5. Procedural History

5.1. The February 25, 1999 Prehearing Conference (PHC)

A duly noticed PHC was held in San Francisco on February 25, 1999 before Assigned Commissioner Henry M. Duque and Administrative Law Judge (ALJ) John B. Weiss.

On February 19, 1999 the City had filed a PHC statement wherein it recognized that the Developer's need to resolve the water and sewer issues was time sensitive, but also stated its view that local resolution of annexation issues could resolve the water/sewer issues without the PUC. In support of this view, the PHC statement noted that on January 19, 1999, a Council subcommittee had approved an annexation study (commissioned a year earlier with a first draft issued July 1998), and that the full City Council would consider the study's recommendations on February 22, 1999 to develop an annexation strategy with negotiation parameters.8 The PHC statement asked for a 60-day continuance of the PHC after which the City would report its progress.

The City did not respond at the February 23, 1999 PHC to the Commissioner's PHC notice posing four questions.9 Nonetheless, the ALJ during the PHC, with the approval of the Commissioner, stated that if the City was unequivocally willing and able to serve with no further delay, its proposal to serve would be heard as an alternative to SCWC's request for a CPCN in an Evidentiary Hearing (EH) which the ALJ was scheduling. The ALJ noted that the Commission was constrained to render a decision on the SCWC application within 18 months; that the issue before the Commission was not "annexation," but whether SCWC should be authorized to serve, and our proceeding would go forward without delay. Should the parties reach a pre-annexation agreement providing for City service, the Commission proceeding could be aborted at any time by the Applicant. A second PHC was scheduled for April 22, 1999 providing negotiation opportunity, but an EH schedule was also tentatively established.

5.2. The Resulting Scoping Memo

Following the February 25 PHC, the Assigned Commissioner issued his Scoping Memo and Ruling pursuant to Rule 6.3 of the Commission's Rules of Practice and Procedure. The Memo and Ruling affirmed the ratemaking categorization of the proceedings, designated ALJ Weiss as the principal hearing officer, adopted the timetable schedule discussed in the PHC, and set forth the scope of the proceeding.

5.3. The April 22, 1999 2nd PHC

As scheduled, the 2nd PHC was held in San Francisco before Commissioner Duque and ALJ Weiss. Both the City and the Developer reported on their negotiations.

Negotiation meetings had been held on March 4, 11, 18, and 25, 1999 and on April 1 and 15, 1999. At the last meeting, the City's staff and the Developer agreed upon a list of "deal points" for a draft pre-annexation agreement. Its staff was to present the Council a proposed draft pre-annexation agreement, but not until June 28, 1999.10

The Developer noted (1) a continuing May 1997 Council Resolution to support public purchase of the Developer's property for open space, and (2) a March 29, 1999 Council majority directive to its staff that as a condition to annexation, the Developer must agree to sell its property for public open space. The Developer concluded that good faith of the city's staff notwithstanding, it saw no reasonable expectation of any pre-annexation agreement. In view of the certain litigation challenges that would attend any agreement, the Developer will not agree to annexation until its development is actually built. Finally, the Developer observed that it was committed to pay $500,000 to SCWC should SCWC not be the service provider. The parties did agree to continue negotiations.

Minor scheduling adjustments were made and affirmed by the Assigned Commissioner on April 26, 1999 in an Addendum Ruling to this Scoping Memo.

5.4. The August 23, 1999 EH

The scheduled EH was held in San Francisco on August 23, 1999 before ALJ Weiss (a City request for a delay having been denied).11 As ordered by the Commissioner's Scoping Memo, prepared testimony had been submitted on August 4, 1999 and rebuttal prepared testimony on August 18, 1999.

The applicant utility's testimony and evidence was introduced by Patrick R. Scanlon, District Manager of SCWC's Orange County District. The Developer's testimony and evidence was introduced by Lucy Dunn, Executive Vice President of Hearthside Homes.

The City's testimony and evidence was introduced by Thomas A. Rulla, Principal Civil Engineer in the City's Public Works Department, Dennis E. MacLain, Water Resources Consultant and the City's Interim Water Operations Manager, and Laurie J. McKinley, Principal Partner, McKinley Nielsen Associates, public policy and governmental affairs consultants.

The RRB introduced no witnesses but did provide a staff report and brief and participated in cross-examination.

5.5. Briefing

Concurrent Closing and Reply Briefs were submitted, respectively, on September 8, 1999 and September 22, 1999. The proceeding was submitted for decision on September 22, 1999.

5.6. Oral Argument

Pursuant to timely written request, an ALJ Ruling set oral argument before a quorum of the Commission for May 2, 2000. SCWC, Hearthside, the City, and the Land Trust presented oral argument to Commissioners Duque, Bilas, Neeper, and Wood as scheduled.

8 Although the Council meeting has transpired only a couple days previously, the City did not report that at its February 22, 1999 meeting, two Council members stated their opposition to any annexation agreement and were against any negotiations at all with the Developer. And as the minutes of that meeting revealed, it was a majority that voted to proceed.

9 In the notice for the PHC, the Assigned Commissioner directed the City to respond to a question at the PHC. Although the City's response was dated February 23, 1999, it was filed March 8, 1999 (after the PHC) in form of a "Supplement to City's PHC Statement." These four questions and a summary of the City's responses follow:

10 When the staff returned to the City Council June 28, 1999 with the "deal points" for a mutually acceptable pre-annexation agreement, and recommended approval, the Council rejected the proposal and directed staff to continue negotiations subject to new conditions and modifications of the "deal points." The City wanted to be able to voice its objections on the Mesa project to the Coastal Commission at that Commission's forthcoming LCP hearing and to be free to take any position. 11 On July 21, 1999, the City requested rescheduling the EH to November 21, 1999, a date after the November 2-5, 1999 period in which the Coastal Commission would perhaps conduct a hearing on the LCP, pursuant to Superior Court's June 25, 1999 order. The City stated that an extension would facilitate negotiations between the City and the Developer on a pre-annexation agreement, noting that a majority of the Council indicated approval of a list of 21 "deal points" arrived at between City's staff and the Developer, but could not support approval until they knew the extent of any Mesa development included in the Coastal Commission approval of an LCP. The Developer strongly opposed delay in the EH, contending that the pending return of the Developer to the Coastal Commission "to remedy defects in the LCP" has no bearing on the PUC's consideration of the SCWC applications; that there is no reasonable expectation that the Coastal Commission's action will change the City's long-standing unwillingness and unreadiness to provide water and sewer services to the Developer's project, and that the City's request is an attempt to inject uncertainty where none exists. SCWC joined the Developer in opposition to any delay in the EH. In his denial of the delay request, the ALJ observed that while the Coastal Commission had scheduled a hearing for during the November 2-5, 1999 period, there could be no assurance as to when it would issue a decision after such hearing (and as of February 2000, no decision has resulted). Furthermore, whether or not the City elects to pursue annexation was not a matter within the purview of the PUC. Should a City-Developer pre-annexation agreement be reached before a PUC decision, the applications can be withdrawn; and should a CPCN be issued, SCWC can still elect not to exercise it and let the CPCN authorization lapse. But as the Assigned Commissioner made clear in his April 26, 1999 addendum to his Scoping Memo, it would be the firm intention of this Commission to conclude the application process by April 2000 (within the 18-month provisions for ratemaking cases) to comply with the Legislative intent expressed in Section 1 of Senate Bill 960, Chapter 856 of 1996 statutes.

Previous PageTop Of PageNext PageGo To First Page