4. Description of the Property Proposed
to be Condemned

Wild Goose proposes to condemn additional narrow strips of property to enable it to adjust its existing 30-foot easement to accommodate the spacing required between the existing pipeline and the new loop pipeline it needs to build to complete its expansion project. At the conclusion of the construction and easement adjustments, Wild Goose will have two parallel pipelines located at opposite sides of a 30-foot easement across Roseville Land's property.1

The legal descriptions of the four parcels are contained in Exhibit A to the application. Parcels one and two are permanent subsurface utility and gas transmission pipeline easements, each 30 feet wide, that follow different sections of the existing pipeline across Roseville Land's property. Parcels three and four are 60 feet wide temporary construction easements to allow construction of the additional facilities. The four parcels are depicted in Attachment A to today's decision.

1 The easement also crosses property of three other landowners, with which Wild Goose has reached agreements for compensation.

Previous PageTop Of PageNext PageGo To First Page