10. Assignment of Proceeding

Geoffrey F. Brown is the Assigned Commissioner and Glen Walker is the assigned Administrative Law Judge in this proceeding.

Findings of Fact

1. SCE is an electric public utility subject to the jurisdiction and regulation of this Commission.

2. SCE has property at the Center-Mesa transmission right of way in the City of Pico Rivera available for secondary use, and it seeks to obtain revenue for ratepayers and shareholders through a secondary use lease.

3. Subject to Commission authorization required under Pub.Util. Code § 851, SCE has negotiated a long-term lease of the property to provide lease revenues with no interference with the operation of the transmission lines.

4. The proposed lessee, RHC, is managed by principals with substantial experience in commercial and industrial real estate projects.

5. RHC intends to finance, construct and maintain a self-storage facility at the site, bearing the costs and making payments to SCE.

6. Revenue in excess of a Commission-established threshold will be shared 70%/30% between the utility and ratepayers by treating all revenues as Other Operating Revenue, pursuant to D.99-09-070.

7. There has been no opposition to this application.

8. SCE has filed lead agency CEQA documentation with this application.

Conclusions of Law

1. No public hearing is necessary.

2. Joint use of utility property should be encouraged in appropriate cases because of the obvious economic and environmental benefits.

3. The Commission should condition its approval of the proposed lease on lessee's compliance with all applicable environmental regulations.

4. SCE should be authorized pursuant to Pub.Util.Code § 851 to lease the designated 11.3-acre site to RHC on the terms and conditions set forth in the application.

5. The proposed sharing of revenues with ratepayers conforms to the Commission's order in D.99-09-070.

6. Because of the benefits of this lease agreement for the utility and for ratepayers, approval of this application should be made effective immediately.

ORDER

IT IS ORDERED that:

1. Southern California Edison Company (SCE) is authorized to enter into a lease of an 11.3-acre site located on a portion of SCE's Center-Mesa transmission right of way in the City of Pico Rivera under the terms and conditions set forth in this application.

2. As received, all revenues from the lease authorized shall be treated as Other Operating Revenue and shall be subject to the gross revenue sharing mechanism set forth in Decision 99-09-070.

3. Approval of this application is conditioned upon lessee's compliance with all applicable environmental regulations, pursuant to the California Environmental Quality Act.

4. SCE shall notify the Director of the Energy Division, in writing, of any substantial amendments to, extension of, or termination of the lease agreement, within 30 days following the execution of such amendments, extensions or termination.

5. Application 05-08-040 is closed.