Introduction:
This Initial Review Process was developed to create a path for selection and rapid approval of those Applications for Interconnection that do not require an Interconnection Study. The capitalized phrases used in this Appendix A have the same meanings as those in Section 8 of the proposed Rule 21.
Purpose:
The Initial Review determines:
a. If an Application qualifies for Simplified Interconnection;
b. If an Application can be made to qualify for Interconnection with supplemental review determining any potential additional requirements, or
c. If an Interconnection Study is required, the cost estimate and schedule for performing the Interconnection Study.
NOTE:
Failure to pass any screen means that further review, and/or studies, are required before the DG project will be approved for interconnection with the Electrical Corporation. It does not mean that the DG cannot interconnect.
Initial Review Process Flow Chart
Provide Completed Application.