P-1 Expansion of the Southern California Edison Fire Prevention and Response Plan (FPRP). SCE's FPRP shall apply to the entire length of the Antelope-Pardee 500-kV Transmission Line ROW, including the portions of the route in unincorporated Los Angeles County, and the Cities of Lancaster and Santa Clarita. SCE shall modify its plan to include the entire Project route, and shall notify the construction contractor(s) that the SCE FPRP and all measures contained within shall be applicable to the entire Project route and be in effect during the entire Project construction phase. SCE shall provide the revisions to the plan to CPUC for review and approval prior to the start of construction.