D0704043 Opinion Approving Settlement on San Diego Gas & Electric Company's Advanced Metering Infrastructure Project
Word Document PDF Document

APPENDIX A

SETTLEMENT AGREEMENT REGARDING SAN DIEGO GAS & ELECTRIC COMPANY'S ADVANCED METERING INFRASTRUCTURE APPLICATION, A.05-03-015

Pursuant to California Public Utilities Commission's Rules of Practice and Procedure, Article 12, Rule 12.1, San Diego Gas & Electric Company (SDG&E), the Division of Ratepayer Advocates (DRA), and Utility Consumers' Action Network (UCAN) (the Settling Parties) enter into this Settlement Agreement regarding SDG&E's Advanced Metering Infrastructure (AMI) proposal, submitted for Commission consideration in Application A. 05-03-015 (the Settlement).1 The Settling Parties, who were the only active parties to the proceeding, believe that the Settlement is reasonable in light of the whole record, consistent with law, and in the public interest.

I. Introduction and Background

The Settling Parties believe that the record is sufficient to meet the burden of proof and to allow the Commission to make a reasoned decision. SDG&E filed its revised business case-in-chief on March 28, 2006, provided supplemental testimony upon the request of presiding Administrative Law Judge (ALJ) Gamson on June 16, 2006, and later updated and revised its showing on July 14, 2006 and again on September 7, 2006. DRA and UCAN propounded numerous data requests and DRA conducted an on-site audit of SDG&E's cost and benefit analysis and supporting workpapers. Both DRA and UCAN filed direct and rebuttal testimony.

The Commission held eight days of evidentiary hearings, beginning September 25, 2006. Subsequently, parties filed opening briefs and reply briefs on October 27 and November 13, respectively. On December 15, 2006, ALJ Gamson issued a ruling to reopen the record to consider further information regarding alternative deployment options. SDG&E responded to ALJ Gamson's ruling on January 4, 2007 and January 11, 2007. SDG&E, DRA and UCAN submitted comments on SDG&E's response. In light of the entire record pre-dating the ALJ's December 15, 2006 ruling and the additional information submitted by all parties in response to that ruling, the record is amply developed to consider this Settlement.

Based on the foregoing, the Settling Parties submit for Commission adoption this comprehensive Settlement, which constitutes a settlement of all issues between the Settling Parties.

In summary, the Settling Parties agree that SDG&E's AMI deployment and cost recovery proposal as set forth in SDG&E's Application 05-03-015, including the supporting testimony,2 is reasonable and should be adopted by the Commission with the following modifications: (1) the total AMI project costs will be increased to $572 million to include additional AMI functionalities and extended meter warranty provisions, as described below; (2) SDG&E will purchase an extended warranty for the AMI equipment, so long as the terms described below are met; (3) SDG&E is required to issue an addendum to its Request for Proposal (RFP) as described below; (4) SDG&E will modify its AMI technology selection, as described below; (5) the risk contingencies will be shared between ratepayers and shareholders in the manner described below; (6) the AMI revenue requirement will be allocated among customer classes, as described below; (7) Critical Peak Pricing (CPP), Peak Time Rebate (PTR) and other AMI related dynamic rates will be determined in SDG&E's January 31, 2007, General Rate Case (GRC) Phase 2 proceeding,3 (8) SDG&E will establish an AMI "Technology Advisory Panel" (TAP) as described below and in Attachment A; (9) SDG&E will report quarterly on AMI implementation progress to the CPUC Energy Division, as described below; and (10) SDG&E may recover increased costs that are the result of uncontrollable/force majeure events, as described below.

Each of these modifications is set forth below.

II. Settlement Agreement Provisions

1 On January 26, 2007, the ALJ issued a ruling granting SDG&E motion to propose a settlement agreement beyond the Rule 12.1 time limit.

2 SDG&E's case-in-chief is comprised of SDG&E's March 28, 2006 submission as revised and superseded by the July 14, 2006, and September 7, 2006 updates.

3 A. 07-01-047.

4 SDG&E's balancing account treatment of AMI project cost and benefits are described in Exhibit 34, Chapter 14 Prepared Direct Testimony of Robert Hansen.

Top Of PageNext PageGo To First Page