GENERAL OPERATION STANDARDS

Standard 12: Operations Conduct

To ensure safety, and optimize plant availability, the GAO conducts operations systematically, professionally, and in accordance with approved policies and procedures. The GAO takes responsibility for personnel actions, assigns personnel to tasks for which they are trained, and requires personnel to follow plant and operation procedures and instructions while taking responsibility for safety.

Among other things:

Guidelines for Standard 12: Operations Conduct

Standard 13: Routine Inspections

Routine inspections by plant personnel ensure that all areas and critical parameters of plant operations are continually monitored, equipment is operating normally, and that routine maintenance is being performed. Results of data collection and monitoring of parameters during routine inspections are utilized to identify and resolve problems, to improve plant operations, and to identify the need for maintenance. All personnel are trained in the routine inspections procedures relevant to their responsibilities.

Among other things, the GAO creates, maintains, and implements routine inspections by:

Guidelines for Standard 13: Routine Inspections

Standard 14: Clearances

Work is performed on equipment only when safe. When necessary, equipment is taken out of service, de-energized, controlled, and tagged in accordance with a clearance procedure. Personnel are trained in the clearance procedure and its use, and always verify that equipment is safe before any work proceeds.

Among other things:

Guidelines for Standard 14: Clearances

Standard 15: Communications and Work Order Meetings

The availability of the generating asset and safety of personnel is ensured during the execution of work orders by adequate communications and meetings, which may be scheduled or as needed, to review work plans with all affected personnel before work begins. Clear lines of communication exist between personnel responsible for operations, maintenance and engineering groups.

Among other things:

Guidelines for Standard 15: Communications and Work Order Meetings

Standard 16: Participation by Operations Personnel in Work Orders

Operations personnel identify potential system and equipment problems and initiate work orders necessary to correct system or equipment problems that may inhibit or prevent plant operations. Operations personnel monitor the progress of work orders affecting operations to ensure timely completion and closeout of the work orders, so that the components and systems are returned to service.

Among other things:

Guidelines for Standard 16: Participation by Operations Personnel in Work Orders

Standard 17: Records of Operation

The GAO assures that data, reports and other records reasonably necessary for ensuring proper operation and monitoring of the generating asset are collected by trained personnel and retained for at least five years, and longer if appropriate

Guidelines for Standard 17: Records of Operation

Standard 18: Unit Performance Testing

The GAO conducts periodic performance tests as appropriate to identify trends and possible improvements in unit operation. The GAO responds to test results with changes to equipment, policies, routines, or procedures necessary to maintaining unit availability and the unit's ability to support grid operations consistent with the Unit Plan.

Guidelines for Standard 18: Unit Performance Testing

(FOR ILLUSTRATIVE PURPOSES ONLY)

 

TABLE I -SCHEDULE OF MAJOR EQUIPMENT TESTS

TYPE OF TEST

CLASS OF UNIT

Supercritical

330 MW

170 MW

50MW

HRSG

Geothermal

Input/Output Single Valve Point

6 Months

6 Months

6 Months

6 Months

12 Months

Monthly

Input/Output Multiple Valve Point

AOH or 18 Months

AOH or 24 Months

AOH or 24 Months

AOH or 24 Months

AOH or 24 Months

N/A

Boiler Efficiency

AOH or 18 Months

AOH or 24 Months

AOH or 24 Months

AOH or 24 Months

AOH or 24 Months

N/A

Enthalpy Drop

AOH or 18 Months

AOH or 24 Months

AOH or 24 Months

AOH or 24 Months

AOH or 24 Months

N/A

Peak Load Capability

Monthly

6 Months

6 Months

6 Months

6 Months

Monthly

Governor Characteristics

AOH or 12 Months

AOH or 12 Months

AOH or 12 Months

AOH or 12 Months

AOH or 12 Months

6 Months

Quick Load Pickup

N/A

N/A

N/A

N/A

N/A

N/A

Boiler, Superheat, Reheat Safety Valves

AOH or 12 Months

AOH or 12 Months

AOH or 12 Months

AOH or 12 Months

AOH or 12 Months

N/A

Full Load Dump

N/A

N/A

N/A

N/A

N/A

N/A

Cooling Tower

AOH or 12 Months

N/A

N/A

N/A

AOH or 12 Months

AOH or 12 Months

Automatic Dispatch

As Required

As Required

As Required

As Required

As Required

N/A

(FOR ILLUSTRATIVE PURPOSES ONLY)

TABLE II -SCHEDULE OF AUXILIARY EQUIPMENT TESTS

TYPE OF TEST

CLASS OF UNIT

Super-critical

330 MW

170 MW

50MW

HRSG

Geothermal

Feedwater Heater

HP Heaters

6 Months (1&2)

LP Heaters

18 Months
(1&3)

24 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

N/A

Circulating Water Pumps and Motors

18 Months

(1)

24 Months

(1)

24 Months

(1)

24 Months

(1)

24 Months

(1)

12 Months

(4)

Boiler Feed Pumps and Motors

3 months

(1)

24 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

N/A

Condensate Pumps and Motors

18 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

12 Months

(4)

Air Preheater

18 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

24 Months

(1&3)

N/A

Fire Pumps and Diesel Engine

12 Months

12 Months

12 Months

12 Months

12 Months

12 Months

1. Tests to be run at test point nearest guaranteed or rated output.

2. Test to be performed in conjunction with I/O single valve point test.

4. Tests to be performed in conjunction with cooling tower test.

Standard 19: Emergency Grid Operations

The GAO prepares for conditions that may be reasonably anticipated to occur during periods of stress or shortage on the state's electric grid. During such periods of stress or shortage, the GAO makes operational decisions to maximize each unit's availability and ability to support grid operations.

Among other things the GAO:

Guidelines for Standard 19: Emergency Grid Operations

Standard 20: Preparedness for On-Site and Off-Site Emergencies

The GAO plans for, prepares for, and responds to reasonably anticipated emergencies on and off the plant site, primarily to protect plant personnel and the public, and secondarily to minimize damage to maintain the reliability and availability of the plant.

Among other things, the GAO:

Guidelines for Standard 20: Preparedness for On- and Off-Site Emergencies

Standard 21: Plant Security

To ensure safe and continued operations, each GAO provides a prudent level of security for the plant, its personnel, operating information and communications, stepping up security measures when necessary.

Guidelines for Standard 21: Plant Security

Standard 22: Readiness

Until a change in a unit's long-term status, except during necessary maintenance or forced outages, the GAO is prepared to operate the unit at full available power if the Control Area Operator so requests, after reasonable notice, when such operation is permitted by law and regulation.

Among other things, the GAO:

Guidelines for Standard 22: Readiness

Standard 23: Notification of Changes in Long-Term Status of a Unit

The GAO notifies the Commission and the Control Area Operator in writing at least 90 days prior to a change in the long-term status of a unit. The notification includes a description of the planned change.

Guidelines for Standard 23: Notification of Changes in Long-Term Status of a Unit

Standard 24: Approval of Changes in Long-Term Status of a Unit

The GAO maintains a unit in readiness for service in conformance with Standard 22 unless the Commission, after consultation with the Control Area Operator, affirmatively declares that a generation facility is unneeded during a specified period of time. This standard is applicable only to the extent that the regulatory body with relevant ratemaking authority has instituted a mechanism to compensate the GAO for readiness services provided.

Guidelines for Standard 24: Approval of Changes in Long-Term Plant Status

Standard 25: Transfer of Ownership

The GAO notifies the Commission and the Control Area Operator in writing at least 90 days prior to any change in ownership.

Standard 26: Planning for Long-Term Unit Storage

At least 90 days before a change in the long-term status of an electric generation unit, other than permanent shutdown and/or decommissioning, the GAO shall submit to the Commission plans and procedures for storage, reliable restart, and operation of the unit.

Guidelines for Standard 26: Planning for Long-Term Unit Storage

Standard 27: Flow Assisted Corrosion

Where circumstances require it, the GAO has a flow-assisted corrosion program, which identifies vulnerable equipment, provides for regular testing of that equipment, and responds appropriately to prevent high energy pipe failures.

Guidelines for Standard 27: Flow Assisted Corrosion

Standard 28: Equipment and Systems

GAO complies with these Operation Standards (1-27) considering the design bases (as defined in the Appendix) of plant equipment and critical systems. The GAO considers the design basis of power plant equipment when as required by other standards it, among other things:

Guidelines for Standard 28: Equipment and Systems

SAMPLE

POINTS

PARAMETERS

NORMAL RANGE

ACTION

LEVEL

ACTION

LEVEL

ACTION LEVEL

CONTROLED

SHUTDOWN

     

1

2

3

 

Condensate Pump Discharge

Cation Conductivity (Micromhos/cm2)

less than 0.2

0.2 - 0.35

0.35 - 0.65

greater than0.65

 

Dissolved Oxygen, ppb

less than 20

20 - 40

greater than 40

   

Feedwater

PH

8.8 - 9.3

less than8.8, greater than 9.3

     
 

Cation Conductivity

less than 0.2

0.2 - 0.35

0.35 - 0.65

greater than 0.65

 
 

Oxygen Scavenger, ppb

1 - 3

less than 1 or greater than 3

     
 

Dissolved Oxygen, ppb

less than 5

5 - 10

10 - 20

greater than 20

 

Boiler Blowdown

pH

9.3 - 9.9

less than 9.3 or greater than 9.9

less than 9.0

less than 8.5

less than 8.0

 

Phosphate, ppm

1 - 3

less than 1 or greater than 3

less than0.5

0

 
 

Silica, ppm

- Silica Action Level Guidelines

         
 

Chloride, ppm

0

0 - 1

1 - 2

2 - 3

greater than 3

 

NaCl , ppm

0

greater than 0 or less than 2

greater than 2 or less than 3

greater than 3 not less than 5

greater 5

Previous PageTop Of PageNext PageGo To First Page