IV. FINDINGS

Based upon the evidence made available to it, it is CPSD's opinion that, at the time of this incident, SDG&E's 69 kV overhead conductors supported on poles Z416675 and Z416676 contacted each other in violation of GO 95, Rule 38.

CPUC GO 95, Rule 31.1, Design, Construction and Maintenance, states:

    "Electrical supply and communication systems shall be designed, constructed, and maintained for their intended use, regard being given to the conditions under which they are to be operated, to enable the furnishing of safe, proper, and adequate service.

    For all particulars not specified in these rules, design, construction, and maintenance should be done in accordance with accepted good practice for the given local conditions known at the time by those responsible for the design, construction, or maintenance of [the] communication or supply lines and equipment.

    All work performed on public streets and highways shall be done in such a manner that the operations of other utilities and the convenience of the public will be interfered with as little as possible and no conditions unusually dangerous to workmen, pedestrians or others shall be established at any time."

GO 95, Rule 38, Minimum Clearances of Wires from Other Wires, states:

    "The minimum vertical, horizontal or radial clearances of wires from other wires shall not be less than the values given in Table 2 and are based on a temperature of 60° F. and no wind. ...

    The clearances in Table 2 shall in no case be reduced more than 10 percent because of temperature and loading as specified in Rule 43 or because of a difference in size or design of the supporting pins, hardware or insulators. All clearances of less than 5 inches shall be applied between surfaces, and clearances of 5 inches or more shall be applied to the center lines of such items."

GO 95, Table 2, Case 17H, requires 24 inches of radial separation between conductors of the same circuit on the same pole.

The winds at the time of the incident were not uncommon for the area and should not have caused the clearance to be reduced by more than 2.4 inches.

Based upon the evidence before it, it is CPSD's opinion that SDG&E's 69kV overhead conductors did not have the minimum separation required by GO 95, Rule 38.

It is also CPSD's opinion that SDG&E violated GO 95, Rule 31.1 relative to ensuring that its facilities are designed, constructed, and maintained, in order to enable safe, proper and adequate service.

V. CONCLUSION AND RECOMMENDATIONS

As a result of this investigation, it is CPSD's opinion that SDG&E's 69 kV overhead conductors contacted each other on October 21, 2007 between SDG&E poles Z416675 and Z416676.

It is also CPSD's opinion that SDG&E failed to design, construct, and maintain the affected lines in accordance with GO 95, Rule 31.1 and that SDG&E failed to maintain the clearances between conductors required by GO 95, Rule 38.

CPSD recommends that the CPUC issue an Order Instituting Investigation (OII) into this matter to examine the extent to which SDG&E violated General Order 95, Rule 31.1 and Rule 38. The OII should also consider whether or not SDG&E should conduct a survey of its transmission and distribution lines to determine all the locations where conductor clearances are potentially in violation of Rule 38 and adopt remedial measures, where necessary, to ensure that conductors maintain the minimum required clearances.

CPSD also believes that SDG&E's unwillingness to provide immediate access to witnesses and evidence prevented CPSD from conducting a more timely investigation.

CPSD also recommends that the CPUC include as an issue in the OII the lack of cooperation of SDG&E and issue an order clarifying that utilities must cooperate fully with CPSD and provide immediate access to witnesses, sites, or any other evidence requested by the CPUC in the course of a CPSD investigation.

California Public Utilities Commission

Consumer Protection and Safety Division

Utilities Safety and Reliability Branch

Investigation of the Rice Fire

Fallbrook, California

October 2007

Prepared by

Mahmoud (Steve) Intably, Utilities Engineer

September 2, 2008

Table of Contents

Page

I. EXECUTIVE SUMMARY

On October 22, 2007, a sycamore tree limb broke and fell on San Diego Gas and Electric's (SDG&E) 12 kV overhead conductors between SDG&E poles 213072 and 112340, causing the conductors to break and fall to the ground. The July 9, 2008 California Department of Forestry and Fire Protection's (CalFire) report on the fires (CalFire Report) determined that the Rice Fire was started by downed power lines located between SDG&E poles 213072 and 112340.

The Consumer Protection and Safety Division (CPSD) of the California Public Utilities Commission (CPUC) investigated this incident. CPSD found that SDG&E's tree trimming contractor (Davey Tree) had inspected the tree which caused the fire, and had determined that the tree be should be trimmed within three months from the time of the inspection. SDG&E failed to trim the tree within the three-month timeframe, and it is CPSD's opinion that SDG&E was in violation of CPUC General Order (GO) 95, Rule 31.1 at the time of the incident. GO 95, Rule 31.1 requires a utility's facilities to be designed, constructed, and maintained, in order to enable safe, proper and adequate service.

CPSD also believes that SDG&E's unwillingness to provide immediate access to witnesses and evidence prevented CPSD from conducting a more timely investigation.

CPSD recommends that the CPUC issue an Order Instituting Investigation (OII) into this matter to examine the extent to which SDG&E violated GO 95, Rule 31.1 with respect to its tree trimming practices. CPSD also recommends that the CPUC include as an issue in the OII the lack of cooperation of SDG&E and issue an order clarifying that utilities must cooperate fully with CPSD and provide immediate access to witnesses, sites, or any other evidence requested by the CPUC in the course of a CPSD investigation.

II. INTRODUCTION

On October 22, 2007, at approximately 4:00 a.m., the Rice Fire started in Fallbrook. SDG&E records show that faults on its lines caused an interruption of power to customers in the Fallbrook area at around the same time. The CalFire Report states that the Rice Fire started when a limb from a Sycamore tree broke and fell through a 12 kV overhead conductor located between SDG&E poles 213072 and 112340.

The CalFire Report states that the Rice Fire burned approximately 9,472 acres, destroyed approximately 206 homes, 2 commercial properties, and 40 outbuildings.

III. REPORT OF INVESTIGATION CONDUCTED BY
MAHMOUD (STEVE) INTABLY

In late October of 2007, CPSD staff learned that there were multiple fires that occurred within SDG&E's service territory. One of the fires was the Rice Fire that started on October 22, 2007, in Fallbrook. Initially, it was not known which fires were caused by electrical facilities.

On November 6, 2007, I contacted an official of SDG&E and requested that he arrange an inspection at the site of the Rice Fire, and interviews of the SDG&E personnel who witnessed the fire. The SDG&E official informed me that that a representative of SDG&E would meet with me at the site of the fire and show me the SDG&E facilities that were involved. The SDG&E official also informed me that I would not be allowed to interview SDG&E personnel because SDG&E had not yet completed its investigation. He instructed me to contact SDG&E's attorneys in order to determine when CPSD staff would be allowed to interview SDG&E personnel.

On November 7, 2007, SDG&E sent an email to CPSD to report that the Rice Fire started on October 22, 2007, in Fallbrook. The e-mail notification did not include specific details about the cause of the fire.

On November 9, 2007, I met with an SDG&E representative at the site of the Rice Fire's suspected origin and took photographs of utility facilities and damaged property at the site. The SDG&E representative refused to answer specific questions about the fire/incident and informed me that he was only available to show me the site of the fire/incident.

During the week of November 12, 2007, an Assistant General Counsel in CPUC Legal Division management contacted SDG&E's attorney and discussed CPUC jurisdiction and authority. SDG&E's attorney subsequently indicated that he would arrange interviews with SDG&E's employees/witnesses.

In early January 2008, a CalFire investigator informed me that a limb from a sycamore tree broke and fell onto SDG&E's 12 kV overhead conductors starting the fire. SDG&E's attorney agreed that a limb from a sycamore tree fell on the 12 kV line.

On January 25, 2008, SDG&E stated that the broken limb/branch of the sycamore tree had internal rot. SDG&E also provided records to CPSD which indicated that the sycamore tree in question was inspected on July 18, 2007. The records also showed that, at the time of the inspection, the clearance between the sycamore tree and SDG&E's 12 kV overhead conductors ranged from 6 to 7.9 feet, that the tree was estimated to be 80 feet tall, and that the tree was considered a fast grower, with growth rate of 4 to 6 feet per year.

On February 8, 2008, I visited the site of the Rice Fire and found that the sycamore tree was trimmed away from the 12 kV overhead conductors and its height was reduced.

On February 28, 2008, SDG&E responded to a CPSD data request and provided several documents regarding this incident. SDG&E's response included weather data it apparently obtained from the Western Region Climate Center website ( http://www.wrcc.dri.edu/). This weather data reflected that the maximum wind speeds measured on October 21, 2007 were:

- Ammo Dump, California 36.0 mph

- Valley Center, California 50.0 mph

- Ammo Dump, California 49.0 mph

- Valley Center, California 52.0 mph

This weather data also reflected that the maximum wind speeds measured for October 23, 2007:

- Ammo Dump, California 37.0 mph

- Valley Center, California 50.0 mph

I have subsequently researched historic weather data for the affected area and have determined that the above wind speeds are not uncommon for this area.

Beginning in March of 2008, CPSD conducted examinations under oath and interviews of certain SDG&E and Davey Tree witnesses. These witnesses described what they saw and did regarding such topics as: inspecting the sycamore tree, cutting the sycamore tree on October 22, 2008, and the interaction between SDG&E and Davey Tree.

On March 25, 2008, a CPUC Staff Counsel examined a Davey Tree Pre-trim Inspector under oath. During the examination, the Pre-trim Inspector confirmed that he was the individual who inspected the subject sycamore tree on July 18, 2007. The Pre-trim Inspector indicated that the sycamore tree may have had a direct overhang relative to an electric line. He also stated that the sycamore tree "had fairly vigorous growth" towards the lines. The Pre-trim Inspector confirmed records indicating that on July 18, 2007, he stated that the sycamore tree should be trimmed within three months. When asked the basis of this recommendation, he stated: "it had strong growth towards the lines, and I felt it would encroach in the 4 foot distance from the primary line in the facilities within three months."

On April 18, 2008, a CPUC Staff Counsel examined an SDG&E Vegetation Management Program Manager under oath. The SDG&E Vegetation Management Program Manager stated that on October 22, 2007, during the morning hours, he received a call from SDG&E's Fire Coordinator regarding a fire in the Fallbrook area. The Vegetation Management Program Manager stated that he arrived at the scene around 9 or 9:30 am. The Vegetation Management Program Manager indicated that he found three downed wires. He indicated that one of the wires was lying on the ground and the other two were in adjacent trees. In addition, the Vegetation Management Program Manager observed that a tree limb from the sycamore tree had broken. The Vegetation Management Program Manager stated that he contacted Davey Tree and requested a crew to respond to this incident. The Vegetation Management Program Manager further stated that he visited the site on October 23, 2007 and found that the sycamore tree was reduced to two-thirds of its height.

On April 18, 2008, a CPUC Staff Counsel examined an SDG&E Utility Forester under oath. The Utility Forester indicated that on October 22, 2007, he received a call from the Vegetation Management Program Manager, who asked him to supervise Davey Tree's crew that was working on the Sycamore tree in question. The Utility Forester indicated that, upon his arrival at the scene, he requested that the tree trimming crew trim the tree to a level below the assumed height of the wire.

- Palomar 18 mph, gust to 24 mph.

- Valley Center 24 mph, gust to 47 mph.

Throughout the course of this investigation, CPSD communicated with and obtained information from CalFire.

IV. FINDINGS

CPUC GO 95, Rule 31.1, Design, Construction and Maintenance, states:

    "Electrical supply and communication systems shall be designed, constructed, and maintained for their intended use, regard being given to the conditions under which they are to be operated, to enable the furnishing of safe, proper, and adequate service.

    For all particulars not specified in these rules, design, construction, and maintenance should be done in accordance with accepted good practice for the given local conditions known at the time by those responsible for the design, construction, or maintenance of [the] communication or supply lines and equipment.

    All work performed on public streets and highways shall be done in such a manner that the operations of other utilities and the convenience of the public will be interfered with as little as possible and no conditions unusually dangerous to workmen, pedestrians or others shall be established at any time."

Based upon the evidence made available to it, it is CPSD's opinion that a sycamore tree limb broke and fell onto SDG&E's 12 kV overhead conductors located between SDG&E poles 213072 and 112340 and caused the conductors to fall down and start the Rice Fire.

SDG&E asserts that the sycamore tree in question was due to be trimmed by November 1, 2007 because they measure the start date of the 3 months from the date that they formally notified Davey to undertake the trimming of the tree. CPSD disagrees and believes that the sycamore tree, from which the broken limb fell, should have been trimmed before October 22, 2007. CPSD believes that SDG&E's failure to trim the sycamore tree in question, within three months of the inspection, was an unsafe maintenance decision which amounts to a violation of General Order 95, Rule 31.1.

Further, currently available evidence does not establish the clearance between the sycamore tree and SDG&E's conductors, immediately prior to the incident. When the tree was cut, after the incident occurred, it was cut to a height significantly lower than its original height. SDG&E claims that this was done for safety reasons. It is inconclusive as to whether SDG&E complied with the provisions in Rule 35 applicable to clearances.

CPSD also believes that SDG&E's inadequate reporting and its unwillingness to provide immediate access to witnesses and evidence prevented CPSD from conducting a more timely investigation.

V. CONCLUSION AND RECOMMENDATIONS

Based upon the evidence made available to it, it is CPSD's opinion that a sycamore tree limb broke and fell onto SDG&E's 12 kV overhead conductors located between SDG&E poles 213072 and 112340 and caused the conductors to fall down and start the Rice Fire.

It is also CPSD's opinion that SDG&E violated GO 95, Rule 31.1. CPSD was unable to reach an opinion as to whether SDG&E had violated GO 95, Rule 35.

CPSD also believes that SDG&E's unwillingness to provide immediate access to witnesses and evidence prevented CPSD from conducting a more timely investigation.

CPSD recommends that the CPUC issue an Order Instituting Investigation (OII) into this matter to examine the extent to which SDG&E violated GO 95, Rule 31.1 with respect to its tree trimming practices. Included in this OII, the Commission should determine whether or not SDG&E should be directed to immediately review and streamline its vegetation management procedures.

CPSD also recommends that the CPUC include as an issue in the OII the lack of cooperation of SDG&E and issue an order clarifying that utilities must cooperate fully with CPSD and provide immediate access to witnesses, sites, or any other evidence requested by the CPUC in the course of a CPSD investigation.

CERTIFICATE OF SERVICE

I hereby certify that I have this day served a copy of [title of document] in [proceeding number] by using the following service:

[ X ] E-Mail Service: sending the entire document as an attachment to all known parties of record who provided electronic mail addresses.

[ ] U.S. Mail Service: mailing by first-class mail with postage prepaid to all known parties of record who did not provide electronic mail addresses.

Executed on September 2, 2008, at San Francisco, California.

NOTICE

Parties should notify the Process Office, Public Utilities Commission, 505 Van Ness Avenue, Room 2000, San Francisco, CA 94102, of any change of address and/or e-mail address to insure that they continue to receive documents. You must indicate the proceeding number on the service list on which your name appears.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

SERVICE LIST

P07-11-007

Robert.F.LeMoine@sce.com

dj0conklin@earthlink.net

lurick@sempra.com

edm@cpuc.ca.gov

gxh@cpuc.ca.gov

slg0@pge.com

jerome@calcable.org

ssiegel@biologicaldiversity.org

Case.Admin@sce.com

james.lehrer@sce.com

jwmitchell@mbartek.com

atrial@sempra.com

esther.northrup@cox.com

liddell@energyattorney.com

cadowney@san.rr.com

RGiles@semprautilities.com

sjkeene@iid.com

RHager@wss-law.com

DNG6@pge.com

FSC2@pge.com

cem@newsdata.com

regrelcpuccases@pge.com

ens@loens.com

dietrichlaw2@earthlink.net

douglas.garrett@cox.com

mp@calcable.org

mrw@mrwassoc.com

aivancovich@caiso.com

dshonkwiler@caiso.com

btorgan@parks.ca.gov

kdw@woodruff-expert-services.com

blamb@parks.ca.gov

ntilg@parks.ca.gov

rrayb@parks.ca.gov

rgf@cpuc.ca.gov

rim@cpuc.ca.gov

tim@cpuc.ca.gov

Previous PageTop Of PageGo To First Page