3. Requirement for a Permit to Construct (PTC)

GO 131-D defines an electric "power line" as one designed to operate between 50 kilovolt (kV) and 200 kV,1 and Section III.B requires utilities to first obtain Commission authorization, in the form of a PTC, before beginning construction of a power line. PTC applications for power lines need not include a detailed analysis of purpose and necessity, a detailed estimate of cost and economic analysis, a detailed schedule, or a detailed description of construction methods (beyond that required for CEQA compliance).2 However, GO 131-D requires PTC applications to:

These requirements are discussed separately below.

1 GO 131-D, Section I.

2 GO 131-D, Section IX.B.1.f.

3 GO 131-D, Section IX.B.1.

4 GO 131-D, Section IX.B.2-5.

5 GO 131-D, Section X.