A. Background

B. Summary of the Petitions

C. Responses to the Petitions

    i. Merced and Modesto

D. Discussion

6 Commission decisions issued in R.02-01-011, including D.04-11-014, D.04-12-059, and D.05-01-040, use the verb "excepted" and its conjugated forms. Today's Decision uses the verbs "except" and "exempt" synonymously.

7 Pursuant to D.04-11-015, the Energy Recovery Bond Charges will replace the RAC.

8 Some CTC costs are not attributable to the energy crisis, but were caused by the transition to a competitive electricity market.

9 Governor's Emergency Proclamation dated January 17, 2001. (D.02-02-051, Appendix B.)

10 The bankruptcy Regulatory Asset was sized to provide PG&E with the necessary revenue, cash flow, and capital structure to pay creditors in full and to enable PG&E to emerge from bankruptcy as an investment grade company.

11 As described more fully in D.03-12-035, PG&E's customers had to contribute several billion dollars over and above the cost of the Regulatory Asset to enable PG&E to emerge from bankruptcy and pay its creditors in full.

12 D.04-02-062, mimeo., pp. 4 - 7, 22 - 23, 34 -35, and 40 [Conclusion of Law (COL) 8].

13 NCPA did not respond to Merced's and Modesto's petitions.

14 PG&E filed Advice Letter (AL) 2624-E on February 7, 2005, to eliminate the Regulatory Asset Revenue Adjustment Mechanism (RARAM) and transfer any remaining balance in the RARAM to the Energy Recovery Bond Balancing Account. The RARAM and RAC will terminate if and when AL 2624-E goes into effect.

15 All statutory references are to the Public Utilities Code unless otherwise indicated.

16 The transferred load that is exempted from the DWR Power Charge by D.04-11-014, as modified and affirmed in D.04-12-059, is load that was forecast by PG&E to be transferred to POUs during 2001-2003. (D.04-11-014, mimeo., p. 18.) This transferred load does not encompass the load served by PG&E during 2000, when PG&E incurred the preponderance of the costs that ultimately resulted in its filing for bankruptcy. The Commission subsequently authorized PG&E to recover these bankruptcy-related costs through the RAC and Energy Recovery Bond Charges.

17 D.04-02-062, mimeo., pp. 22 -23, 34 - 35, and 40 [COL 8].

Previous PageTop Of PageNext PageGo To First Page