SCE and Protestants offered exhibits into the record, which are received herein as Exhibits 1 and 2, respectively.
The Public Scoping Report, Draft EIR, Final EIR, Recirculated Draft EIR and the Recirculated Final EIR will be received into the record of this proceeding as Reference Exhibits A-E, respectively. [These documents are available for inspection on the Commission's website.]39
The testimony is identified as follows and is received into evidence:
Exhibit 1 - SCE's Supplemental Testimony dated April 11, 2008.
Exhibit 2 - Citizens of Sun Lakes Country Club Supplemental Testimony dated April 29, 2008.
Reference Exhibit A - Public Scoping Report issued September , 2007.
Reference Exhibit B - Draft Environmental Impact Report issued December 12, 2007.
Reference Exhibit C - Final Environmental Impact Report issued April 11, 2008.
Reference Exhibit D - Recirculated Draft Environmental Impact Report issued July 9, 2008.
Reference Exhibit E - Recirculated Final Environmental Impact Report issued October 17, 2008.
39 Currently at http://www.cpuc.ca.gov/Environment/info/aspen/elcasco/elcasco.htm