| Word Document PDF Document | 
ALJ/MSW/avs Date of Issuance 6/27/2008
Decision 08-06-031 June 26, 2008
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Order Instituting Rulemaking to Consider Annual Revisions to Local Procurement Obligations and Refinements to the Resource Adequacy Program.  | 
Rulemaking 08-01-025 (Filed January 31, 2008)  | 
DECISION ADOPTING LOCAL PROCUREMENT OBLIGATIONS FOR 2009 AND REFINEMENTS TO THE RESOURCE ADEQUACY PROGRAM
Title Page
DECISION ADOPTING LOCAL PROCUREMENT OBLIGATIONS FOR 2009 AND REFINEMENTS TO THE RESOURCE ADEQUACY PROGRAM 22
3.2. Local Procurement Obligations for 2009 88
3.2.1. Continuation of the Local RA Program 88
3.2.3. Aggregation of Local Areas 1010
4. RA Program Refinements 1212
4.1. Outage Counting Rules 1212
4.4. RA Compliance Reporting 1818
4.5. Allocation of CAM-Related RA Credits 2121
DECISION ADOPTING LOCAL PROCUREMENT OBLIGATIONS FOR 2009 AND REFINEMENTS TO THE RESOURCE ADEQUACY PROGRAM
This decision adopts local procurement obligations for 2009 applicable to Commission-jurisdictional electric load-serving entities (LSEs). These procurement obligations are based on a study of local capacity requirements (LCRs) for 2009 performed by the California Independent System Operator (CAISO). Even though peak loads are expected to increase in all but one of the defined local areas, the total LCR for all such areas combined has declined slightly, from 28,106 megawatts (MW) in 2008 to 27,915 MW in 2009.
In addition, we approve and adopt certain proposed resource adequacy (RA) program refinements. We simplify the rule for counting the capacity of a new resource by focusing on the resource's commercial operation date, approve an interim rule for new resources for 2009, and approve proposed clarifications and modifications to the rules for counting the capacity of Qualifying Facility (QF) resources. We also approve and adopt modifications to the RA compliance reporting procedure that include a provision for electronic compliance reporting.