Interconnection study

Measurements

PG&E will place measuring devices on its distribution system in the vicinity of Complainant's premises. These devices will provide PG&E with information regarding loads, currents, and voltages on the part of its distribution system providing service to Complainant and other customers in the area. The measurements will be completed during the week of September 17, 2001.

System model

PG&E will model its distribution system in the vicinity of Complainant's premises. The purpose of this model will be to provide information regarding likely system conditions occurring during fault events. The system model will be completed during the week of September 17, 2001.

Multiple inverter test/data

The Parties will use best efforts to obtain, as soon as possible, any test data reasonably necessary to resolve issues pertaining to the anti-islanding performance of multiple inverters of the type used by Complainant, and in the configuration used by the Complainant. Such data may be obtained from tests conducted by the manufacturer, PG&E or some third party.

20 kVA maximum

Based on engineering judgment and the results of the above described studies and tests, PG&E will evaluate how to address the 20 kVA maximum generator size set forth in Electric Rule 21, Section D.3.a.2 and will submit its evaluation to Complainant. .

Previous PageTop Of PageNext PageGo To First Page