Word Document PDF Document |
STATE OF CALIFORNIA GRAY DAVIS, Governor
PUBLIC UTILITIES COMMISSION
505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3298
October 9, 2003
TO: ALL PARTIES OF RECORD IN APPLICATION 99-09-006
Decision 03-10-013 is being mailed without the Dissent of Commissioner Lynch. The Dissent will be mailed separately.
Very truly yours,
/s/ ANGELA K. MINKIN
Angela K. Minkin, Chief
Administrative Law Judge
ANG:sid
Attachment
ALJ/BDP/sid Mailed 10/9/2003
Decision 03-10-013 October 2, 2003
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of PACIFIC GAS AND ELECTRIC COMPANY in the 1999 Annual Transition Cost Proceeding. |
Application 99-09-006 (Filed September 1, 1999) |
(See Appendix A for a list of appearances.)
OPINION ADOPTING ESTIMATE FOR HUNTERS POINT POWER PLANT SITE REMEDIATION
TABLE OF CONTENTS
OPINION ADOPTING ESTIMATE FOR HUNTERS POINT 2
POWER PLANT SITE REMEDIATION 2
I. Summary 2
II. Procedural Summary 3
III. Background 3
IV. Estimated Cost of Decommissioning HPPP 4
A. PG&E's Estimate 4
B. Position of CCSF 5
C. Position of SAEJ 6
D. Position of ORA 6
E. Response of PG&E. 6
F. Discussion 9
V. Ratemaking Treatment 11
VI. California Environmental Quality Act (CEQA) 13
VII. Comments on Proposed Decision 15
VIII. Assignment of Proceeding 16
Findings of Fact 16
Conclusions of Law 17
ORDER 18
APPENDIX A - Service List
OPINION ADOPTING ESTIMATE FOR HUNTERS POINT
The Commission adopts Pacific Gas and Electric Company's (PG&E) estimate of approximately $65.1 million net present value (NPV) for the future decommissioning and site remediation of Hunters Point Power Plant (HPPP).1 The appropriate ratemaking treatment for this cost estimate will be determined in PG&E's 2003 General Rate Case (GRC) application, A.02-11-017.
This decision does not prescribe site remediation measures or dictate clean-up levels. These matters will be determined by the Lead Agency and other regulatory agencies in a public forum when decommissioning actually occurs.
While recovering decommissioning costs based on estimates may sometimes be less desirable than recovering the actual costs, we believe PG&E's cost estimate is adequate for ratemaking purposes. As demonstrated in the volumes of evidence presented in this proceeding, PG&E's environmental decommissioning cost estimate is based on industry-accepted practices to determine the amount of remediation expected to be required at HPPP, and the regulatory requirements expected to apply to those activities once they commence.
We note that Decision (D.) 98-10-029 approved the request of PG&E to withdraw its request to sell the HPPP. This approval was found to be consistent with Pub. Util. Code § 363(c). We also approved an agreement between PG&E and the City and County of San Francisco (CCSF) that set out steps for closing the HPPP.
1 The 1996 GRC adopted estimate of these costs is currently being recovered through the Transition Cost Balancing Account (TCBA) pursuant to D.97-11-074.