For a number of years, the Upper Ridge communities and neighboring areas in Northern California have experienced repeated water shortages and droughts. The wells that Del Oro and its predecessor water purveyors in the Lime Saddle and Magalia system service areas have used as the principal sources of water have grown progressively unreliable. As a consequence, Del Oro is now looking into an alternative supply of water. Del Oro's consulting engineers have recommended extending the utility's facilities to Lake Oroville where an abundant supply of water is available for both present and future needs of the Upper Ridge water customers.

In November 2000, Del Oro surveyed its Upper Ridge customers to determine if they favored a plan for additions to its facilities that would involve the construction, in two phases, of a project connecting its systems to Lake Oroville. The first phase would include construction of a two-mile long pipeline along Pentz Road in the Upper Ridge area that would interconnect the northerly portion of the Lime Saddle District with existing treatment and storage facilities that are currently drawing supply from Lake Oroville. The second phase would involve construction of a 6.6-mile pipeline connecting the Lime Saddle District to Paradise Pines District.

Phase one is expected to solve the on-going water shortage problems and threats of water usage curtailment of customers served by the Lime Saddle District system. It will also make approximately 260 acre feet of surplus water (secured from the Stirling City system to alleviate water shortages in the Lime Saddle District) available each year to customers in both the Paradise Pines and Magalia Districts. Phase two will provide an alternative source of supply in the Paradise Pines and Magalia Districts.

Pursuant to the Application, 73 percent of Del Oro's customers responding to the survey approved phase one. Phase two was approved by a majority of responding customers.

The projected cost of the entire project is $7,364,942 (including a 20 percent construction cost contingency, engineering design and contract administration costs). Phase one is expected to take 24 months to complete. Another 24 months is required for completion of phase two.

Application 02-02-001

Financing the Costs of CEQA Review

Capital Ratios

Del Oro's capital ratios as of December 31, 2001 are shown below as recorded and as adjusted to give pro forma effect to the proposed $250,000 clearance loan:

The issuance of long-term debt is subject to §§ 817 and 818 of the PU Code which state, in relevant part, as follows:

§ 817: A public utility may issue ... bonds, notes, and other evidence of indebtedness payable at periods of more than 12 months after the date thereof for any of the following purposes and no other:

(a) Acquisition of property.

(b) Construction, completion, extension, or improvement of its facilities.

(c) Improvement or maintenance of its service.

(d) Discharge or lawful refunding of its obligations.

(e) Financing the acquisition and installation of electrical and plumbing appliances and agricultural equipment that are sold by other than a public utility, for use within the service area of the public utility.

(f) Reorganization or readjustment of its indebtedness or capitalization upon a merger, consolidation, or other reorganization.

(g) Retirement of or in exchange for one ore more outstanding stocks or stock certificates or other evidence of interest or ownership of such public utility, or bonds, notes, or other evidence of indebtedness of such public utility, with or without the payment of cash.

(h) Reimbursement of moneys .. expended from income or from any other money in the treasury of the public utility not secured by or obtained from the issue of stocks or stock certificates or other evidence of interest or ownership, or bonds, notes, or other evidences of indebtedness of the public utility, for any of the aforesaid purposes except maintenance of service and replacements, in cases where the applicant has kept its accounts and vouchers for such expenditures in such manner as to enable the commission to ascertain the amount of money so expended and the purposes for which expenditure was made.

§ 818: No public utility may issue stocks ... or other evidences of indebtedness payable at periods of more than 12 months after the date thereof unless, in addition to the other requirements of law it shall first have secured from the commission an order authorizing the issue, stating the amount thereof and the purposes to which the issue or the proceeds thereof are to be applied...

Proposed Surcharge Rate

The issue of ratebasing versus surcharge must balance the interests of both utility ratepayers and shareholders. While the surcharge method ensures that the costs of the loan will be repaid without financial stress to the utility, the Commission must also guard against unnecessary costs for ratepayers and ascertain that the loan proceeds are used properly.

In order for this Commission to authorize a principal and interest surcharge, the utility must make a showing that the lender requires a dedicated source of payment for the loan and must comply with the notification procedure under Rule 24 of the Commission's Rules of Practice and Procedure.

For the above reasons, we will deny without prejudice Del Oro's request for authority to impose a surcharge to repay the proposed $250,000 environmental clearance loan. If Del Oro is unable to obtain a loan without authorization for surcharge recovery, it can enter a loan agreement conditioned upon the Commission's authorization of a surcharge. Then, it may file a motion to request such surcharge recovery. At that time Del Oro must make a showing that the lender requires a dedicated source of payment and it must comply with the customer notification procedure for rate increase contained in the Commission's Rules of Practice and Procedure.

This proceeding will remain open for one year from the effective date of this order.

In Resolution (Res.) ALJ 176-3090 dated 6/27/02, the Commission preliminarily categorized this Application as ratesetting, and preliminarily determined that hearings were not necessary. No protests have been received. Given these developments, a public hearing is not necessary, and there is no need to alter the preliminary determinations made in Res. ALJ 176-3090.

This is an uncontested matter in which the decision pertains solely to a water company. Accordingly, pursuant to PU Code § 311(g)(3), the 30-day period for public review and comment under § 311(g)(1) does not apply.

Findings of Fact

1. Del Oro, a California corporation, is a public utility subject to the jurisdiction of this Commission.

2. Del Oro needs external funds for the purposes set forth in the Application.

3. The authorized issue of debt is for proper purposes and is not adverse to the public interest.

4. Del Oro cannot seek authority for a certificate of public convenience and necessity and to incur indebtedness to pay the costs of its Upper Ridge project until Del Oro submits the Proponent's Environmental Assessment required by Rule 17.1 of the Commission's Rules for Practice and Procedure.

5. Notice of the filing of the Application appeared on the Commission's Daily Calendar of June 25, 2002. There is no known opposition to this Application, and the authority requested should be granted, subject to the conditions below.

Conclusions of Law

1. A public hearing is not necessary.

2. The Application should be granted to the extent set forth in the order that follows.

3. Upon securing the loan, Del Oro should pay the fee determined in accordance with PU Code § 1904(b).

4. The following order should be effective on the date of signature.

ORDER

IT IS ORDERED that:

1. Del Oro Water Co., Inc. (Del Oro), on or after the effective date of this order is authorized to secure a loan in the amount of $250,000 upon terms and conditions substantially consistent with those set forth in or contemplated in Application (A.) 02-06-033 (Application).

2. Del Oro may transact the above financing with the state Department of Health Services or with a conventional lender. Del Oro shall exercise prudent management practices in selecting the lender and the appropriate interest rate method for the loan.

3. Del Oro may execute and deliver a loan contract or related documents in connection with the loan.

4. Del Oro shall file with the Water Division a copy of the loan agreement, promissory note, and debt service schedule within 15 days after execution.

5. Del Oro may by the application process request for surcharge method of recovery once the environmental impact report is completed and once it has secured a loan provider for the project covering its Paradise Pines District, Lime Saddle District, and Magalia District.

6. Del Oro shall provide the Water Division a copy of the Environmental Impact Report and the Notice of Determination from Butte County.

7. The authority granted by this order shall become effective when Del Oro pays $500 as required by Public Utilities Code § 1904(b).

8. Application 02-06-033 is granted as set forth above.

9. Application 02-06-033 shall remain open for one year from the effective date of this order.

This order is effective today.

Dated September 19, 2002, at San Francisco, California.

Previous PageTop Of PageGo To First Page