Under the California Environmental Quality Act (CEQA) and Rule 17.1 of the Commission's Rules of Practice and Procedure (Rules), we must consider the environmental consequences of projects that are subject to our discretionary approval.23 Thus, in deciding whether to approve A.04-05-034, we must consider if doing so will alter an approved project, result in new projects, change facility operations, etc., in ways that have an environmental impact.
The record of this proceeding indicates that approval of A.04-05-034 will not have a significant effect on the environment. In particular, the Application does not request authority for new construction, and the Applicants represent that approval of A.04-05-034 will not result in any to changes to RRLD's operations or use of existing property or facilities. Therefore, the proposed project qualifies for an exemption from CEQA pursuant to Section 15061(b)(3)(1) of the CEQA guidelines. Consequently, there is no need for further environmental review.
23 Pub. Resources Code Section 21080.