There is still much uncertainty regarding the ASR system which won't be resolved until permits are issued.

Cal Am Data Response #50 provides justification for increasing the ASR well estimate $3,000,000 from the 2005 estimate. This cost increase appears reasonable considering design changes and additional technical data that has become available since the 2005 estimate was prepared. Currently, Cal Am is in the process of obtaining the necessary permits in order to access the proposed ASR sites. Once Cal-Am obtains site access and drills the proposed monitoring well, it will be possible to further refine the ASR cost estimates.151

If the Peninsula were not in jeopardy of draconian water reductions imposed by the CDO, some elements of the phased and conditional approval advocated by DRA might be warranted. However the Peninsula cannot afford a significant Project delay given the time constraints arising from the CDO. Financing must be procured and construction must commence as soon as possible.154

In today's case, we are considering a project that must move forward. The seismic risk of the San Clemente Dam must be remedied. There is no uncertainty in that. We have found that where there are regulatory compliance requirements and long-term capital outlays for a project are a foregone conclusion, it is reasonable to authorize the use of the authorized ROR [rate of return] as the AFUDC rate, and it is appropriate to undertake a reasonableness review at the completion of the project.167

When a public agency undertakes a water project, it customarily recovers all of its reasonable, project-related development costs when it bonds or otherwise finances the project, with those costs ultimately being borne by ratepayers. That is just and reasonable because the costs recovered by the agency are part of the costs of the water supply project and hence the costs of providing the water. Notably, such project development costs do not normally include the costs of legal representation in a proceeding before the Commission, nor do they include the necessity of countless meetings and negotiations with other parties, including DRA, because public agencies are not normally required to appear before the Commission in proceedings like this one. MCWD and MCWRA should not be punished because they have partnered with CAW, a Commission-regulated water company, in developing the Regional Desalination Project and participating before the Commission in this proceeding.176

147 Exhibit 363, § 8 at 10; Attachments 3 and 4 to the Settlement Agreement filed on April 7, 2010.

148 As defined, the most probable capital cost with contingency includes base construction cost + post-effective date implementation costs + right-of-way land acquisition and easement costs + costs of environmental mitigation measures + project contingency of 25%. (DRA Opening Brief at 40.)

149 DRA Opening Brief at 47.

150 Cal-Am Reply Brief at 24, citing Exhibit 105 at 16-17.

151 Exhibit 204 at 20.

152 Exhibit 105 at 10.

153 Motion to Approve Settlement Agreement, filed April 7, 2010, Attachment 3 at 6.

154 Opening Brief of Cities of Seaside, Sand City, Monterey, Carmel-By-The-Sea, and Pacific Grove at 3.

155 Cal-Am Reply Brief at 26-27.

156 Exhibit 363., § 8.1.4 at 10.

157 Exhibit 363, § 9.4.3 at 14.

158 Exhibit 103 at 19.

159 Exhibit 103 at 4.

160 Note that Exhibit 103 at 4, Footnote 1 provides a correction to Section 9.1.2 of the Settlement Agreement.

161 DRA Opening Brief at 49, citing 12 RT at 1092.

162 Exhibit 103 at 17, citing Uniform System of Accounts for Water Utilities, Class A http://docs.cpuc.ca.gov/published/Graphics/83011.PDF.

163 The authorized return on equity for Cal-Am is currently set at 10.2%. For illustrative purposes, Cal-Am calculates the AFUDC for the Cal-Am facilities at 8.40%.

164 D.08-05-036 at 9.

165 Id.

166 Id. at 11.

167 Id. at 13.

168 D.08-10-019, denying rehearing of D.08-05-036, at 8.

169 DRA Opening Brief at 51.

170 General Order 96-B sets forth 3 categories of advice letters. Tier 1 advice letters are effective upon filing; Tier 2 advice letters are effective after staff review and approval; and Tier 3 advice letters are not effective unless the Commission issues a resolution so finding.


172 RT at 1767.

173 MPWMD Opening Brief at 30.

174 DRA Opening Brief at 55, citing 2 RT 71.

175 DRA Opening Brief at 55.

176 MCWD Opening Brief at 53.

177 An application for rehearing of D.10-08-008 is pending. Our determinations today in no way prejudge our adjudication of that application for rehearing.

178 D.10-08-008 at 17.

179 D.10-04-030 at 12.

Previous PageTop Of PageNext PageGo To First Page