STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor
PUBLIC UTILITIES COMMISSION
505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3298
August 27, 2008
TO PARTIES OF RECORD IN CASE 07-06-001 DECISION 08-08-038,
MAILED AUGUST 27, 2008.
On July 25, 2008, a Presiding Officer's Decision in this proceeding was mailed to all parties. Public Utilities Code Section 1701.2 and Rule 15.5(a) of the Commission's Rules of Practice and Procedures provide that the Presiding Officer's Decision becomes the decision of the Commission 30 days after its mailing unless an appeal to the Commission or a request for review has been filed.
No timely appeals to the Commission or requests for review have been filed. Therefore, the Presiding Officer's Decision is now the decision of the Commission.
The decision number is shown above.
/s/ PHILIP S. WEISMEHL for
Angela K. Minkin, Chief
Administrative Law Judge
ANG:rbg
Attachment
ALJ/VDR-POD/rbg Date of Issuance 8/27/2008
Decision 08-08-038
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Lawrence A. Rupprecht, Complainant, vs. Southern California Edison Company (U338E), Defendant. |
Case 07-06-001 (Filed June 1, 2007) |
Lawrence Rupprecht, in pro per, complainant.
Gary Chen, Attorney at Law, for Southern California
Edison Company, defendant.
PRESIDING OFFICER'S DECISION DISMISSING COMPLAINT AND ORDERING EXTRAORDINARY RELIEF PURSUANT TO
GENERAL ORDER 95, RULE 12.4
TABLE OF CONTENTS
TITLE PAGE
PRESIDING OFFICER'S DECISION DISMISSING COMPLAINT AND ORDERING EXTRAORDINARY RELIEF PURSUANT TO GENERAL
ORDER 95, RULE 12.4 22
4.2. Clearance of the line over the Elna Property 1010
4.3. "Flicker" and the replacement of the secondary line. 1010
PRESIDING OFFICER'S DECISION DISMISSING COMPLAINT AND ORDERING EXTRAORDINARY RELIEF PURSUANT TO
GENERAL ORDER 95, RULE 12.4
Lawrence Rupprecht (Rupprecht or complainant) seeks to have existing overhead electric facilities to his residence in Cathedral City reconfigured and partially undergrounded. He claims that the existing configuration violates certain provisions of Commission General Order (GO) 95, and that accordingly a secondary pole on his property must be replaced, and a span of wire must be upgraded, at the sole expense of Southern California Edison Company (Edison or defendant), his service provider.
We disagree with complainant's contentions, and we conclude that the complaint must be dismissed. However, as a result of the matters called to our attention by the complaint, we order Edison to inspect and measure the clearance of the secondary line above the residence of complainant's neighbor at 39015 Elna Way. If that clearance fails to comply with the clearance requirement of GO 95, we order Edison to alter or reconstruct the line at its expense in the interest of safety, as provided in Rule 12.4 of GO 95.
The complaint is dismissed and Case 07-06-001 is closed.