8. Assignment of the Proceeding
Rachelle B. Chong is the assigned Commissioner for Rulemaking 07-12-001 and Timothy Kenney is the assigned Administrative Law Judge.
1. The TCR contains a proposal by the active parties in this proceeding to revise GO 95 to incorporate basic construction standards for pole-top antennas on joint-use utility poles. The proposal is supported by a broad cross section of affected interests. There is no opposition to the proposal.
2. The proposed construction standards for pole-top antennas are designed to (i) protect the safety of workers and the public, and (ii) allow pole-top antennas to be installed in a manner that is compatible with equipment and facilities attached to joint-use utility poles by electric utilities, telecommunications providers, and cable service providers.
3. A strong and robust wireless infrastructure is essential to many consumers' daily lives; the state's economic growth and prosperity; and public safety and welfare. Expanding the wireless infrastructure therefore provides significant public benefits.
4. The proposed revisions to GO 95 contained in the TCR will facilitate the expansion of the State's wireless infrastructure.
5. The TCR's proposed Rule 92-1F(2) inadvertently excluded a cross-reference to "Rule 38."
6. SCE's proposed revisions to Rule 94.5, Appendix H, were never identified as a matter within the scope of this proceeding. SCE did not provide notice of its proposed revisions until its written comments on the TCR.
7. The Commission preliminarily determined in the OIR that hearings were needed. This was affirmed by the Scoping Memo.
8. Hearings were not held because (i) all matters within the scope of this proceeding were addressed by the parties through the technical conferences, the TCR, and written comments on the TCR; and (ii) no party requested a hearing.
1. It is in the public interest to expand California's wireless infrastructure.
2. The proposed revisions to GO 95 contained in the TCR should be adopted because, for the reasons set forth in the body of today's Decision, the revisions are reasonable in light of the whole record, consistent with the law, and in the public interest.
3. Proposed Rule 92.1-F(2) should be corrected to include a cross-reference to "Rule 38."
4. SCE's proposal to delete parts of GO 95, Rule 94.5, Appendix H, cannot be considered at this time because (i) it is outside the scope of this proceeding, and (ii) the notice requirements of Pub. Util. Code § 1708 have not been met.
5. Affected parties should work cooperatively to resolve antenna installation issues in a way that (i) protects the safety of workers and public, and (ii) facilitates the expansion of the State's wireless infrastructure.
6. The revisions to GO 95 adopted by today's Decision should be effective 270 days after the date of today's Decision.
7. CPSD should revise GO 95 to conform to today's Decision and post the revised general order on the Commission's website within 45 days.
8. Pursuant to existing GO 95, Rule 13, the revisions to GO 95 adopted by today's Decision are not intended as complete construction specifications, but embody only the requirements that are most important from the standpoint of safety and service. Construction shall be according to accepted good practice for the given local conditions in all particulars not specified in the rules.
9. There is no need for hearings in this proceeding. The previous determination that hearings are needed should be reversed.
10. The following order should be effective immediately.
IT IS ORDERED that:
1. The proposed revisions to General Order (GO) 95 that are contained in the Technical Conference Report are hereby adopted, effective 270 days after the date of today's Decision. The affected provisions of GO 95, as amended by this Decision, are shown in Appendix A, Attachment C of today's Decision.
2. The Commission's Consumer Protection and Safety Division shall revise GO 95 to conform to this Decision and post the revised general order on the Commission's website within 45 days from the effective date of today's Decision.
3. Hearings are not needed.
4. Rulemaking 07-12-001 is closed.
This order is effective today.
Dated October 2, 2008, at San Francisco, California.
MICHAEL R. PEEVEY
President
DIAN M. GRUENEICH
JOHN A. BOHN
RACHELLE B. CHONG
TIMOTHY ALAN SIMON
Commissioners
SUBMISSION OF POLE-TOP ANTENNAS WORKSHOP REPORT BY SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) ON BEHALF OF
WORKSHOP PARTICIPANTS
Pursuant to the Scoping Memo and Ruling of the Assigned Commissioner filed March 21, 2008 ("Scoping Memo"), Southern California Edison Company ("SCE"), on behalf of the workshop participants,18 submits this Workshop Report on the Pole-Top Antennas workshops held April 3 & 4, 2008 in San Francisco, April 16, 2008 in San Diego, and May 01, 2008 in San Francisco.19 It is expected that Parties will comment on the Workshop Report, attached hereto as Appendix 1, pursuant to the schedule set forth in the Scoping Memo as modified by the May 2, 2008 Administrative Law Judge's Ruling Revising the Schedule for the Proceeding, with Opening Comments due May 27, 2008 and Reply Comments due June 6, 2008.
Respectfully submitted,
JAMES M. LEHRER
ROBERT F. LeMOINE
/s/ Robert F. LeMoine
By: |
Robert F. LeMoine |
Attorneys for
SOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue
Post Office Box 800
Rosemead, California 91770
Telephone: (626) 302-4182
Facsimile: (626) 302-6693
E-mail: Robert.F.LeMoine@sce.com
Appendix 1
I. INTRODUCTION
The stated purpose of this proceeding ((R) 07-12-001) is to determine whether the Commission should adopt the proposed revisions to General Order (GO) 95 as submitted by the GO 95/128 Rules Committee in Petition (P) 07-07-020.
II. PROCEDURAL HISTORY
In Decision (D) 07-02-030, the Commission adopted new GO 95 rules for the installation of wireless antennas on jointly used utility poles, but expressly reserved for a later date the possible adoption of rules for the installation of wireless antennas above or between supply lines.
Subsequently, the GO 95/128 Rules Committee submitted P.07-07-020, recommending revisions to Rule 94 as adopted in D.07-02-030 and proposed changes to other GO 95 rules to establish new uniform construction standards for wireless antennas installed above or between supply conductors operating at 0 -50,000 Volts, including pole-top antennas above communication lines on joint-use utility poles.
The Commission later issued an Order Instituting Rulemaking (OIR) 07-12-001 to consider uniform construction standards for "pole-top antennas." Opening and reply comments were filed on January 14 and February 15, 2008, respectively. A prehearing conference (PHC) was held on March 5, 2008 to develop a joint PHC statement that affirmed the Parties' consensus on the scope and schedule of this instant proceeding.
On March 21, 2008, the Commission issued a Scoping Memo setting forth the scope, schedule, category, need for hearing, the presiding officer and the rules for ex parte communications in this instant proceeding, pursuant to Rule 7.3(a) of the Rules of Practice and Procedure.
III. WORKSHOPS
In keeping with the workshop calendar established in the Scoping Memo, a two-day technical workshop was convened in San Francisco on April 03-04, 2008, followed by a one-day workshop in San Diego on April 16, 2008 and concluded with a one-half day workshop in San Francisco on May 01, 2008.
San Francisco Workshop
On April 3, 2008, interested parties met to consider several audio-visual presentations in advance of engaging in technical discussions concerning the minimum vertical clearances between wireless antennas and supply lines operating at 750 - 22,500 Volts noted in Proposed Rule Change (PRC) #4 (Rule 38, Table 2, new Case 21). After the lunch break, the CPSD representative stated that after an internal review, the CPSD was officially withdrawing a previously stated concern regarding the possible need for insulating a pole-top antenna's communication cables that pass high voltage supply lines. At the conclusion of the afternoon session, attendees agreed to reconvene the next morning to discuss, in more detail, the possible reduction of the 96-inch vertical clearance (in PRC #4) to 72-inches.
During the April 4th morning session, attendees thoroughly assessed the correlating provisions of Case 21 and Rule 94 and agreed that each entity would need to consider (internally) the ramifications of a 72-inch vertical clearance in advance of the next workshop. A draft "red-line" revision of new Case 21, including a 72-inch minimum vertical clearance between antennas (including associated equipment and support elements) installed above 750 - 35,000 Volt supply lines was prepared. During the afternoon session, attending parties also agreed to consider certain editorial revisions to Rule 94 (PRC #1), Rule 91.3-B (PRC #2) and Rule 92.1-F2 (PRC #3). Before adjourning, Raymond Fugere (CPSD) offered to revise the Figures 94.1 - 94.5 and Sam Stonerock (SCE) offered to organize the proposed workshop revisions to PRCs 1-4. Both the Figures and revisions were subsequently distributed to the Parties.
San Diego Workshop
On April 16th, interested parties met at the San Diego Sheraton Hotel. At the start of the workshop, a non-binding poll indicated attending parties either agreed with the previously proposed 72-inch clearance or chose to take no position.
During the morning session, no "showstoppers" were identified; however, attendees did engage in a protracted discussion about the implications of a 72-inch vertical clearance. Because there appeared to be some interpretive ambiguity stemming from Footnote "v v" to Case 21, the attendees eventually agreed to revise this footnote.
During the afternoon session, attendees discussed revisions to Figures 94.1 - 94.5 and concluded that a new Figure that encapsulates the variety of wireless antenna installations above and below supply and communication lines on a joint-use utility pole would be preferable to five separate Figures.
Prior to adjournment, the remaining attendees agreed to reconvene via teleconference on April 24th, at 8:30 a.m., to review the draft workshop report and identify new items of concern (if any) in advance of a scheduled teleconference with ALJ Kenney on April 25. Raymond Fugere offered to continue development of a new Figure (94-1) and Sam Stonerock agreed to compile and compose a draft workshop report for distribution to parties on or before April 21.
San Francisco Workshop
On May 01, 2008, interested parties met at the California Public Utilities Commission offices in San Francisco to resolve an interpretive dispute arising after the San Diego Workshop. The attendees20 discussed the possible addition of a new footnote "yy" to apply to Columns E, F, and G of new Case 21, that would allow certain support elements (for example, pole-top antenna mounting brackets) to extend into the required vertical clearance by "mutual agreement." After extensive discussion, the attendees21 concluded the new footnote was unnecessary because existing GO 95 Rule 15.2 allows experimental installations 15 days after the filing of a full statement with the Commission disclosing such installation, provided the appropriate precautions and other requirements of Rule 15.2 are met.
IV. CONCLUSION
Before the first technical workshop was convened, Parties agreed that the 8-foot vertical clearance expressed in Rule 38, Table 2, Case 21 Columns E, F, G was the principal matter of dispute. Parties also agreed that a number of editorial revisions should be considered in light of the written comments.
After three and one-half days of careful review and discussion during technical workshops sessions (including several parties' technical presentations) and multiple hours expended between workshops, it was determined that a 6-foot vertical clearance between Antennas (including associated equipment and support elements) and supply lines energized at 750 - 35,000 Volts is an appropriate minimum requirement.
It was also determined that additional practical and editorial revisions to Rules 94, 91.3, 92.1, and Rule 38, Case 21 are needed to help ensure the new "pole-top" antenna requirements: (1) protect the safety of utility workers and the public; (2) do not compromise system reliability; (3) are consistent with other GO 95 rules; and (4) meet the Commission's broader goal of facilitating the expansion of California's wireless infrastructure.
V. WORKSHOP REPORT ATTACHMENTS
· Attachment A: Proposed Rule Changes Submitted in P.07-07-020
· Attachment B: Strikeout/Underline Revisions
· Attachment C: Final Versions of GO 95 Rules
· Attachment D: Rationales for GO 95 Rules
· Attachment E: Workshop Attendees
ATTACHMENT - A
Proposed Rule Changes
Submitted in Petition 07-07-020
Proposed Final in P.07-07-020
94 Antennas
94.1 Definition (See Rule 20.0)
94.2 Maintenance and Inspection (See Rules 31.1 and 31.2)
94.3 General Requirements
On joint use poles supporting Class T, C, L or H Circuits (up to 50 kV), the following shall apply:
A. Antennas shall meet the requirements of Class C equipment, unless otherwise specified in this rule.
B. All associated elements of the antenna (e.g. associated cables, messengers, and pole line hardware) shall meet the requirements of Class C circuits.
94.4 Material Strengths
A. Support elements (e.g. arms, braces, brackets, pole-top extensions, hardware) installed above supply lines must:
(1) Meet Grade A requirements.
(2) Conform to the requirements of Section IV.
B. Support elements (e.g. arms, braces, brackets, pole-top extensions, hardware) installed above or below communication lines (where supply lines are not attached) must:
(1) Meet Grade F requirements.
(2) Conform to the requirements of Section IV.
94.5 Clearances
A. Antennas and supporting elements (e.g. crossarms, brackets) below supply lines shall maintain a vertical clearance of 6 feet from Supply Conductors operating at 0 -50kV. (See Figure 94-1)
B. Antennas and supporting elements (e.g. crossarms, brackets) below communication lines shall maintain a 2 ft. vertical separation from communication conductors and equipment. (See Figure 94-2)
C. Antennas, associated equipment (e.g. terminations, enclosures) and support elements installed above supply lines and/or communication lines of different ownership attached to the same structure shall maintain the vertical clearances specified in Rule 38, Table 2, Case 21, Columns A - H.
Note: Other vertical clearances between communication equipment and supply lines are specified in Rule 92.1-F(2).
D. Antennas, associated equipment (e.g. terminations, enclosures) and support elements, installed above supply lines and/or communication lines of different ownership, shall maintain the radial clearances from unattached supply and communication lines specified in Rule 38, Table 2, Case 3.
E. Antennas shall maintain a 2 ft. horizontal clearance from centerline of pole when affixed between supply and communication lines or below communication lines. (See Figures 94-1 and 94-2)
F. Horizontal clearances from centerline of the pole for Antennas, associated equipment and support elements, affixed between supply lines or at the top of a climbable pole, are not specified, but must be arranged so that qualified persons may climb the structure safely.
G. Antennas shall have a vertical clearance above ground as specified in Table 1, Column B, Cases 1 to 6a.
94.6 Marking
A. No antenna owner or operator shall install an antenna on a joint use pole unless such installation is subject to an agreement with the pole owner(s) that includes marking requirements that are substantially similar to and achieve at least the same safety standards as those set forth in Appendix H to GO 95.
B. Joint use poles shall be marked with a sign for each antenna installation as follows:
(1) Identification of the antenna operator.
(2) A 24-hour contact number of antenna operator for Emergency or Information.
(3) Unique identifier of the antenna installation.
94.7 Climbing Space
A. Climbing space above supply lines shall be maintained in accordance with Rule 54.7-A to:
(1) The bottom of the Antenna (including associated support elements) if affixed less than eight inches from the surface of the pole at the top of the pole or pole-top extension.
(2) The top of the pole or pole-top extension if the Antenna (including associated support elements) is affixed more than eight inches from the surface of the pole or pole-top extension.
(3) The bottom of the uppermost Antenna (including associated support elements) if multiple Antennas are present at different levels above supply lines. (See Figure 94.3)
B. Climbing space above communication lines shall be maintained in accordance with Rule 84.7 to:
(1) The bottom of the Antenna (including associated support elements) at the top of the pole or pole-top extension when affixed less than eight inches from the surface of the pole.
(2) The top of the pole or pole-top extension if the Antenna (including associated support elements) is affixed more than eight inches from the surface of the pole or pole-top extension.
(3) The bottom of the uppermost Antenna (including associated support elements) if multiple Antennas are present at different levels.
94.8 Stepping (See Exception to Rule 91.3)
94.9 Risers and Vertical Runs
A. Risers and vertical runs passing supply and/or communication lines, or space typically occupied by supply or communication lines, and equipment on nonmetallic structures (e.g. single wood, concrete, composite, fiberglass poles or multiple pole configurations) shall be suitably covered throughout its length; occur on a single pole; and shall be installed outside the climbing space in accordance with Rule 54.6-D 1, 2, 3 and 5.
(1) Associated cable runs extending to an adjacent structure or building shall be bonded to existing communication cables and messengers and effectively grounded at the originating structure. (See Rule 83.4) Where communication guard arm construction exists, the protective covering shall extend below the guard arm.
B. The suitable protective covering for risers and vertical runs passing supply lines or space typically occupied by supply lines and equipment shall extend no less than: (See Figure 94.3)
(1) 3 ft. above lines energized from 0 - 750 Volts.
(2) 7 ft. above lines energized from 750 - 22,500 Volts.
(3) 9 ft. above lines energized from 22,500 - 50,000 Volts.
C. Risers and vertical runs passing supply and/or communication lines, or space typically occupied by supply or communication lines and equipment, on metallic structures shall occur on a single structure, and be installed outside the climbing space in accordance with Rule 54.6-D 4.
94.10 De-energizing
No antenna owner or operator shall install an antenna on a joint use pole unless such installation is subject to an agreement with the pole owner(s) that includes de-energizing protocols that are substantially similar to and achieve at least the same safety standards as set forth in Appendix H to GO 95.
Exceptions: Antennas utilized by utilities for the sole purpose of operating and monitoring their supply system are exempt from this rule and shall only meet the construction and clearance requirements of supply equipment.
Antennas embedded in or attached to communication cables and messengers are exempt from this rule and shall only meet the construction requirements for Class C circuits.
Figure 94.1
Figure 94.2
Figure 94.3
Figure 94.4
Figure 94.5
GO 95 Rule 91.3-B (Stepping)
Proposed Final in P.07-07-020
91.3 Stepping
B. Location of Steps
The lowest step shall be not less than 7 feet 6 inches from the ground line and above this point steps shall be placed, with spacing between steps on the same side of the pole not exceeding 36 inches, at least to that conductor level above which only circuits operated and maintained by one party remain. Steps shall be so placed that runs or risers do not interfere with the free use of the steps.
Exception: Steps are not required in a Supply utility's designated space when a third party Antenna is affixed above supply conductors.
GO 95, Rule 92.1-F(2)
Proposed Final in P.07-07-020
92.1 Vertical Clearances
F. Between Conductors, Cables, Messengers and Miscellaneous Equipment)
(2) Cable Terminals or Metal Boxes: On jointly used poles, all parts of metal communication cable terminals, metal boxes or similar equipment shall maintain vertical clearances from conductors not less than those specified in Table 2, Col. C, Cases 8 to 13 inclusive.
Exception: The minimum vertical distance between all parts of such metal terminals, boxes or similar equipment which are 8 inches or more from the center line of pole and are supported by cable and/or messenger alone can be reduced to not less than 1 inch by mutual agreement between the affected owners (see Rule 38, Table 2, Case 8, Column C).
For clearance between street light drop wires and cables, other conductors, and metal boxes see Rules 58.5-B3 and 92.1-F5.
For vertical clearances between Antennas and associated elements located above supply and communication lines see Rule 38, Table 2, Case 21.
GO 95, Rule 38, Table 2, Case 21
Proposed Final in P.07-07-020
Case No. |
Nature of Class and Class and Voltage of Wire, Cable or Conductor Concerned |
A Span Wires, Guys and Messengers |
B Trolley Contact Conductors 0-750 Volts |
C Communication Conductors (Including Open Wire, Cables and Service Drops |
D 0 - 750 Volts (Including Service Drops) and Trolley Feeders (a) |
E 750 - 7,500 Volts |
F 7,500 - 20,000 Volts |
G 20,000 - 35,000 Volts |
H 35,000 - 75,000 Volts |
I 75,000 - 150,000 Volts |
J 150,000 - 300,000 Volts |
Vertical clearance above supply and/or communication lines |
|||||||||||
21 |
Antennas and associated elements on the same support structure. (tt, xx) |
24 (ww) |
48 (ww) |
24 (uu) |
48 (ww) |
96 (ww, zz) |
96 (ww, zz) |
120 (ww, yy) |
120 (vv, ww) |
- |
- |
(tt) Clearances for supply antennas from supply and communication lines ... 58.6 and 54.4-G
(uu) May be reduced to 10 inches for cables installed/operated by antenna owner.
(vv) Up to 50 kV.
(ww) Pole-top antenna lead-in wires, drip loops or incidental wiring shall not extend more than 12 inches below the specified clearance.
(xx) For clearances below supply and communication lines and between supply and communication lines see Rule 94.5A - B.
(yy) May be reduced to 96 inches for circuits up to 22,500 volts.
(zz) May be reduced to 72 inches for circuits up to 22,500 volts provided the antenna is suitably isolated. Where a reduction to 72 inches is allowed, the clearance for associated risers and vertical runs specified in 94.9-B2 may be reduced to 5 feet.
ATTACHMENT - B
Strikeout/Underline Revisions
Developed in R.07-12-001 Workshops
GO 95, Rule 94 (Antennas)
Strikeout / Underline Revisions
94 Antennas
94.1 Definition (See Rule 20.0)
94.2 Maintenance and Inspection (See Rules 31.1 and 31.2)
94.3 General Requirements
On joint use poles supporting Class T, C, L or H Circuits (up to 50 kV), the following shall apply:
A. Antennas shall meet the requirements of Class C equipment, unless otherwise specified in this rule.
B. All associated elements of the antenna (e.g. associated cables, messengers, and pole line hardware) shall meet the requirements of Class C circuits.
C. Support elements (e.g. arms, braces, brackets, hardware) and pole-top extensions shall conform to the requirements of Section IV.
Note: Support elements (e.g. arms, braces, brackets, hardware) and pole-top extensions installed above supply lines shall must meet Grade "A" requirements and safety factors specified in Rule 44 Table 4.
(2) Conform to the requirements of Section IV.
B. Support elements (e.g. arms, braces, brackets, pole top extensions, hardware) installed above or below communication lines (where supply lines are not attached) must:
(1) Meet Grade F requirements.
(2) Conform to the requirements of Section IV.
94.5 4 Clearances
A. Antennas and supporting elements (e.g. crossarms, brackets) below supply lines shall maintain a vertical clearance of 6 feet from Supply Conductors operating at 0 -50kV. (See Figure 94-1)
B. Antennas and supporting elements (e.g. crossarms, brackets) below communication lines shall maintain a 2 ft. vertical separation from communication conductors and equipment. (See Figure 94-12)
C. Antennas, associated equipment (e.g. terminations, enclosures) and support elements installed above supply lines and/or communication lines of different ownership attached to the same structure shall maintain the vertical clearances specified in Rule 38, Table 2, Case 21, Columns A - H.
Note: Other vertical clearances between communication equipment and supply lines are specified in Rule 92.1-F (2).
D. Antennas, associated equipment (e.g. terminations, enclosures) and support elements, installed above supply lines and/or communication lines of different ownership, shall maintain the radial clearances from unattached supply and communication lines specified in Rule 38, Table 2, Case 3.
E. Antennas shall maintain a 2 ft. horizontal clearance from centerline of pole when affixed between supply and communication lines or below communication lines. (See Figure 94-1 and 94-2)
F. Horizontal clearances from centerline of the pole for Antennas, associated equipment and support elements, affixed between supply lines or at the top of a climbable pole, are not specified, but must be arranged so that qualified persons may climb the pole may be climbed structure safely.
G. Antennas shall have a vertical clearance above ground as specified in Rule 37, Table 1, Column B, Cases 1 - to- 6a. (See Figure 94-1)
94.6 5 Marking
A. No antenna owner or operator shall install an antenna on a joint use pole unless such installation is subject to an agreement with the pole owner(s) that includes marking requirements that are substantially similar to and achieve at least the same safety standards as those set forth in Appendix H to GO 95.
B. Joint use poles shall be marked with a sign for each antenna installation as follows:
(1) Identification of the antenna operator.
(2) A 24-hour contact number of antenna operator for Emergency or Information.
(3) Unique identifier of the antenna installation.
94.7 6 Climbing Space
A. Climbing space above supply lines shall be maintained in accordance with Rule 54.7-A to:
(1) The bottom of the Antenna (including associated support elements) if affixed less than eight inches from the surface of the pole at the top of the pole or pole-top extension.
(2) The top of the pole or pole-top extension if the Antenna (including associated support elements) is affixed more than eight inches from the surface of the pole or pole-top extension.
(3) The bottom of the uppermost Antenna (including associated support elements) if multiple Antennas are present at different levels above supply lines. (See Figure 94.3)
B. Climbing space above communication lines shall be maintained in accordance with Rule 84.7 to:
(1) The bottom of the Antenna (including associated support elements) at the top of the pole or pole-top extension when affixed less than eight inches from the surface of the pole.
(2) The top of the pole or pole-top extension if the Antenna (including associated support elements) is affixed more than eight inches from the surface of the pole or pole-top extension.
(3) The bottom of the uppermost Antenna (including associated support elements) if multiple Antennas are present at different levels.
94.8 7 Stepping (See Rule 91.3)
94.9 8 Risers and Vertical Runs
A. Risers and vertical runs passing supply lines and/or equipment/or or communication lines, or space typically occupied by supply or communication lines, and and/or equipment on nonmetallic structures (e.g. single wood, concrete, composite, fiberglass poles or multiple pole configurations) shall be suitably covered throughout its their length; shall occur on a single pole; and shall be installed outside the climbing space; and shall be constructed and maintained in accordance with Rules 54.6-D 1, 2, 3 and 5.
(1) Associated cable runs extending to an adjacent structure or building shall be bonded to existing communication cables and messengers and effectively grounded at the originating structure. (Ssee Rule 83.4). Where communication guard arm construction exists, the protective covering shall extend below the guard arm.
B. The suitable protective covering (see Rule 22.8) for risers and vertical runs passing supply lines or space typically occupied by supply lines and/or equipment shall extend no less than: (Ssee Figure 94.13):
(1) 3 ft. above lines energized from 0 - 750 Volts.
(2) 7 6 ft. above lines energized from 750 - 22,500 35,000 Volts.
(3) 9 ft. above lines energized from 22,500 35,000 - 50,000 Volts.
C. Risers and vertical runs passing supply lines and/or equipment or communication lines, or space typically occupied by supply or communication lines and/or equipment, on metallic structures shall occur on a single structure, and be installed outside the climbing space in accordance with Rule 54.6-D 4.
94.10 9 De-energizing
No antenna owner or operator shall install an antenna on a joint use pole unless such installation is subject to an agreement with the pole owner(s) that includes de-energizing protocols that are substantially similar to and achieve at least the same safety standards as set forth in Appendix H to GO 95.
Exceptions: Antennas utilized by utilities for the sole purpose of operating and monitoring their supply system are exempt from this rule and shall only meet the construction and clearance requirements of supply equipment.
Antennas embedded in or attached to communication cables and messengers are exempt from this rule and shall only meet the construction requirements for Class C circuits.
PRC #2 - GO 95 Rule 91.3-B (Stepping)
Strikeout / Underline Revisions
91.3 Stepping
B. Location of Steps
The lowest step shall be not less than 7 feet 6 inches from the ground line and above this point steps shall be placed, with spacing between steps on the same side of the pole not exceeding 36 inches, at least to that conductor level above which only circuits operated and maintained by one party remain. Steps shall be so placed that runs or risers do not interfere with the free use of the steps.
Exception: Steps are not required in a Supply utility's designated space when a third party above the uppermost Class C circuit where an Antenna is affixed above supply conductors.
GO 95, Rule 92.1-F(2) (Vertical Clearances)
Strikeout / Underline Revisions
92.1 Vertical Clearances
F. Between Conductors, Cables, Messengers and Miscellaneous Equipment)
(2) Cable Terminals or Metal Boxes: On jointly used poles, all parts of metal communication cable terminals, metal boxes or similar equipment shall maintain vertical clearances from conductors not less than those specified in Table 2, Col. C, Cases 8 to 13 inclusive.
Exception: The minimum vertical distance between all parts of such metal terminals, boxes or similar equipment which are 8 inches or more from the center line of pole and are supported by cable and/or messenger alone can be reduced to not less than 1 inch by mutual agreement between the affected owners (see Rule 38, Table 2, Case 8, Column C).
For clearance between street light drop wires and cables, other conductors, and metal boxes see Rules 58.5-B3 and 92.1-F5.
For vertical clearances between Antennas and associated elements located above supply and or communication lines see Rule 38, Table 2, Case 21 and Rule 94.4.
GO 95, Rule 38, Table 2, Case 21
Strikeout / Underline Revisions
Case No. |
Nature of Class and Class and Voltage of Wire, Cable or Conductor Concerned |
A Span Wires, Guys and Messengers |
B Trolley Contact Conductors 0-750 Volts |
C Communication Conductors (Including Open Wire, Cables and Service Drops) |
D 0-750 Volts (Including Service Drops) and Trolley Feeders (a) |
E 750 - 7,500 Volts |
F 7,500 - 20,000 Volts |
G 20,000 - 35,000 Volts |
H 35,000 - 75,000 Volts |
I 75,000 - 150,000 Volts |
J 150,000 - 300,000 Volts |
Vertical clearance above supply and/or communication lines |
|||||||||||
21 |
Antennas and associated elements on the same support structure. (tt, |
24 (vv) |
48 ( |
24 ( |
48 ( |
|
|
|
120 (vv, yy, |
- |
- |
(tt) For Antennas utilized by utilities for the sole purpose of operating and monitoring their supply system see Rules 54.4-G and 58.6. Clearances for supply antennas from supply and communication lines ... 58.6 and 54.4-G
(uu) For clearances below supply and communication lines see Rules 94.4-A and 94.4-B and between supply and communications lines see Rules 94.5-A and 94.5-B.
(vv) Pole top Antenna Clearances for exposed lead in wires, drop loops or incidental associated cables wiring may be reduced by shall not extend more than 12 inches below the specified clearance.
(ww) May be reduced to 10 inches for cables installed/operated by antenna Antenna owner/operator.
(vv xx) Clearance from service drop point of attachment on structure to Antenna(s) and associated supporting elements may be reduced to 10 inches.
(yy) Up to 50 kV.
(ww) Pole top antenna lead-in wires, drip loops or incidental wiring shall not extend more than 12 inches below the specified clearance.
(xx) For clearances below supply and communication lines and between supply and communication lines see Rule 94.5A - B.
(yy) May be reduced to 96 inches for circuits up to 22,500 volts.
(zz) May be reduced to 72 inches for circuits up to 22,500 volts provided the antenna is suitably isolated. Where a reduction to 72 inches is allowed, the clearance for associated risers and vertical runs specified in 94.9-B2 may be reduced to 5 feet.
ATTACHMENT - C
Final Version of GO 95 Rules
Developed in R.07-12-001 Workshops
PRC #1 - GO 95, Rule 94 (Antennas)
Proposed Final
94 Antennas
94.1 Definition (See Rule 20.0)
94.2 Maintenance and Inspection (See Rules 31.1 and 31.2)
94.3 General Requirements
On joint use poles supporting Class T, C, L or H Circuits (up to 50 kV), the following shall apply:
A. Antennas shall meet the requirements of Class C equipment, unless otherwise specified in this rule.
B. All associated elements of the antenna (e.g. associated cables, messengers) shall meet the requirements of Class C circuits.
C. Support elements (e.g. arms, braces, brackets, hardware) and pole-top extensions shall conform to the requirements of Section IV.
Note: Support elements (e.g. arms, braces, brackets, hardware) and pole-top extensions installed above supply lines shall meet Grade "A" requirements and safety factors specified in Rule 44, Table 4.
94.4 Clearances
A. Antennas and support elements below supply lines shall maintain a vertical clearance of 6 feet from Supply Conductors operating at 0 -50kV. (See Figure 94-1)
B. Antennas and support elements below communication lines shall maintain a 2 ft. vertical separation from communication conductors and equipment. (See Figure 94-1)
C. Antennas, associated equipment (e.g. terminations, enclosures) and support elements installed above supply lines and/or communication lines of different ownership attached to the same structure shall maintain the vertical clearances specified in Rule 38, Table 2, Case 21, Columns A - H.
Note: Other vertical clearances between communication equipment and supply lines are specified in Rule 92.1-F(2).
D. Antennas, associated equipment (e.g. terminations, enclosures) and support elements, installed above supply lines and/or communication lines of different ownership, shall maintain the radial clearances from unattached supply and communication lines specified in Rule 38, Table 2, Case 3.
E. Antennas shall maintain a 2 ft. horizontal clearance from centerline of pole when affixed between supply and communication lines or below communication lines. (See Figure 94-1)
F. Horizontal clearances from centerline of the pole for Antennas, associated equipment and support elements, affixed between supply lines or at the top of a climbable pole, are not specified, but must be arranged so that the pole may be climbed safely.
G. Antennas shall have a vertical clearance above ground as specified in Rule 37, Table 1, Column B, Cases 1 - 6a. (See Figure 94-1)
94.5 Marking
A. No antenna owner or operator shall install an antenna on a joint use pole unless such installation is subject to an agreement with the pole owner(s) that includes marking requirements that are substantially similar to and achieve at least the same safety standards as those set forth in Appendix H to GO 95.
B. Joint use poles shall be marked with a sign for each antenna installation as follows:
(1) Identification of the antenna operator.
(2) A 24-hour contact number of antenna operator for Emergency or Information.
(3) Unique identifier of the antenna installation.
94.6 Climbing Space
A. Climbing space above supply lines shall be maintained in accordance with Rule 54.7-A to:
(1) The bottom of the Antenna (including associated support elements) if affixed less than eight inches from the surface of the pole at the top of the pole or pole-top extension.
(2) The top of the pole or pole-top extension if the Antenna (including associated support elements) is affixed more than eight inches from the surface of the pole or pole-top extension.
(3) The bottom of the uppermost Antenna (including associated support elements) if multiple Antennas are present at different levels above supply lines.
B. Climbing space above communication lines shall be maintained in accordance with Rule 84.7 to:
(1) The bottom of the Antenna (including associated support elements) at the top of the pole or pole-top extension when affixed less than eight inches from the surface of the pole.
(2) The top of the pole or pole-top extension if the Antenna (including associated support elements) is affixed more than eight inches from the surface of the pole or pole-top extension.
(3) The bottom of the uppermost Antenna (including associated support elements) if multiple Antennas are present at different levels.
94.7 Stepping (See Rule 91.3)
94.8 Risers and Vertical Runs
A. Risers and vertical runs passing supply lines and/or equipment or communication lines and/or equipment on nonmetallic structures (e.g. single wood, concrete, composite, fiberglass poles or multiple pole configurations) shall be suitably covered throughout their length; shall occur on a single pole; shall be installed outside the climbing space; and shall be constructed and maintained in accordance with Rules 54.6-D 1, 2, 3 and 5.
(1) Associated cable runs extending to an adjacent structure or building shall be bonded to existing communication cables and messengers and effectively grounded at the originating structure (see Rule 83.4). Where communication guard arm construction exists, the protective covering shall extend below the arm.
B. The suitable protective covering (see Rule 22.8) for risers and vertical runs passing supply lines and/or equipment shall extend no less than (see Figure 94.1):
(1) 3 ft. above lines energized from 0 - 750 Volts.
(2) 6 ft. above lines energized from 750 - 35,000 Volts.
(3) 9 ft. above lines energized from 35,000 - 50,000 Volts.
C. Risers and vertical runs passing supply lines and/or equipment or communication lines and/or equipment on metallic structures shall occur on a single structure, and be installed outside the climbing space in accordance with Rule 54.6-D 4.
94.9 De-energizing
No antenna owner or operator shall install an antenna on a joint use pole unless such installation is subject to an agreement with the pole owner(s) that includes de-energizing protocols that are substantially similar to and achieve at least the same safety standards as set forth in Appendix H to GO 95.
Exceptions: Antennas utilized by utilities for the sole purpose of operating and monitoring their supply system are exempt from this rule and shall only meet the construction and clearance requirements of supply equipment.
Antennas embedded in or attached to communication cables and messengers are exempt from this rule and shall only meet the construction requirements for Class C circuits.
PRC #2 - GO 95 Rule 91.3-B (Stepping)
Proposed Final
91.3 Stepping
B. Location of Steps
The lowest step shall be not less than 7 feet 6 inches from the ground line and above this point steps shall be placed, with spacing between steps on the same side of the pole not exceeding 36 inches, at least to that conductor level above which only circuits operated and maintained by one party remain. Steps shall be so placed that runs or risers do not interfere with the free use of the steps.
Exception: Steps are not required above the uppermost Class C circuit where an Antenna is affixed above supply conductors.
PRC #3 - GO 95, Rule 92.1-F(2) (Vertical Clearances)
Proposed Final
92.1 Vertical Clearances
F. Between Conductors, Cables, Messengers and Miscellaneous Equipment)
(2) Cable Terminals or Metal Boxes: On jointly used poles, all parts of metal communication cable terminals, metal boxes or similar equipment shall maintain vertical clearances from conductors not less than those specified in Rule 38, Table 2, Col. C, Cases 8 to 13 inclusive.
Exception: The minimum vertical distance between all parts of such metal terminals, boxes or similar equipment which are 8 inches or more from the center line of pole and are supported by cable and/or messenger alone can be reduced to not less than 1 inch by mutual agreement between the affected owners (see Rule 38, Table 2, Case 8, Column C).
For clearance between street light drop wires and cables, other conductors, and metal boxes see Rules 58.5-B3 and 92.1-F5.
For clearances between Antennas and supply or communication lines see Rule 38, Table 2, Case 21 and Rule 94.4.
PRC #4 - GO 95, Rule 38, Table 2, Case 21
Proposed Final
Case No. |
Nature of Class and Class and Voltage of Wire, Cable or Conductor Concerned |
A Span Wires, Guys and Messengers |
B Trolley Contact Conductors 0-750 Volts |
C Communication Conductors (Including Open Wire, Cables and Service Drops) |
D 0-750 Volts (Including Service Drops) and Trolley Feeders (a) |
E 750 - 7,500 Volts |
F 7,500 - 20,000 Volts |
G 20,000 - 35,000 Volts |
H 35,000 - 75,000 Volts |
I 75,000 - 150,000 Volts |
J 150,000 - 300,000 Volts |
Vertical clearance above supply and/or communication lines |
|||||||||||
21 |
Antennas and associated elements on the same support structure. (tt, uu) |
24 (vv) |
48 (vv) |
24 (ww) |
48 (vv, xx) |
72 |
72 |
72 |
120 ( vv, yy) |
- |
- |
(tt) For Antennas utilized by utilities for the sole purpose of operating and monitoring their supply system see Rules 54.4-G and 58.6.
(uu) For clearances below supply and communication lines see Rules 94.4-A and 94.4-B
(vv) Clearances for exposed associated cables may be reduced by 12 inches.
(ww) May be reduced to 10 inches for cables installed by Antenna owner/operator.
(xx) Clearance from service drop point of attachment on structure to Antenna(s) and associated supporting elements may be reduced to 10 inches.
(yy) Up to 50 kV.
ATTACHMENT - D
~
Rationales for GO 95 Rules
Developed in R.07-12-001 Workshops
Introduction
Many of the proposed revisions to Proposed Rule Changes (PRCs) 1-4 developed during the technical workshops stemmed from the central topic of dispute (i.e., "vertical clearances"), while other revisions are more editorial in nature and intended to clarify conditions and/or help ensure continuity within the rule itself or the within the context of other General Order (GO) 95 requirements.
The rationales provided herein are not intended for use as "rule interpretations," but should be viewed as a high-level account of the decisions reached by the Parties attending the workshops.
Final Version - PRC #1
94.3-B: This revision is linked to new 94.3-C and demonstrates the differences between "associated elements" and "support elements".
New 94.3-C: This revision would add a new Subsection "C" and encapsulate the intent of the deleted Section 94.4 (proposed by the Rules Committee). This revision demonstrates the differences between "support elements" and "associated elements," and sets pole-top extensions apart from both categories.
The fine print note is needed to ensure that the material strengths and safety factors of support elements and pole-top extensions meet the requirements as those for Supply utilities constructing at the top of a joint-use utility pole.
New 94.4: In addition to being renumbered from (original) 94.5, several formatting and editorial corrections were made to Subsections A, B, E, F and G, due in part to the recommendations made by the CPSD and PG&E.
Also, the references to multiple Figures (94.1 - 94.5) were replaced with references to a new composite Figure 94.1.
New 94.5: Renumbered from (original) 94.6.
New 94.6: Renumbered from (original) 94.7, a reference to (original) Figure 94.3 was also removed as parties agreed this reference was no longer needed.
New 94.7: Renumbered from (original) 94.8. The text -"Exception to" was deleted as parties agreed the entirety of Rule 91.3 should be referenced.
New 94.8: Renumbered from (original) 94.9. Subsections A, A(1), B and C were modified to address PG&E and CPSD comments and to clarify the proper application of these requirements
The revisions to Subsection B(2) were made in conjunction with the revisions to PRC #4 to clarify that a wireless antenna's communication cables and conductors must be encased by suitable protective covering within the ascribed 6 ft. vertical clearance between wireless antennas and 750 - 35,000 Volt supply lines.
The revision to Subsection B(3) was made to reconcile the revised voltage ranges now expressed in B(2).
The revisions to Subsection B(3) were made to reconcile the text with the revisions to Subsection A.
New 94.9: Renumbered from (original) 94.10.
Final Version - PRC #2
91.3-B, Exception: This revision was made in response to a CPSD comment regarding the use of the term "designated space" and still allows for the omission of pole steps when a wireless antenna is installed between or above supply lines.
Final Version - PRC #3
92.1-F(2): The revision to the final paragraph reconciles the editorial revisions proposed in Rule 94 and adds a reference to same.
Final Version - PRC #4
Columns A - D and H: No changes were made to the vertical clearances originally expressed in PRC #4. The principle revisions involve the Footnote designations.
Columns E - G: These revisions specify that a minimum 6 ft. vertical clearance is required between wireless antennas installed above supply lines operating at 750 - 35,000 Volts. Notably, the Footnote designations have been removed as there are no allowable vertical clearance reductions for these voltage ranges.
Footnotes:
New "tt" - text revised to match Rule 94 Exception.
New "uu" - Revised text from (original) "xx". Renumbered to support alphabetical rearrangement of Footnotes within the Case. An editorial revision was also made to the cited rules.
New "vv" - revised from (original) "ww" for editorial purposes. New text encompasses previously referenced lead-in wires, drip loops and incidental wiring into new term "associated cables". This footnote retains the original option of reducing the expressed vertical clearance for these cables by 12 inches.
New "ww" - revised from (original) "uu" for editorial purposes. Editorial change clarifies the excepted vertical clearance is applicable to cables installed by Antenna's owner/operator.
New "xx" - allows for a reduction in the prescribed vertical clearance under a specific set of circumstances.
New "yy" - revised from (original) "vv" for editorial purposes. No changes to text.
Original "zz" - deleted, as workshop attendees agreed to clearances for Columns E - G.
ATTACHMENT - E
~
R.07-12-001 Workshop Attendees
April 03 - 04, 2008 Workshops - San Francisco, CA
ATTENDEES: |
Jerome Candelaria (CCTA) |
Joe Kieren (AT&T-CA) |
Don Hooper (ES&C Inc. / CCTA) |
Ellen Magnie (AT&T-CA) |
David Pierce (American Tower) |
Tony Lloyd (AT&T-CA) |
Fred Barvarz (Anaheim) |
David Miller (AT&T-CA) |
Andy Campbell (CPUC) |
Kent Tracey (AT&T-CA) |
Raymond Fugere (CPUC/CPSD) |
Robert Wolfe (AT&T-CA) |
Jane Whang (CPUC) |
Cindy Manheim (AT&T Mobility) |
Justin Wynne (CMUA) |
Bob Gundermann (Crown Castle) |
Natasha Ernst (ExteNet Systems) |
Bob Ritter (Crown Castle) |
Anita Taff-Rice (ExteNet Systems) |
Rich Rolita (Crown Castle) |
Randy Heldoorn (IBEW 47) |
Nick Goldman (NextG Networks) |
Landis Martilla (IBEW 1245) |
Nicole Mason (NextG Networks) |
Steve Bowen (NewPath Networks/BLG) |
David Marne (NextG Networks) |
Jacqueline McCarthy (PCIA) |
Richard Walker (NextG Networks) |
Leon Bloomfield (T-Mobile) |
Deanna Adams (Pacific Corp) |
Marc Brock (PG&E) |
Heide Caswell (Pacific Corp) |
Pat Geoffrey (PG&E) |
Ryan Flynn (Pacific Corp) |
Grant Guerra (PG&E) |
Larry Chow (SCE) |
Charlie Poston (PG&E) |
Steve Ford (SCE) |
Paul Alvarado (SDG&E) |
Robert F. LeMoine (SCE) |
Rebecca Giles (SDG&E) |
Sam Stonerock (SCE) |
John Pacheco (SDG&E) |
Kristen Jacobsen (Sprint PCS) |
Greg Walters (SDG&E) |
Jim Graham (Verizon Wireless) |
Ron Boyer (Time Warner Cable) |
Michael Bagley (Verizon Wireless) |
|
Via teleconference: |
|
Barry McCarthy (Anaheim / NCPA) |
Tom Dell (BMS) |
Stella Zahariudakis (PG&E) |
Steve Rodriguez (T-Mobile) |
Patty Larson (PG&E) |
|
April 16, 2008 Workshop - San Diego, CA
ATTENDEES: |
|
Dave Miller (AT&T-CA) |
Tom Dell (BMS Communications) |
Robert Wolfe (AT&T-CA) |
Don Hooper (CCTA/ ES&C Inc.) |
Kent Tracey (AT&T-CA) |
Jackie Hooper (CCTA/ ES&C Inc.) |
Jay Baumler (CES) |
Jerome Candelaria (CCTA) |
Raymond Fugere (CPUC/CPSD) |
Natasha Ernst (ExteNet Systems) |
Rich Rolita (Crown Castle) |
Anita Taff-Rice (ExteNet Systems) |
Randy Heldoorn (IBEW 47) |
Larry Chow (SCE) |
Steve Bowen (NewPath/ BLG) |
Sam Stonerock (SCE) |
Nicole Mason (NextG Networks) |
Paul Alvarado (SDG&E) |
Richard Walker (NextG Networks) |
Carlos Castro (SDG&E) |
Heide Caswell (Pacific Corp) |
Rebecca Giles (SDG&E) |
David Holt (PacifiCorp) |
John Pacheco (SDG&E) |
Pat Geoffrey (PG&E) |
Jim Turman (SDG&E) |
Ron Boyer (Time Warner Cable) |
Greg Walters (SDG&E) |
Steve Rodriguez (T-Mobile) |
Alvin White (SDG&E) |
Malcolm Brown (Verizon Wireless) |
|
Via teleconference: |
|
Andy Campbell (CPUC) |
Cindy Manheim (AT&T Mobility) |
Jane Whang (CPUC) |
Suzanne Toller (DWT/Crown Castle) |
Ryan Flynn (Pacific Corp) |
Susan O'Brien (NCPA/Anaheim) |
Grant Guerra (PG&E) |
May 01, 2008 Workshop - San Francisco, CA
ATTENDEES: |
|
Dave Miller (AT&T-CA) |
Suzanne Toller (DWT/Crown Castle) |
Raymond Fugere (CPUC/CPSD) |
Anita Taff-Rice (ExteNet Systems) |
Rich Rolita (Crown Castle) |
Steve Bowen (NewPath/ BLG) |
Marc Brock (PG&E) |
Paul Alvarado (SDG&E) |
Pat Geoffrey (PG&E) |
Carlos Castro (SDG&E) |
Grant Guerra (PG&E) |
Rebecca Giles (SDG&E) |
Sam Stonerock (SCE) |
John Pacheco (SDG&E) |
Via teleconference: |
|
Robert Wolfe (AT&T-CA) |
Barry McCarthy (Anaheim / NCPA) |
Kent Tracey (AT&T-CA) |
Jerome Candelaria (CCTA) |
Cindy Manheim (AT&T Mobility) |
Tom Dell (BMS Communications) |
Don Hooper (CCTA/ ES&C Inc.) |
Nicole Mason (NextG Networks) |
Justin Wynne (CMUA) |
Heide Caswell (Pacific Corp) |
Natasha Ernst (ExteNet Systems) |
Kristen Jacobson (Sprint PCS) |
Larry Chow (SCE) |
Steve Rodriguez (T-Mobile) |
Robert LeMoine (SCE) |
18 The workshop participants on whose behalf SCE files this report are: AT&T - California, AT&T Mobility, California Cable & Telecommunications Association (CCTA), California Municipal Utility Association (CMUA), City of Anaheim, Consumer Protection & Safety Division (CPSD), Crown Castle USA, ExteNet Systems, IBEW 47, IBEW 1245, Northern California Power Agency (NCPA), NewPath Networks, NextG Networks, PacifiCorp, Pacific Gas & Electric Company (PG&E), San Diego Gas & Electric Company (SDG&E), Southern California Edison Company (SCE), Sprint-Nextel, Time Warner Cable, T-Mobile, Verizon - California, and Verizon Wireless. The foregoing workshop participants have authorized SCE to sign and submit this filing on their behalf.
19 The workshop participants also wish to thank PG&E for hosting the prehearing conference "meet and confer session", as well as AT&T - California, SDG&E and the CPSD for hosting technical workshops.
20 See Attachment E.
21 The CPSD did not agree with the other attendees' views regarding the applicability of Rule 15.2.