3. Substantial Contribution to Resolution of Issues

Under Section 1802(h), a party may make a substantial contribution to a decision in one of several ways. It may offer a factual or legal contention upon which the Commission relied in making a decision, or it may advance a specific policy or procedural recommendation that the Administrative Law Judge or Commission adopted. A substantial contribution includes evidence or argument that supports part of the decision even if the Commission does not adopt a party's position in total.3

3.1 Contribution to D.01-03-082

TURN's contribution here was multi-faceted. TURN proposed changes to accounting rules we had adopted in Resolution E-3527 when TURN determined that those rules were leading to results that were inconsistent with the "rate freeze" principle embodied in AB 1890. TURN explained that it filed a petition to modify the Resolution, and the petition was subsequently consolidated with the Rate Stabilization docket. The Commission issued D.01-03-082 in which it adopted TURN's proposed accounting changes across the board.

In D.01-03-082, the Commission also granted the utilities a rate increase of three cents/kWh, despite TURN's objections. TURN points out, however, that the Commission also imposed a significant limitation on the use of the funds collected, namely, that the funds could only be used for power costs incurred after the effective date of the decision.

We conclude that TURN, through its filings and petition consolidated with the applications in this docket, made a substantial contribution to D.01-03-082.

3.2 Contribution to Other Decisions

In D.01-05-064, we addressed the revenue allocation and rate design issues created by the three-cent increase authorized by D.01-03-082. TURN stated that it substantially contributed to that decision because the Commission adopted TURN's positions on (1) definition of "equity" in rate design principles and goals, (2) revenue allocation methodology, (3) five-tier residential rate structure, and (4) non-residential rate spread, and several other smaller issues. We agree with TURN that its participation resulted in a far-reaching and substantial contribution to D.01-05-064. TURN also made substantial contributions to D.01-03-029, on the issue of the proper accounting for employee reductions and other cost-cutting measures, and to D.01-01-018, on the issue of utility shareholders bearing a share of the unanticipated costs of electricity procurement.

3.3 Contribution of TURN's Federal Court Work

TURN also has participated in federal court litigation4 initiated by the utilities and seeks compensation for this work. According to TURN, the utilities argued that under the filed rate doctrine, the Commission could not prevent the utilities from raising rates to collect increased wholesale procurement costs. TURN stated that its participation in the federal court litigation was necessary to ensure that the Commission could address the merits of the issues in the decisions covered by the present applications.

TURN stated that it made a substantial contribution to the federal court litigation by attaining, over the vigorous objection of both utilities, the status of formal intervenor pursuant to Federal Rule of Civil Procedure 24(b)(2). According to TURN, federal court intervention requires a far more rigorous showing than intervenor status at the Commission. TURN explained that initially the federal court only allowed it to participate as amicus curiae, with limited rights of participation. After reviewing TURN's motion to dismiss and opposition to SCE's motion for preliminary injunction (discussed in greater detail below), the court found that TURN's participation "would be helpful for the court in supporting the complex factual, legal issues involved in this case" and allowed TURN to participate as a formal intervenor.5

TURN also pointed out that it entered into a Joint Defense Agreement with the Commission on December 4, 2000. TURN stated that this agreement allowed TURN and the Commission to coordinate and share information related to the litigation without losing any claim of privilege. TURN said that counsel for TURN and the Commission consulted extensively on strategic and technical issues, to the mutual benefit of both parties.

In response to TURN's assertions of "coordination" with the Commission, SCE6 contended that TURN failed to identify any specific topic on which the parties consulted. SCE posited that the Commission and TURN might raise claims of privilege in regard to the details of these consultations.

We decline to open a new potential dispute regarding privilege. We are satisfied that the parties entered into an agreement to consult and coordinate because both parties perceived the agreement to be advantageous. Moreover, we note that the time records presented by TURN reflect numerous consultations between TURN's lawyers and the Commission's lawyers.

SCE also contended that TURN overstated its role in the federal litigation, particularly above and beyond that of the Commission. However, even SCE appears to acknowledge that TURN could present more specific arguments than the Commission. Some issues in the federal litigation were simultaneously before the Commission, and the Commission could not predetermine the outcome of these other proceedings by presenting definitive arguments in federal court. (See, e.g., § 454.) TURN was thus able to argue specific recommendations but the Commission was limited to hypothesizing a number of potential results. In this way, TURN could use its status to present arguments that complemented the Commission's.

TURN also emphasized its work in opposing SCE's motion for a preliminary injunction. Specifically, SCE had asked the court to require that:

[Proposed] Order Granting Plaintiff Southern California Edison Company's Motion for Preliminary Injunction, Case No. 00-12056-RSWL (January 22, 2001) (emphasis omitted).

In response to SCE's request, TURN filed a 19-page brief in opposition. To provide factual support for the brief, TURN also supplied the court with declarations from Michel P. Florio (explaining the cause of the energy crisis), Peter Navarro (outlining the likely effects of rate increases sought by the utilities), and William Marcus (describing alternative means to meet SCE's revenue needs), and a supplemental declaration by Florio on SCE's risk of bankruptcy. The Commission in its brief cited to the Navarro and Florio declarations.

The court denied SCE's motion for a preliminary injunction. The court characterized SCE's requested injunction as violating the Eleventh Amendment to the Unites States Constitution because, in the court's view, the requested injunction would "effectively usurp the regulatory authority of the State over intrastate retail rates."7

TURN's request for compensation for its federal court work raises two fundamental questions. First, may the Commission, under the intervenor compensation statutes, compensate an intervenor for work done in a forum (here, federal court) other than a Commission proceeding? Second, if the answer to the first question is yes, did TURN's federal court work make a "substantial contribution" to the Commission decisions that are the subject of TURN's compensation request? As discussed below, we answer both questions in the affirmative. Our discussion begins with the threshold question of whether the intervenor compensation statutes authorize compensation for work in a forum other than a Commission proceeding.

In its Comments on the Draft Decision awarding TURN compensation, SCE challenged the Commission's authority to award compensation for TURN's work in the federal court. SCE argued that the intervenor compensation statutes, §§ 1801-1812, only provide for compensation for participation in Commission proceedings. SCE cited to § 1802(f), among others, where "proceeding" is defined as any of several kinds of proceedings "before the commission." From this language, SCE concluded that the Commission must deny TURN's request for compensation for the work in federal court.

In response, TURN pointed to § 1802 (a) where "compensation" is defined to include the costs of "judicial review." As judicial review is necessarily before an entity other than the Commission, TURN concludes that the Commission may grant TURN's request for compensation for the federal court work.

In analyzing this issue, we turn first to the plain words of the statute. With emphasis added, § 1803 states that:

As noted by SCE, § 1802(f) defines "proceeding" as: "an application, complaint, or investigation, rulemaking, alternative dispute resolution procedures in lieu of formal proceedings as may be sponsored or endorsed by the Commission, or other formal proceeding before the Commission." However, the term "hearing" is not defined in the statute.

Because "hearing" is not defined in the statute, we must interpret the statute, guided by the legal principles of statutory construction, as well as our own precedent. We recently reviewed these principles:

D.01-11-031 (modifying D.01-04-006, and denying rehearing as modified) (November 8, 2001).

Applying these principles to § 1803 requires that the Commission use the plain and commonsense meaning of "hearing" to achieve a reasonable and practical construction that is consistent with the legislative purpose. Giving effect to each word leads to the conclusion that the Legislature intended to allow compensation for (1) participation in "proceedings" before the Commission and (2) participation in "hearings" before other entities but only so far as such participation is linked to the "substantial contribution" for which compensation is claimed. Any other interpretation of "hearing" would render the word surplusage in contravention of the judicial precedent quoted above.

Our interpretation of § 1803 also harmonizes with § 1802(a), which allows compensation for "judicial review." As TURN correctly pointed out, this section clearly contemplates the Commission granting compensation for work done before other entities. Section 1802(a) defines "compensation" to include the costs "of obtaining judicial review." In its reply comments, TURN stated that the statute clearly provides for an award of costs for work during judicial review of Commission decisions, and does not distinguish between judicial review in the state courts and judicial review in the federal courts. TURN also stated that SCE's arguments to the federal court sought to prevent the Commission from enforcing its earlier decisions against SCE, such that the federal lawsuits amounted to judicial review of the earlier decisions.

Black's Law Dictionary, 7th ed. (1999), defines "judicial review" as "a court's review of a lower court's or an administrative body's factual or legal findings." As SCE's lawsuit illustrates, in addition to the state courts, the federal courts may also review the Commission's actions. Furthermore, judicial review of our "findings" occasionally is sought, as SCE did here, during a proceeding rather than after a final order. Accordingly, we agree with TURN that the only logically consistent interpretation of §§ 1802(a) and 1803 is that the Commission, under certain circumstances, may grant compensation for work before other entities.

The circumstances under which we can compensate work done before other entities are narrow, however. As quoted above, § 1803 requires that the customer's presentation make a "substantial contribution to adoption, in whole or in part, to the commission's order or decision." Thus, the work before the other entity must have a direct effect on the Commission's decision.8 We view this limitation as key to our ability to evaluate whether the work has met the standards of § 1803. This limitation is a formidable impediment to obtaining compensation for work before other entities. Only extraordinary circumstances would support the findings necessary for such an award. Drawing on D.89-09-103, discussed in footnote 3, as well as our precedent, discussed below, we find that such an award may be proper where (1) a strong public policy exists to encourage intervenor participation due to factors not present in the usual Commission proceeding, (2) the intervenor's participation in the non-Commission forum was necessary and not the intervenor's choice of forums, and (3) the case is of unusual importance due the scope of its potential impacts.

The Commission has previously awarded compensation for work done outside the Commission, specifically before the California Legislature and the Federal Energy Regulatory Commission (FERC). The Commission authorized compensation for activities before the Assembly Committee on Utilities and Commerce and the Senate Committee on Energy and Public Utilities held in response to allegations of irregularities in the decision-making process for the Implementation Rate Design (IRD) decision. In addition to the Commission and its senior staff, several parties to the underlying proceeding appeared to offer testimony and recommendations for changes to the Commission's decision-making process. In considering the ensuing intervenor compensation request from one of the appearing parties, the Commission stated: "We believe that time devoted to these hearings was properly chargeable for intervenor compensation. The procedural matters discussed and advice obtained were a part of the guidance that went into the eventual decision in this matter." (D.95-08-051, Re Alternative Regulatory Frameworks for Local Exchange Carriers, (1995) 61 CPUC2d 142, 148.)

D.98-10-030 also involved a unique set of facts, where the FERC was addressing the then-proposed structure of the Power Exchange (PX) and the Independent System Operator (ISO), entities critical to the operation of newly deregulated energy markets. The Commission sought comments from parties to assist in developing the Commission's comments to FERC. In a subsequent request for internvenor compensation, the Commission found that the work performed in preparing the FERC comments could be included:

Order Instituting Rulemaking on the Commission's Proposed Policies Governing Restructuring California's Electric Services Industry and Reforming Regulation, Order Instituting Investigation on the Commission's Proposed Policies Governing Restructuring California's Electric Services Industry and Reforming Regulation, D.98-10-030 (October 8, 1998).

Here, the utilities sought to use the federal court to undermine this Commission's authority over retail ratemaking. As TURN noted in its request for compensation, these issues represent literally billions of dollars for the utilities' customers and arise under the well-known financial and power supply emergency conditions that resulted from deregulation. These circumstances fit well within the standards set out above to guide our exercise of discretion under § 1803. Due to the financial and power supply emergency, the public interest is well-served by the participation of experienced and knowledgeable intervenors, such as TURN, before all tribunals whose jurisdiction is involved. The utilities chose the federal court forum, not TURN, and it cannot be disputed that this is a case of unusual importance to all Californians.

In sum, TURN's participation in the federal court forum was helpful in protecting the Commission's authority to act as it eventually did. In this way, TURN's federal court actions significantly contributed to "the eventual decision in this matter." Accordingly, we will recognize TURN's expenses for participation in the federal court as part of its intervenor compensation claim.

We believe this outcome is consistent with the letter, spirit, and intent of the intervenor compensation statute. The federal court litigation was an essential component of these consolidated proceedings and the Commission decisions that are the subject of TURN's compensation request. As such, TURN could not practically or effectively advocate its position before the Commission without first helping to overcome utility litigation intended to prevent the Commission from acting on the very points TURN was seeking to raise at the Commission.

3 The Commission has provided compensation even when the position advanced by the intervenor is rejected. See D.89-03-063 (awarding San Luis Obispo Mothers For Peace and Rochelle Becker compensation in Diablo Canyon Rate Case because their arguments, while ultimately unsuccessful, forced the utility to thoroughly document the safety issues involved). See also D.89-09-103 (modifying D.89-03-063) where we hold that in certain exceptional circumstances, the Commission may find that a party has made a substantial contribution in the absence of the adoption of any of its recommendations. Such a liberalized standard should be utilized only in cases where a strong public policy exists to encourage intervenor participation because of factors not present in the usual Commission proceeding. These factors must include (1) an extraordinarily complex proceeding, and (2) a case of unusual importance. Additionally, the Commission may consider the presence of a proposed settlement. 4 Southern California Edison v. Lynch et al., Case No. 00-12056-RSWL (Mcx), United States District Court for the Central District of California (Western Division) (filed November 13, 2000); Pacific Gas and Electric Company v. Lynch et al., Case No. CV 00-4128 (SBA), United States District Court for the Northern District of California (filed November 8, 2000). 5 Reporter's Transcript of Proceedings, CV 00-1056-RSWL, February 12, 2001, page 7. 6 SCE's motion to accept its response for filing is granted. 7 Southern California Edison v. Lynch, CV 00-12056 RSWL, Order Denying Plaintiff's Motion for Preliminary Injunction (February 15, 2001) at page 2. 8 Such an interpretation is also consistent with judicial precedent, albeit applying a different statute. Pursuant to Code of Civil Procedure § 1021.5, California's "Private Attorney General" statute, successful plaintiffs may petition the court for attorney's fees in "any action which has resulted in the enforcement of an important right affecting the public interest" if three conditions are met: (1) a significant benefit, either pecuniary or nonpecuniary, has been conferred upon the general public or a broad class of people; (2) the necessity and financial burden of private enforcement make an award appropriate; and (3) the fees should not, in the interests of justice, be paid out of any recovery. When confronted with the question of whether to award attorney fees for work performed before an administrative agency either before or after the court litigation, the California courts have allowed recovery where the services before the administrative agency were "useful and necessary to the ultimate resolution of the action and directly contributed to that resolution." Wallace v. Consumers Co-op of Berkeley, (1985) 170 Cal. App.3d 836, 848-9.

Previous PageTop Of PageNext PageGo To First Page