II. DISCUSSION

A. The Otay Mesa PPA should not have been considered as part of SDG&E's RFP solicitation, but rather as a bilateral contract.

TURN/UCAN raise two main objections to the Commission's approval of the Otay Mesa PPA. First, they assert that SDG&E ignored its threshold criteria because the Otay Mesa PPA would not be in service by the RFP cutoff date of June 1, 2007. (TURN/UCAN's Rhg. App., p. 16.) Next, TURN/UCAN assert that SDG&E violated its own RFP evaluation criteria by selecting Otay Mesa without demonstrating that it was superior to other options bid into the RFP. (TURN/UCAN's Rhg. App., p. 18.) Based on these objections, TURN/UCAN maintain that we improperly concluded that SDG&E had conducted a reasonable solicitation. (TURN/UCAN's Rhg. App., p. 13.)

Our consideration of the allegations raised by TURN/UCAN lead us to conclude that limited rehearing should be granted. Based on the evidentiary record, we should not have considered the Otay Mesa PPA a "winning bidder" of SDG&E's RFP at all, but rather a bilateral contract to meet needs outside the scope of the RFP. SDG&E presented evidence throughout the proceeding that the Otay Mesa PPA was negotiated separately, after its grid reliability needs were met. (See, e.g., RT 52, p. 6552:9-14 (Avery testimony regarding SDG&E's decision to pursue projects that were not necessary to meet the RFP requirements); RT 52, pp. 6582:6-21 & 6590:23 - 6591:11 (Avery testimony regarding sequence of RFP and SDG&E's decision to pursue Calpine option after RFP needs were met).) As such, we incorrectly concluded that the Otay Mesa PPA was the result of a competitive solicitation and reasonable under Public Utilities Code section 454.5(c)(1).1

Although we did not use the appropriate procedure to approve the Otay Mesa PPA, we do not believe it is necessary to reject the PPA outright. SDG&E has clearly demonstrated a need for the power to be supplied by the Otay Mesa PPA. (See, e.g., RT 51, pp. 6452:26 - 6455:23 (Anderson); RT 49, p. 6077:2-8 (Lorenz); Exh. RFP-6, p. LPL-5 (Lorenz).) Furthermore, there was convincing evidence that a similar opportunity such as the Otay Mesa PPA would not likely be available in the immediate future. As the Decision notes,

"As of today, Palomar and Otay Mesa provide the only possible sources of new generation with capacity over 500 MW, in SDG&E's service territory, that can serve SDG&E's needs in the foreseeable future. These facilities are fully permitted, have water for cooling purposes, which helps them operate at low heat rates, and have already received the appropriate imprimatur from local and regional environmental and community groups. SDG&E's witness hypothesized that any other new generation source comparable in size to Palomar or Otay Mesa that began to germinate as a concept today would take at least four years to come on-line."

(D.04-06-011, p. 55.)

Since SDG&E has already established a need for the Otay Mesa PPA, we do not believe it is necessary to reconsider this issue again, as the need identified by SDG&E does not change whether the Otay Mesa PPA is the result of a competitive solicitation or a bilateral contract.2 Moreover, parties to the proceeding were provided an opportunity to, and did, cross-examine SDG&E witnesses on the need for the Otay Mesa PPA, including the fact that it was not necessary to meet SDG&E's grid reliability needs. (See, e.g., RT 50, pp. 6189:15 - 6207:16 (Lorenz); RT 52, pp. 6537:2 - 6538:8 (Avery).)

Although the need for power from the Otay Mesa PPA has been demonstrated, we find that the record does not contain evidence to demonstrate that the PPA is beneficial to SDG&E ratepayers and should be considered reasonable pursuant to section 454.5(c)(3). Therefore, limited rehearing is granted for the sole basis for determining the reasonableness of the PPA, as required by section 454.5(c)(3).3 Our grant of a limited rehearing should not be considered a rejection of the PPA. Rather, by today's decision, we consider the review of the PPA for purposes of whether it should be approved or not as a matter still pending before us. This includes issues concerning reasonableness and benefits to ratepayers.

B. The Commission has authority to impose stranded cost obligations associated with new utility generation on current bundled SDG&E customers who may become future direct access or community choice aggregation customers.

1. Direct Access Customers

"It is the intent of the Legislature that each retail end-use customer that has purchased power from an electrical corporation on or after February 1, 2001, should bear a fair share of the [DWR's] electricity purchase costs, as well as electricity purchase contract obligations incurred... that are recoverable from electrical corporation customers in commission-approved rates. It is further the intent of the Legislature to prevent any shifting of recoverable costs between customers."

(Pub. Util. Code, § 366.2, subd. (d)(1) (emphasis added).)4 Had the Legislature intended to obligate direct access customers to pay only their "fair share" of DWR costs, it would not have included the phrase "as well as electricity purchase contract obligations incurred... that are recoverable from electrical corporation customers in commission-approved rates" nor stated that it was "further" the Legislature's intent "to prevent any shifting of recoverable costs between customers." (See, e.g., Breshears v. Indiana Lumbermen (1967) 256 Cal.App.2d 245, 250 (discussing plain language of statute); People v. Baker (1968) 69 Cal.2d 44, 50 [courts should not insert or delete words in a statute or give a different meaning to the words used].) By including these statements, and specifically the phrase "recoverable costs," the Legislature clearly intended retail end-use customers to be responsible for their fair share of all costs incurred on their behalf. This would include utility retained generation costs, as well as stranded costs associated with any new contracts entered into by the utilities at the time these future direct access customers were bundled utility customers.5 Otherwise, there would be unlawful cost-shifting. (See, Pub. Util. Code, §366.2, subd. (d)(1); see

also, Pub. Util. Code, §451 [requiring just and reasonable cost allocation].) Thus, we acted within our authority when we determined that current bundled customers who may become future direct access customers should bear their fair share of stranded costs from the Ramco and Palomar contracts associated with their departure from bundled service.6

2. Community Choice Aggregation Customers

City's assertions regarding Finding of Fact 19 and Conclusion of Law 8 are based on text in the Decision stating:

"We therefore adopt the same mechanism here that we did in the Edison/Mountainview decision, D.03-12-059, whereby all customers of SDG&E that are currently ineligible for direct access are obligated to pay for the stranded costs of any new generation for the next ten years. This will insure that neither the utility, nor its bundled customers, will be forced to pay stranded costs for these generation assets in the event that new direct access is permitted."

(City's Rhg. App., p. 5 (quoting D.04-06-011, p. 42).) City argues that a "plain reading" of this language could only mean that stranded cost obligations only apply to future direct access customers. (City's Rhg. App., p. 5.) However, it believes the language in Finding of Fact 19 and Conclusion of Law 8 could be interpreted as also imposing stranded cost obligations on future CCA customers. Therefore, City requests that the Finding of Fact 19 and Conclusion of Law 8 be clarified to state that any stranded cost obligations do not apply to future CCA customers. (City's Rhg. App., p. 6.) We disagree with City's reading of Finding of Fact 19 and Conclusion of Law 8, and therefore deny their request for clarification.

Our interpretation is also not contrary to the Legislative mandate of AB 117. AB 117, codified in section 366.2, specifically provides

"A retail end-use customer purchasing electricity from a community choice aggregator pursuant to this section shall reimburse the electrical corporation that previously served the customer for all of the following:
. . .
(2) Any additional costs of the electrical corporation recoverable in commission-approved rates, equal to the share of the electrical corporation's estimated net unavoidable electricity purchase contract costs attributable to the customer, as determined by the commission, for the period commencing with the customer's purchases of electricity from the community choice aggregator, through the expiration of all then existing electricity purchase contracts entered into by the electrical corporation."

(Pub. Util. Code, §366.2, subd. (f)(2).) Electricity purchase contracts are not limited only to those instances where a utility purchases electricity, but can include contracts for turnkey operations.8 The Ramco and Palomar contracts are "necessary to enable SDG&E to meet its electric grid reliability capacity needs and reserve margin requirements during 2005 - 2007." (SDG&E Motion, p. 2.) Therefore, CCA customers who are bundled customers during the period these grid reliability and reserve margin requirements are acquired should be required to pay their fair share of stranded costs associated with their departure from bundled service. This is consistent with the provisions of section 366.2(f)(2).

"This chaotic and every-changing energy environment has caused, and is causing, constant recalibration of state and Commission policies toward the present and future rights and obligations of investor-owned utilities, providers of DA, community aggregators, local jurisdictions proposing municipalization, and other stakeholders in the energy service industry. . . . [T]he current substantial uncertainty surrounding state and federal energy policy, the lack of clear legislative direction on recovery of investment in generation assets as compared to purchase power contracts, the considerable uncertainty pertaining to the stability of SDG&E's future retail customer base, and the general risks inherent in the ownership and operation of major generation facilities above and beyond the risks associated with electric distribution facilities require that utility investment in new generation be strongly supported . . . [to ensure] the full recovery of all capital and operating costs over the life of the generation investment."

(SDG&E Motion, pp. 27-28 (emphasis in original).) In their testimony and briefs, TURN/UCAN also advocated that all current bundled SDG&E customers who could become future DA or CCA customers should bear an ongoing responsibility for any costs that were incurred on their behalf while they were taking bundles service. (See, e.g., Ex. RFP-59 (Woodruff), pp. 5, 41-45; Concurrent Brief of The Utility Reform Network and the Utility Consumers Action Network on the Motion of San Diego Gas & Electric Company for Approval to Enter into New Electric Resource Contracts, March 8, 2004, pp. 82-85.) The Decision also refers to "future changes to the retail market structure" as a basis for imposing stranded costs obligations. As noted above, community choice aggregation was identified as a "future change" in the current retail energy market. Therefore, our determination to impose stranded cost obligations on future CCA customers is supported by the record.

C. Commissioner Peevey's participation in voting on the SDG&E Motion does not violate due process.

D. AReM's request for clarification is denied.

1 Unless otherwise stated, all statutory references are to the Public Utilities Code. 2 Events arising since the Decision was issued only serves to reinforce the need for the Otay Mesa PPA. For example, in D.04-07-028, we determined that the utilities should have more responsibility for local area reliability within their own service territories. (See D.04-07-028, pp. 7-8.) To some extent, the Otay Mesa PPA will help to meet these local reliability needs. In D.04-10-035, we accelerated the phase-in of the 15-17% planning reserve margin from January 1, 2008 to June 1, 2006. (D.04-10-035, p. 16.) Consequently, SDG&E will have a need for capacity sooner than previously anticipated. 3 Since we have determined that the Otay Mesa PPA is in actuality a bilateral contract, TURN/UCAN's assertions of legal error with respect to the Otay Mesa PPA are moot. 4 Although AB 117 is primarily about community aggregation programs, section 366.2(d) specifically conveys the Legislature's intent concerning the cost responsibility of each retail end-use customer who was a customer on or after February 1, 2001. The Commission has determined that this cost responsibility applies to those customers that subsequently become direct access customers (see, e.g., D.02-11-022 and D.02-12-027) or municipal departing load customers (see, e.g., D.03-07-028 and D.03-08-076). Challenges to the Commission's interpretation of AB 117 have been denied by the California Supreme Court. (See, e.g., Modesto Irrigation District v. Public Utilities Commission, et al., Case Nos. S119310, S119365, S119368, S119376 (petition for writ of review denied February 18, 2004); Strategic Energy et al. v. CPUC, Case No. S112802 (petition for writ of review denied April 30, 2003).) 5 AReM also concludes that since AB 117 specified in greater detail the stranded cost obligations of CCA customers, then future DA customers must only be responsible for their "fair share" of DWR costs, since that is the only cost specified in section 366.2(d)(1). (AReM's Rhg. App., p. 7.) This conclusion is in error. As discussed, AB 117 is primarily about community choice aggregation, a new program. Not surprisingly, the Legislature has provided more detail regarding this program than for direct access. Moreover, as discussed, section 366.2(d)(1) refers to all "recoverable costs," not just DWR costs. 6 AReM had raised a similar argument in its application for rehearing of D.03-12-059, which authorized Southern California Edison Company to acquire Mountainview Power Company, LLC as a subsidiary and enter into a 30 year power purchase contract with it ("Mountainview Decision"). In that decision, the Commission determined that "all customers currently ineligible for direct access will be obligated to pay for stranded costs related to Mountainview for the first 10 years of its life." (D.03-12-059, p. 35.) In denying rehearing, the Commission noted that retail customers departing to purchase power from community aggregators were responsible for their fair share of DWR and utility contract costs "stranded" by their departure and that this same principle of fairness applied to direct access customers. (See D.04-04-019, p. 17 (the stranded cost provision adopted for Mountainview "was adopted to prevent unfair cost-shifting to bundled customers, consistent with current state policy.").) 7 The Legislature's focus was on cost-shifting, and assuring that costs incurred on behalf of all those ineligible for DA could not be avoided by a customer simply by departing the system. (See, Pub. Util. Code, §366.2, subd. (d)(1).) 8 In a contract for a turnkey operation, the developer is responsible for building the power plant and preparing it for commercial service. Once the plant is completed and ready for commercial service, the utility will purchase the plant from the developer. The utility, as owner of the plant, will then determine when to operate the plant and the amount of energy to be generated. 9 Moreover, City's assertion that "SDG&E will no longer need to provide power for up to 9% of its current load" when City becomes a community choice aggregator is speculative at best. Further, the issue is about grid reliability, and not about who will become a community choice aggregator. Because the utilities are the providers of last resort, the utilities must purchase electricity in response to this reliability requirement. 10 City also states that it may "have to consider its permitting and legal options concerning the construction of the Ramco facility and facilities necessary to provide the transmission of power from the Otay Mesa project" if the Commission does not grant its rehearing request. (City's Rhg. App., p. 8.) City appears to be insinuating that even if there is no basis for finding legal error, rehearing must be granted or else it will undermine the approved contracts. By resorting to threats, City has undercut its legal challenge to the Decision. 11 Thus, even under the stricter standard of "prejudgment of disputed issues of fact," Commissioner Peevey would not have been disqualified. 12 Further, the Decision clearly states in the beginning that "for the two turn-key projects, Ramco and Palomar, all customers of SDG&E that are currently ineligible for direct access are obligated to pay for stranded costs of these generation projects for the next ten years." (D.04-06-011, p. 6.)

Previous PageTop Of PageNext PageGo To First Page