In November 2000, Del Oro surveyed its Upper Ridge customers to determine if they favored a plan for additions to its facilities that would involve the construction, in two phases, of a project connecting its systems to Lake Oroville. The first phase would include construction of a two-mile long pipeline along Pentz Road in the Upper Ridge area that would interconnect the northerly portion of the Lime Saddle District with existing treatment and storage facilities that are currently drawing supply from Lake Oroville. The second phase would involve construction of a 6.6-mile pipeline connecting the Lime Saddle District to Paradise Pines District.
Phase one is expected to solve the on-going water shortage problems and threats of water usage curtailment of customers served by the Lime Saddle District system. It will also make approximately 260 acre feet of surplus water (secured from the Stirling City system to alleviate water shortages in the Lime Saddle District) available each year to customers in both the Paradise Pines and Magalia Districts. Phase two will provide an alternative source of supply in the Paradise Pines and Magalia Districts.
Pursuant to the Application, 73 percent of Del Oro's customers responding to the survey approved phase one. Phase two was approved by a majority of responding customers.
The projected cost of the entire project is $7,364,942 (including a 20 percent construction cost contingency, engineering design and contract administration costs). Phase one is expected to take 24 months to complete. Another 24 months is required for completion of phase two.
Application 02-02-001
On February 4, 2002, Del Oro filed A.02-02-001 with the Commission seeking, among other things, a certificate that present and future public convenience and necessity requires Del Oro to install the project described above; for authority to incur indebtedness to pay the costs of such project; and for authority to recover all present and future costs in connection therewith by increases in the water rates.
On March 4, 2002, the presiding Administrative Law Judge ruled that A.02-02-001 was defective in that CEQA compliance must be addressed before the Commission may consider granting its approval to the issuance of a certificate of public convenience and necessity. The ruling declared that there is "ample reason to believe Applicant should submit the Proponent's Environmental Assessment [for the project] required by Rule 17.1 [of the Commission's Rules of Practice and Procedure]" and recommended that Del Oro should "consult...with the Commission's CEQA Staff in the Energy Division to discuss the procedures, project scope and timeline for CEQA implementation".
The CEQA Staff has advised Del Oro that while the Commission might be regarded as a "responsible agency" for securing CEQA implementation of the project, Butte County should be regarded as the "lead agency". The cost of preparing an Environmental Impact Report is approximately $250,000.
Financing the Costs of CEQA Review
Del Oro is now requesting authority to obtain a $250,000 "environmental clearance loan" from a conventional lender or from the Safe Drinking Water State Revolving Fund (SDWSRF) to finance the costs associated with securing CEQA review of the proposed project and to place in effect a surcharge on existing water rates to repay the loan principal and interest.
Del Oro states in the Application that it seeks authority to secure a loan and collect a surcharge at this time rather than waiting until all the terms and conditions of the loan agreement are known so that it will have the ability to negotiate in an effective and expeditious manner with a lender.
Pursuant to its Income Statement for the fiscal year ended December 31, 2001, shown as Exhibit A-2 to the Application, Del Oro reported total operating revenues of $2,463,887 and net loss of $98,353.
Del Oro's Balance Sheet at December 31, 2001, shown as Exhibit A-1 to the Application is summarized as follows:
Assets and other Debits Amount
Current Assets $ 2,039,837
Fixed Assets 6,351,284
Other Investments 859,652
Other Assets 320,262
Total $ 9,571,036
Liabilities and other Credits
Current Liabilities $ 4,419,320
Long-term Debt 3,140,029
Equity 2,011,687
Total $ 9,571,036
Capital Ratios
Del Oro's capital ratios as of December 31, 2001 are shown below as recorded and as adjusted to give pro forma effect to the proposed $250,000 clearance loan:
Recorded Pro Forma
($000) % ($000) %
Long-Term Debt 2,985 55.2 3,226 57.0
Short-Term Debt 1,541 28.5 1,550 27.4
Sub-Total 4,526 83.7 4,776 84.4
Common Equity 886 16.3 886 15.6
Total Capitalization 5,412 100.0 5,662 100.0
Capital structures are normally subject to review in cost of capital or general rate case proceedings. We will not, therefore, make a finding in this decision of the reasonableness of the projected capital ratios for ratemaking purposes. However, we need to mention that Del Oro's change in capital structure from a 16.3% effective equity position to 84.4% debt and 15.6% equity position would increase the difficulty for Del Oro to finance the estimated debt of $7.4 million needed for its Upper Ridge project (a substantial plant addition).
The issuance of long-term debt is subject to §§ 817 and 818 of the PU Code which state, in relevant part, as follows:
§ 817: A public utility may issue ... bonds, notes, and other evidence of indebtedness payable at periods of more than 12 months after the date thereof for any of the following purposes and no other:
(a) Acquisition of property.
(b) Construction, completion, extension, or improvement of its facilities.
(c) Improvement or maintenance of its service.
(d) Discharge or lawful refunding of its obligations.
(e) Financing the acquisition and installation of electrical and plumbing appliances and agricultural equipment that are sold by other than a public utility, for use within the service area of the public utility.
(f) Reorganization or readjustment of its indebtedness or capitalization upon a merger, consolidation, or other reorganization.
(g) Retirement of or in exchange for one ore more outstanding stocks or stock certificates or other evidence of interest or ownership of such public utility, or bonds, notes, or other evidence of indebtedness of such public utility, with or without the payment of cash.
(h) Reimbursement of moneys .. expended from income or from any other money in the treasury of the public utility not secured by or obtained from the issue of stocks or stock certificates or other evidence of interest or ownership, or bonds, notes, or other evidences of indebtedness of the public utility, for any of the aforesaid purposes except maintenance of service and replacements, in cases where the applicant has kept its accounts and vouchers for such expenditures in such manner as to enable the commission to ascertain the amount of money so expended and the purposes for which expenditure was made.
§ 818: No public utility may issue stocks ... or other evidences of indebtedness payable at periods of more than 12 months after the date thereof unless, in addition to the other requirements of law it shall first have secured from the commission an order authorizing the issue, stating the amount thereof and the purposes to which the issue or the proceeds thereof are to be applied...
We find that Del Oro has demonstrated a reasonable need to issue up to $250,000 debt to finance its CEQA review. We find that the use of debt to finance this pre-construction cost is consistent with §§ 817 and 816, which allow a utility to issue debt for the purpose of construction, completion, extension or improvement of facilities. Without the CEQA review, Del Oro's Upper Ridge project will remain on the drawing board.
Del Oro proposes three alternative surcharge schedules as shown in Exhibit D to the Application: 1) a SDWSRF loan with a 20-year repayment schedule with monthly payments of principal and estimated interest rate of 3% per annum, 2) a conventional loan with a 6-year repayment schedule with monthly payments of principal and estimated interest rate of 8% per annum, or 3) a conventional loan with a 6-year repayment schedule with monthly payments of principal and estimated interest rate of 10% per annum.
The annual requirement for the $250,000 loan through SDWSRF is approximately $18,885 and through conventional loan is $52,450 (8%) or $55,767 (10%). The amount of the surcharge to repay the loan principal and interest will be in direct proportion to the capacity of each customer's meter or service connection.
The issue of ratebasing versus surcharge must balance the interests of both utility ratepayers and shareholders. While the surcharge method ensures that the costs of the loan will be repaid without financial stress to the utility, the Commission must also guard against unnecessary costs for ratepayers and ascertain that the loan proceeds are used properly.
In order for this Commission to authorize a principal and interest surcharge, the utility must make a showing that the lender requires a dedicated source of payment for the loan and must comply with the notification procedure under Rule 24 of the Commission's Rules of Practice and Procedure.
For the above reasons, we will deny without prejudice Del Oro's request for authority to impose a surcharge to repay the proposed $250,000 environmental clearance loan. If Del Oro is unable to obtain a loan without authorization for surcharge recovery, it can enter a loan agreement conditioned upon the Commission's authorization of a surcharge. Then, it may file a motion to request such surcharge recovery. At that time Del Oro must make a showing that the lender requires a dedicated source of payment and it must comply with the customer notification procedure for rate increase contained in the Commission's Rules of Practice and Procedure.
This proceeding will remain open for one year from the effective date of this order.
In Resolution (Res.) ALJ 176-3090 dated 6/27/02, the Commission preliminarily categorized this Application as ratesetting, and preliminarily determined that hearings were not necessary. No protests have been received. Given these developments, a public hearing is not necessary, and there is no need to alter the preliminary determinations made in Res. ALJ 176-3090.
This is an uncontested matter in which the decision pertains solely to a water company. Accordingly, pursuant to PU Code § 311(g)(3), the 30-day period for public review and comment under § 311(g)(1) does not apply.
1. Del Oro, a California corporation, is a public utility subject to the jurisdiction of this Commission.
2. Del Oro needs external funds for the purposes set forth in the Application.
3. The authorized issue of debt is for proper purposes and is not adverse to the public interest.
4. Del Oro cannot seek authority for a certificate of public convenience and necessity and to incur indebtedness to pay the costs of its Upper Ridge project until Del Oro submits the Proponent's Environmental Assessment required by Rule 17.1 of the Commission's Rules for Practice and Procedure.
5. Notice of the filing of the Application appeared on the Commission's Daily Calendar of June 25, 2002. There is no known opposition to this Application, and the authority requested should be granted, subject to the conditions below.
Conclusions of Law
1. A public hearing is not necessary.
2. The Application should be granted to the extent set forth in the order that follows.
3. Upon securing the loan, Del Oro should pay the fee determined in accordance with PU Code § 1904(b).
4. The following order should be effective on the date of signature.
IT IS ORDERED that:
1. Del Oro Water Co., Inc. (Del Oro), on or after the effective date of this order is authorized to secure a loan in the amount of $250,000 upon terms and conditions substantially consistent with those set forth in or contemplated in Application (A.) 02-06-033 (Application).
2. Del Oro may transact the above financing with the state Department of Health Services or with a conventional lender. Del Oro shall exercise prudent management practices in selecting the lender and the appropriate interest rate method for the loan.
3. Del Oro may execute and deliver a loan contract or related documents in connection with the loan.
4. Del Oro shall file with the Water Division a copy of the loan agreement, promissory note, and debt service schedule within 15 days after execution.
5. Del Oro may by the application process request for surcharge method of recovery once the environmental impact report is completed and once it has secured a loan provider for the project covering its Paradise Pines District, Lime Saddle District, and Magalia District.
6. Del Oro shall provide the Water Division a copy of the Environmental Impact Report and the Notice of Determination from Butte County.
7. The authority granted by this order shall become effective when Del Oro pays $500 as required by Public Utilities Code § 1904(b).
8. Application 02-06-033 is granted as set forth above.
9. Application 02-06-033 shall remain open for one year from the effective date of this order.
This order is effective today.
Dated September 19, 2002, at San Francisco, California.
LORETTA M. LYNCH
President
HENRY M. DUQUE
CARL W. WOOD
GEOFFREY F. BROWN
MICHAEL R. PEEVEY
Commissioners