Word Document PDF Document |
STATE OF CALIFORNIA GRAY DAVIS, Governor
PUBLIC UTILITIES COMMISSION
505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3298
June 6, 2003
TO: ALL PARTIES OF RECORD IN ORDER INSTITUTING RULEMAKING 02-06-016
Decision 03-06-032 is being mailed without the written Dissents of Commissioner Lynch and Commissioner Wood. The Dissents will be mailed separately.
Very truly yours,
/s/ ANGELA K. MINKIN
Angela K. Minkin, Chief
Administrative Law Judge
ANG:acb
Attachment
ALJ/LTC/acb Mailed 6/6/03
Decision 03-06-032 June 5, 2003
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Order Instituting Rulemaking on policies and practices for advanced metering, demand response, and dynamic pricing. |
Rulemaking 02-06-001 (Filed June 6, 2002) |
INTERIM OPINION IN PHASE 1 ADDRESSING DEMAND RESPONSE GOALS AND ADOPTING TARIFFS AND PROGRAMS FOR LARGE CUSTOMERS 11
III. Statewide Demand Response Vision and Goals 77
IV. Demand Response Programs For Large Customers 1111
A. This Decision in Context: The Challenge of Developing Demand Response Programs for Large Customers 1111
B. Design Objectives for Demand Response Programs 1313
C. Mandatory or Voluntary Participation? 1414
E. Customer Participation Issues 3636
1. Agricultural Customers 3636
2. Multiple Meter Situations 3838
2. The Principle of Revenue Neutrality and Recovery of Revenue Shortfalls 5656
3. Program Administrative Costs 5959
5. The Costs of Incentives 6060
V. Phase 2 of this Rulemaking 6666
VI. Comments on Draft Decision 6666
A. Revisions: Program Details 6767
B. Revisions: Customer Participation Issues 6767
C. Revisions: Program Costs and Related Cost Issues 6868
D. Revisions: Program Evaluation and Monitoring Oversight 6868
VII. Assignment of Proceeding 6868
Attachment A
Attachment B
Attachment C
Attachment D
Attachment E