4. Contract Allocation Options and Positions of the Parties

4.1 DWR's Presentation of Allocation Options

4.3 PG&E's Preferred Allocation


"(1) Allocate all of Coral to PG&E and all of Sunrise to SDG&E/SCE. In doing so, SDG&E and SCE may rebalance the mix of the SP-15 contracts they allocated between them in their July 19 proposals in making this modification. However, dispatchable contracts (such as Sunrise) should not be split. If the rebalancing between SDG&E and SCE would now involve allocation of an affiliates contract or portion thereof to either of them-they should discuss why this exception is warranted. Do not modify any NP-15 allocations to PG&E.


"(2) [L]ook at an alternative that instead of Sunrise being allocated to SCE/SDG&E, a comparable shift of contract quantities was accomplished by an alternate split of the Coral contract. This additional permutation is optional. No others should be submitted."33

4.5 ORA's Position

20 RT at 17. 21 RT at 16-20; CERS Summary Diagram of Written Example Used at July 26, 2002 Workshop, dated July 30, 2002. 22 See RT at 22 and CERS Contract Allocation Analysis dated August 7, 2002. 23 The preferred options of ORA, SDG&E and PG&E presented in this section represent their recommendations assuming that the Commission does not adopt a planning approach. As discussed above, these parties prefer that DWR continue to administer the contracts in a statewide portfolio and that contract quantities be allocated for planning purposes only. 24 DWR states that this is the model run it is using to support its 2003 revenue requirements. RT at 24. 25 For example, the El Paso contract is a 50 megawatt (MW) 6-by-16 product that has 50 MWs delivered in the north and 50 MWs delivered in the south. Assuming that PG&E would be allocated the northern portion and SDG&E the southern portion, each utility could submit separate schedules for their allocated quantities to the ISO. In the alternative, either PG&E or SDG&E could submit schedules on behalf of both. Each would determine the need for or excess of the allocated contract quantities, and handle those decisions operationally as if each held an individual contract. RT at 9-11. 26 RT at 24, lines 6-10. 27 SCE's July 19, 2002 filing, pp. 17-18. See also, RT, Attachment C, p. 8. 28 RT at 92. 29 RT at 93. 30 SDG&E does not include in its calculation of all-in costs any revenues from sales associated with the economic dispatch of surplus capacity. 31 However, SDG&E's average $/MWh contract cost calculations cannot be directly compared to DWR's "contract costs assuming cost following contract" numbers because SDG&E averages over a 5-year subset of the 7-year period that DWR uses. 32 RT, p. Attachment B, p. 4. 33 Electronic ruling from ALJ to parties summarizing her direction to parties, July 26, 2002 at 6:35 p.m. 34 PG&E also presents a modification of this permutation that allocates (in addition to Sunrise), the Allegheny 2, Constellation-Produce and El Paso NP 15 deliveries to SDG&E and SCE. We agree with SCE and SDG&E that PG&E violated the ALJ's direction regarding the scope of additional scenarios, and do not consider this permutation any further.

Previous PageTop Of PageNext PageGo To First Page