D0312059 Appendix B
Word Document PDF Document

STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor

PUBLIC UTILITIES COMMISSION

505 VAN NESS AVENUE

SAN FRANCISCO, CA 94102-3298

December 23, 2003

TO: ALL PARTIES OF RECORD IN APPLICATION 03-07-032

Decision 03-12-059 is being mailed without the Concurrence of Commissioner Brown. The Concurrence will be mailed separately.

Very truly yours,

/s/ ANGELA K. MINKIN by PSW

Angela K. Minkin, Chief

Administrative Law Judge

ANG:sid

Attachment

ALJ/CAB/sid Mailed 12/23/2003

Decision 03-12-059 December 18, 2003

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

In the Matter of the Application of Southern California Edison Company (U 338-E) for Approval of a Power Purchase Agreement under PUHCA Section 32(k) Between the Utility and a Wholly-owned Subsidiary and for Authority to Recover the Costs of Such Power Purchase Agreements in Rates.

Application 03-07-032

(Filed July 21, 2003)

(See Appendix A for a list of appearances.)

OPINION GRANTING SOUTHERN CALIFORNIA EDISON COMPANY'S APPLICATION TO ACQUIRE MOUNTAINVIEW POWER COMPANY, LLC (MVL) EITHER AS A WHOLLY OWNED SUBSIDIARY AND TO ENTER INTO A POWER PURCHASE AGREEMENT WITH MVL FOR ELECTRICITY FROM THE MOUNTAINVIEW POWER PROJECT,

OR AS A UTILITY-OWNED GENERATION FACILITY

TABLE OF CONTENTS

Title Page

OPINION GRANTING SOUTHERN CALIFORNIA EDISON COMPANY'S APPLICATION TO ACQUIRE MOUNTAINVIEW POWER COMPANY, LLC (MVL) EITHER AS A WHOLLY OWNED SUBSIDIARY AND TO ENTER INTO A POWER PURCHASE AGREEMENT WITH MVL FOR ELECTRICITY FROM THE MOUNTAINVIEW POWER PROJECT,

OR AS A UTILITY-OWNED GENERATION FACILITY 2

I. Summary 2

II. Proposed Decision/Alternate Proposed Decision 3

III. Background 4

IV. Motions 8

V. Summary of Parties' Positions 11

VI. FERC Jurisdictional PPA 16

VII. Affiliate Issues 25

VIII. Cost Effectiveness and Need 31

IX. Cost Effectiveness 36

X. PUHCA Section 32(k) Findings 40

XI. CPUC Regulatory Authority 43

XII. The PPA Does Not Violate Any State Law 44

XIII. The PPA Does Not Confer Any Unfair Competitive Advantage 45

XIV. Public Interest and Benefit to Consumers 46

XV. Cost Recovery 47

XVI. Recovery of Initial Capital Outlay 48

XVII. Recovery of Operating Costs 50

XVIII. Incentives 50

XIX. Capital Additions and Betterments 51

XX. Ratemaking Issues 52

XXI. Decommissioning Costs 55

XXII. Expedited Advice Letter Process 56

XXIII. Financing 57

XXIV. CPCN and CEQA Issues 58

XXV. Comments on Proposed Decision 61

XXVI. Assignment of Proceeding 61

Findings of Fact 61

Conclusions of Law 65

ORDER 67

APPENDIX A - List of Appearances

APPENDIX B - Mountainview Cost Categories and Forecasted Costs

OPINION GRANTING SOUTHERN CALIFORNIA EDISON COMPANY'S APPLICATION TO ACQUIRE MOUNTAINVIEW POWER COMPANY, LLC (MVL) EITHER AS A WHOLLY OWNED SUBSIDIARY AND TO ENTER INTO A POWER PURCHASE AGREEMENT WITH MVL FOR ELECTRICITY FROM THE MOUNTAINVIEW POWER PROJECT,

OR AS A UTILITY-OWNED GENERATION FACILITY

I. Summary

This opinion authorizes Southern California Edison Company (Edison) to acquire Mountainview Power Company, LLC (MVL) as a wholly-owned subsidiary of Edison and to enter into a power purchase agreement (PPA) with MVL for the purchase of electricity from Mountainview Power Project (Mountainview), subject to the conditions and modifications set forth herein, or as a utility-owned generation facility. Although the Commission approves Edison's application for a Federal Energy Regulatory Commission (FERC) jurisdictional Power Purchase Agreement (PPA), with modifications, that avenue requires that Edison seek FERC approval for the project before it can go forward. The option agreement Edison has to acquire Mountainview expires February 29, 2004, and there is a risk that Edison cannot obtain the necessary FERC approval in time to exercise the option, putting the opportunity in peril. If Edison chooses to proceed with the project as a utility-owned facility, this opinion issues Edison a certificate of public convenience and necessity (CPCN) now, allowing Edison to immediately exercise the option agreement obviating any risk that FERC approval will not be forthcoming within the option time.

While we authorize Edison to proceed with the proposed FERC jurisdictional PPA, we are desirous of having Mountainview owned and operated as a utility-owned project some time in the future. If legislation is enacted that secures cost recovery of a utility generation investment over the life of the asset, Edison is directed to file an application, within 60 days of the effective date of the legislation, to terminate the PPA and put Mountainview in rate base. Then all costs for Mountainview will be recovered through Commission-jurisdictional rates. Edison will then have MVL agree to terminate the PPA, subject to FERC approval.

Top Of PageNext PageGo To First Page