut off power, and that customers should prepare for a power shut-off event.

The second notice will occur two to three hours prior to the forecasted shut-off event. This second notice will have a more urgent tone about the need to prepare for the expected shut-off event. If the forecast changes and SDG&E determines that a power shut-off event is no longer likely, SDG&E will use its outbound dialer system to notify customers.

Essential Customers will be notified at the same times as other customers, but through phone calls and e-mails consistent with the individual customer preferences. SDG&E will also alert the Red Cross and 2-1-1 when a shut-off event is forecasted.

It is possible that the first forecast that SDG&E receives indicates a shut-off event could occur in three hours or less. In this situation, only one notice will be provided. In the unlikely event that a shut-off event occurs with no warning, SDG&E will notify customers as soon as practicable. Customers with functioning land lines or registered cell phones will receive a call.

    6.6.7. Mitigation of Adverse Impacts on Customers

SDG&E acknowledges that shutting off power imposes hardships on customers, particularly low income customers and customers with medical needs. SDG&E will implement a variety of measures to mitigate the hardships, such as providing advance warning of an impending shut-off event whenever possible so customers can prepare; providing $250 debit cards to customers participating in the CARE and/or Medical Baseline programs; opening shelters in the areas where power is shut off; and transporting customers who depend on life support equipment to appropriate medical facilities when a shut-off event is declared. SDG&E does not request additional funding in rates for these mitigation efforts in 2009.

SDG&E will contact all impacted Special Needs Customers in person or by telephone to discuss their emergency readiness and medical transportation needs in the case of a power shut-off event. Because Special Needs Customers are recertified bi-annually, SDG&E will use this opportunity to again discuss their emergency readiness and medical transportation needs. Once the power shut-off event is over and the Special Needs Customers are back home, there will be an in-person visit by an SDG&E employee to deliver assistance, followed by a live-person phone call to discuss the service level and overall experience.

SDG&E also recognizes that shutting off power will prevent the Water Districts from using many of their electric-powered pumps, which could disrupt the supply of water used to fight fires. To mitigate this adverse impact, SDG&E will procure a pool of six portable backup generators (four 400 kW and two 750 kW) that can be dispatched to the Water Districts during power shut-off events. The six portable generators are intended to support 20 critical pump stations with loads of 100 kW or greater. SDG&E will install and own the wiring and permanent electric transfer safety switches at these 20 facilities. The total estimated cost of the six generators and wiring is $3.9 million.23

If more than six generators are needed to provide water for fire-fighting purposes, SDG&E will re-energize any part of its system if ordered to do so by the incident commander. For example, if all six generators have been deployed to Water District facilities and additional Water District pump stations need to be brought on line at locations that remain de-energized, SDG&E could re-energize the circuit(s) serving the pump stations after conducting a safety inspection.

SDG&E is willing to own and maintain a pool of six generators for a two-year period. SDG&E believes that two years is enough time for the Water Districts to procure and install emergency back-up generation they should have for any of a number of emergency situations.

SDG&E does not intend to procure a pool of portable generators or install wiring for critical pump stations with a load of less than 100 kW. SDG&E believes that back-up generators for loads of less than 100 kW should be the responsibility of the individual Water Districts.

    6.6.8. Cost of the Power Shut-Off Plan

SDG&E states that the costs for its Power Shut-Off Plan will depend on the frequency and scope of shut-off events. Assuming two events per year, the annual costs will be in the range of $7 - $11 million. Startup costs will be in the range of $14 - $24 million.24 These estimates do not include any costs that result from Commission requirements that are adopted in this proceeding. SDG&E does not seek ratepayer funding for costs incurred in 2009.25

The above costs for the Power Shut-Off Plan are incremental to normal operating and maintenance costs and do not include other expenses for SDG&E's Community Fire Safety Program such as system hardening.

10 SDG&E defines an "Elevated Fire Condition" as occurring when live vegetation fuel moisture is 75% or less as measured by the California Department of Forestry and Fire (Cal Fire).

11 The planned operation of re-closers is described in Exhibit SDG&E-2, p. 11. Turning off re-closers prevents automatic attempts to re-energize the line.

12 SDG&E is considering the use of a new technology that sends a low-energy pulse through faulted power lines to determine if it is safe to re-energize. These devices might reduce restoration time.

13 The term "Power Shut-Off Areas" is defined later in today's decision.

14 The planned staging of personnel is summarized in Exhibit SDG&E-2, p. 13.

15 Live fuel moisture is the amount of moisture, expressed as a percentage of weight, in a living fuel sample compared to that sample when oven dry.

16 Non-living fuel moisture is the amount of moisture in a non-living wood dowel expressed as a percent of the dry weight of that wood.

17 Relative humidity is the ratio of actual moisture in a given volume of air at a given temperature compared to the total amount of moisture that volume of air could hold.

18 Wind speeds are measured at RAWS and are reported once per hour. The reported sustained wind speed is the average wind speed during the ten-minute interval prior to the hourly report. The reported maximum gust speed is the maximum wind speed recorded for any six-second interval since the prior hourly report.

19 The RAWS monitor and automatically report three of the five criteria used by SDG&E's Power Shut-Off Plan. The two criteria that are not monitored by the RAWS are (1) the Red Flag Warnings declared by the National Weather Service, and (2) live fuel moisture, which is provided periodically by Cal Fire and the U.S. Forrest Service.

20 There is some overlap between Power Shut-Off Areas. Consequently, shutting off power in one Area could affect another Area to the extent the two Areas overlap.

21 SDG&E defines Special Needs Customers as those who participate in the Medical Baseline Allowance and/or Life Support programs.

22 SDG&E treatment of schools as Essential Customers is limited to customer education and notice. SDG&E does not treat schools as Essential Customers with respect to SDG&E's proposed tariff provisions for demand normalization, critical peak pricing, and demand response.

23 At the all-party meeting held on July 6, 2009, SDG&E stated that it would procure a pool of 31 portable generators. Six would be for the Water Districts, ten for evacuation centers, and 15 for schools. SDG&E also proposed to pre-wire 110 sites to accept the portable generators. Ten of these sites would be evacuation centers, 20 sites would be critical pump stations, and the remainder would be schools. SDG&E did not state who will ultimately pay for the generators and wiring. (Reporter's Transcript, pp. 39-40.)

24 At the all-party meeting held on July 6, 2009, SDG&E stated that its startup costs would be in the range of $24 - $36 million. (Reporter's Transcript, pp. 39 - 40.)

25 SDG&E does not state if or when it will request ratepayer funding of costs incurred in 2010 and future years.

Previous PageTop Of PageNext PageGo To First Page