In April 2000, the assigned Commissioner found the following issues to be within the scope of this proceeding:
1. Need for the proposed project including consideration of the decision by the ISO that the project is needed;
2. Assessment of the merits of alternative routes, including route segments located underground, the proposed and alternate routes, and proposed and alternative substation locations;
3. Consideration of the following factors contained in Pub. Util. Code § 1002:
a. Community values;
b. Recreational and park areas;
c. Historical and aesthetic values; and
d. Influence on the environment;
4. Consideration of whether, pursuant to the Commission's General Order (GO) 131-D, the project promotes the safety, health, comfort, and convenience of the public;
5. Jurisdiction over costs, and advisability and amount of a cap on project cost;
6. Whether the project has cumulative and/or growth-inducing impacts.3