4. Estimated Project Costs

PG&E estimates the cost of Path 15 upgrades along its preferred route at $323.1 million, including reconductoring of the Gates-Midway 230 kV line.17 The annual revenue requirement associated with this cost would be between $48 million and $58 million/year depending on what factor (15% to 18%) is used to levelize costs.

17 Exh. 214, Section 6, p. 11.