The Settlement

The two active parties entered into settlement discussions to try to resolve their differences. This settlement is the result of those discussions. The settlement consists of the following agreements by the Settling Parties:

1. The reasonable total cost recoverable from this CEMA application is $15.5 million, consisting of $11.3 million in capital costs and $4.2 million in expenses. The revenue requirement resulting from these costs is $12.138 million in electric revenue requirements, including interest through December 31, 2010, franchise fees, and uncollectibles, to be collected in rates beginning January 1, 2008, with $9.333 million collected in rates in 2008, $1.431 million in 2009, and $1.374 million in 2010.10 Upon approval of this settlement by the Commission, PG&E will record the CEMA revenue requirement into the Distribution Revenue Adjustment Mechanism ($11.46 million) and to the Utility Generation Balancing Account ($503,00011) for rate recovery through the Annual Electric True-up advice letter.

10 The revenue requirement numbers include interest calculated at the actual 90-day commercial paper rate through August 2007, and at the August 2007 90-day commercial paper rate thereafter on the unamortized balance through 2010. The numbers will change slightly over time as the forecasted 90-day commercial paper rate is replaced by the actual 90-day commercial paper rate in each month following August 2007.

11 These numbers only total $11.963 million because they assume interest only through December 31, 2007, when the revenue requirement numbers are assumed to be transferred to the DRAM and UGBA, using the same assumptions as footnote 1.

Previous PageTop Of PageNext PageGo To First Page