| Word Document PDF Document |
COM/GFB/eam Mailed 4/25/05
Decision 05-04-049 April 21, 2005
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of Southern California Edison Company (E 338-E) for Authority to Institute a Rate Stabilization Plan with a Rate Increase and End of Rate Freeze Tariffs. |
Application 00-11-038 (Filed November 16, 2000) |
|
Emergency Application of Pacific Gas and Electric Company to Adopt a Rate Stabilization Plan. (U 39 E) |
Application 00-11-056 (Filed November 22, 2000) |
|
Petition of THE UTILITY REFORM NETWORK for Modification of Resolution E-3527. |
Application 00-10-028 (Filed October 17, 2000) |
OPINION GRANTING AND DENYING INTERVENOR COMPENSATION
Title Page
OPINION GRANTING AND DENYING INTERVENOR COMPENSATION 22
B. Requirements for Awards of Compensation 55
D. Substantial Contribution 77
1. Contribution to the Settlement with Edison 88
2. Contribution to the Commission's Decisions on TURN's
Initial Compensation Request 1313
E. Reasonableness of Requested Compensation 1414
1. Overall Benefits of Participation 1616
2. Hours Claimed and Allowed 1717
G. Assignment of Proceeding 2727
OPINION GRANTING AND DENYING INTERVENOR COMPENSATION
This decision awards The Utility Reform Network (TURN) $389,119.68 in compensation for (1) its further participation in the federal district court proceedings in which Southern California Edison Company (Edison) and Pacific Gas and Electric Company (PG&E) challenged the Commission's jurisdiction to limit the utilities' recovery of increased wholesale procurement costs, and (2) its efforts in the judicial review of Decision (D.) 02-06-070, which awarded TURN intervenor compensation for its earlier participation in those federal proceedings. However, the decision denies TURN compensation for its judicial litigation costs of challenging the Commission's settlement in resolution of the Edison federal district court proceeding.
These consolidated proceedings include the Post-Transition Ratemaking dockets (A.99-10-016 et al.) in which we addressed post-rate freeze recovery of rate freeze costs, and the Rate Stabilization Plan dockets (A.00-11-038 et al.) in which we addressed PG&E's and Edison's applications for emergency relief from the skyrocketing wholesale electricity prices in 2000. In the Post-Transition Ratemaking dockets, we determined that Pub. Util. Code § 368 bars utilities from recovering, through post-rate freeze rates, costs incurred during the rate freeze. (D.99-10-057, as modified by D.00-03-058.) (Subsequent statutory references are to the Public Utilities Code unless otherwise indicated.) In the Rate Stabilization Plan dockets, however, we ultimately authorized and implemented a rate increase of four cents/kWh in recognition of Edison's and PG&E's increased costs due to the extraordinary circumstances in California's wholesale power markets. (D.01-03-082.)
In November 2000, Edison and PG&E filed separate federal court actions challenging the Commission's jurisdiction to limit the utilities' recovery of their increased wholesale procurement costs.1 TURN intervened in those actions.
The two federal lawsuits followed different procedural paths. PG&E filed for bankruptcy in April 2001, and the Commission entered into a settlement of the bankruptcy in December 2003. (See D.03-12-035.) Pursuant to the terms of the bankruptcy settlement, PG&E's federal court action will be dismissed.2
The Commission and Edison entered into a Joint Stipulation in settlement of Edison's federal lawsuit on October 2, 2001. TURN appealed the District Court's judgment affirming the settlement to the Ninth Circuit Court of Appeals. On September 23, 2002, the Ninth Circuit affirmed the District Court's judgment in part and certified several questions to the California Supreme Court regarding whether the agreement violated state law.3 On August 21, 2003, the Supreme Court answered the Ninth Circuit, concluding that the Stipulated Judgment did not violate state law.4
As these events were unfolding, TURN in July 2001 filed a request for compensation for the costs, among others, of the first six months of its participation in Edison's and PG&E's federal court actions. The Commission granted TURN's request 11 months later in D.02-06-070, finding that TURN had made a substantial contribution to the various decisions affecting the utilities' ability to recover their costs of wholesale power during the energy crisis. Because the federal lawsuits sought to challenge the Commission's authority to make those decisions, the Commission found that the costs of TURN's federal court work were reasonably incurred in order to make its substantial contribution to the adopted decisions.
Edison and PG&E each applied for rehearing of D.02-06-070 on the issue of compensation for TURN's federal district court work. We denied rehearing of our order, as modified. (See D.03-04-034.) Edison petitioned the Second Appellate District of the California Court of Appeal for writ of review of those orders. On October 8, 2003, the court issued the writ granting review. The court ultimately rejected Edison's appeal on April 19, 2004.5 Sixty days after the court's decision upholding D.02-06-070 and D.03-04-034,6 TURN filed this request for compensation. Edison opposes TURN's request only insofar as TURN seeks an award enhancement, full compensation for time spent preparing this request, and compensation for time spent on media and outside lobbying. TURN has replied to Edison's opposition.
1 Edison v. Lynch et al., Case No. 00-12056-RSWL (Mcx), United States District Court for the Central District of California (Western Division) (filed November 13, 2000), and PG&E v. Lynch, et al., Case No. CV 00-4128 (SBA), United States District Court for the Northern District of California (filed November 8, 2000).2 PG&E v. Lynch remains an open docket, pending resolution of an appeal of the Commission's decision approving the settlement (D.03-12-035) and of the confirmation order approving the settlement in bankruptcy court (In re Pacific Gas and Electric Company, Debtor, United States Bankruptcy Court, Northern District of California, San Francisco Division, Case No. 01-30923 DM, Confirmation Order, dated December 22, 2003).
3 Edison v. Lynch, 308 F.3d 794 (9th Cir. 2002). 4 Edison v. Peevey (2003) 31 Cal.4th 781. The Ninth Circuit entered final judgment in Edison v. Lynch on December 19, 2003, bringing Edison's federal lawsuit to a close. (See 353 F.3d 648.) 5 Edison v. CPUC (2004) 117 Cal. App.4th 1039. 6 On November 22, 2002, TURN filed a request for intervenor compensation for its work in the federal lawsuits from mid-2001 through September 2002. The Commission denied the request without prejudice because the Commission wanted to await final determinations on the federal lawsuits before evaluating it. (See D.03-12-044.)