| Word Document |
STATE OF CALIFORNIA GRAY DAVIS, Governor

PUBLIC UTILITIES COMMISSION
505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3298
October 12, 2000
TO: ALL PARTIES OF RECORD IN RULEMAKING 99-11-022
Decision 00-10-030 is being mailed without the Dissent of Commissioner Carl Wood. The Dissent will be mailed separately.
Very truly yours,
/s/ LYNN T. CAREW
Lynn T. Carew, Chief
Administrative Law Judge
LTC: k47
ALJ/MLC/k47 Mailed 10/12/2000
Decision 00-10-030 October 5, 2000
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Order Instituting Rulemaking into Implementation of Pub. Util. Code § 390. |
Rulemaking 99-11-022 (Filed November 18, 1999) |
QUALIFYING FACILITY AVOIDED COST POSTING
AND ORDERING SOUTHERN CALIFORNIA EDISON COMPANY
AND SAN DIEGO GAS & ELECTRIC COMPANY
TO COMPLY WITH DECISION 96-12-028
This decision denies the emergency motion by Southern California Edison Company (SCE) to implement a provisional qualifying facility avoided cost posting for September 2000 and future months. SCE and San Diego Gas & Electric Company (SDG&E) are ordered to refile their September 2000 avoided cost postings in compliance with Decision (D.) 96-12-028.