Construction Work in Progress (CWIP) for Region II and General Office - In ¶ 2.12, GSWC and DRA agree on an overall amount of CWIP for Region II projects to be amortized from 2006-2008 pursuant to an agreed-upon schedule. In ¶ 2.13, these parties agree that it is reasonable to include in rates $900,000 for general office CWIP to be closed in 2006. With respect to the latter, GSWC agrees that in future rate cases, its CWIP requests will be supported by workpapers and testimony to facilitate DRA's review of the requests. This is one of at least two instances in the stipulation where GSWC acknowledges that its showing on certain issues was insufficient.