V. Resolution of CMUA Petition for Modification

A. Overview of Issues


How many years' worth of forecast data were provided in the initial load forecast that PG&E delivered to DWR? When was the forecast first delivered to DWR?


What was the amount of "transferred load" that PG&E incorporated from its Bypass Report into the initial load forecast provided to DWR?


How does the "transferred load" impact the power requirements that DWR procured for (1) existing IOU customers as of February 1, 2001 that subsequently became MDL and (2) new load, if any, added by municipalities or irrigation districts after February 1, 2001 that were in areas covered by the "transferred load" forecasts.


To the extent that DWR independently extrapolated additional years of forecast data beyond those provided by PG&E, what, if any, data relating to municipal load bypass incorporated in DWR's calculations?


Do the currently adopted requirements for MDL CRS obligations appropriately take into account the effects of PG&E "transferred load" incorporated into forecasts utilized by DWR? If not, what adjustments to the MDL CRS obligation need to be adopted in order to recognize the effects of PG&E's "transferred load"?

B. Implications of Assumptions Concerning Delivery Date of PG&E Load Forecast Data to DWR

C. Quantification of PG&E "transferred load" Reflected in DWR Forecast

Source of Bypass

Forecast Sales From Bypass Report (in GWh)

2003 Forecast 2000 Actuals Exception

To Irrigation Districts

588

352

237

Municipalization

152

101

51

       

D. Allocation of Transferred Load Exception Among MDL Customers

E. Extent to Which DWR Procurement was Influenced by Forecast Data


"It is clear that DWR, when negotiating long-term power contracts, assumed that a certain amount of customer generation departing load would occur every year and therefore did not procure long-term power for that portion of the load. In fact, such an assumption is based on common sense, since utilities have always faced departing load in various forms, including that caused by an economic downturn, improvements in energy efficiency and building codes, as well as installation of self-generation systems."17

F. Timing of DWR Procurement Relative to Date of Receipt of Forecast

G. Significance of Whether DWR, Itself, Makes the Adjustment

H. Analogies to the U.S. Navy Load CRS Requirement


"SDG&E points out that [Navy] was on bundled service as of February 1, 2001. Under the provisions of D.02-11-022, the Navy thus is obligated to pay the DA CRS on the same basis as other customers that meet that criterion.... Although the Navy procured power under the 80 MW independently of DWR, the power did not begin to flow under the special contract until after February 1, 2001....For at least some period on and after February 1, 2001 up until it began to be served under the special contract, the Navy would have been subject to bundled procurement for meeting its load demand. To the extent that DWR procured the net short for SDG&E bundled load during the period prior to April 1, 2001, some bundled power would have flowed to the Navy."29

8 See Ex. 5.

9 McDonald Testimony, Tr. 1474.

10 See Tr. 2488-2489, (PG&E/Keane).

11 Ex. 3 (Kuga) at DMK-2-3

12 Tr. 2551 (PG&E/Keane).

13 . See Tr. 2676-79 (DWR/McDonald).

14 See Tr. 2593 (DWR/McDonald).

15 See Tr. 2610-12/DWR McDonald.

16 DWR/McDonald RT 2688: 22-28.

17 D.03-04-030, mimeo. at p. 54.

18 . See, Tr. 2608 (DWR/McDonald).

19 Exh. 18, pg. 3, Response 1(g). As clarified by PG&E witness Keane, the forecast in question was a sales forecast (i.e., stated in MWh), not a load forecast (stated in MW capacity). 21 Tr/ 2497:7-9 (PG&E/Keane).

20 22 Tr. 2588:24-25 (DWR/McDonald)

21 22 Tr. 2631:9-12 (DWR/McDonald)

22 22 Tr. 26321:13-23 (DWR/McDonald)

23 Exh. 72 ("Forecast for Distributed Generation in California").

24 Tr. Vol. 12 (DWR/McDonald), p. 1473, line 10 to p. 1474, line 10 (testifying to the time frame over which the forecast for customer generation was prepared).

25 Tr. Vol. 12 (DWR/McDonald), p. 1484 (testifying to the fact that DWR negotiated and executed a material number of contracts between April 2001 and September 13, 2001).

26 See D.03-04-030, p. 64 (slip op.).

27 D.03-07-028, pp. 36-37 (slip op.).

28 D.03-05-036, p. 4 (slip op.).


29 D.03-05-036, p. 7 (slip op).

30 D.03-07-028, p. 57 (slip op.).

Previous PageTop Of PageNext PageGo To First Page