Standard of Review for this Acquisition

Commission authorization pursuant to §§ 851 and 8544 is necessary in order for the applicants to assume indirect control of Valencia. The Commission has previously determined that such approval will only be granted where the proposed transfer of control is in the public interest. The Commission may use the standards set out in § 854(b) and (c) to "inform" its public interest determination. (Decision (D.) 02-12-068, mimeo. at 9.) Due to the nature of the proposed transfer, which is an indirect change of control several corporate ownership steps removed from the utility holding company, where the holding company has little, if any, day-to-day involvement with the public utility, the primary focus of our evaluation will be the transfer's effects on ratepayers.

4 All citations are to the Public Utilities Code unless otherwise indicated.