10. SDG&E's Wildfires Update

When SDG&E filed A.04-06-035, $66.4 million had already been recorded to SDG&E's Wildfires Account through May 31, 2004. As updated in Ex. SDG&E-9,49 SDG&E's actual total firestorm costs recorded through December 31, 2004 are $70.6 million, representing a difference of $4.2 million from May 31, 2004. According to SDG&E, the difference is the result of approximately $0.2 million of O&M (primarily environmental costs and accounting adjustments) and $4.0 million of capital expenditures primarily incurred for the rebuilding of Circuit 7950 and the smaller amount spent on Circuit 176 that serves the eastern area of the city of Poway.

$2.9 million of the additional costs recorded through December 31, 2004 are incremental Commission jurisdictional costs, and according to SDG&E, the balance of $1.3 million is non-incremental and should be excluded from the Wildfires Account. The capital costs were not included when the application was filed because SDG&E records the costs in the Wildfires Account after the work is completed.51

On February 4, 2005, SDG&E filed Ex. SDG&E-10, which as errata to Ex. SDG&E-9, made several adjustments to the update. As updated52 in Ex. SDG&E-10, SDG&E's actual total firestorm costs recorded through December 31, 2004 are $71.1 million, representing an increase of $4.7 million ($71.1 million less $66.4 million) from May 31, 2004. Thus the errata, Ex. SDG&E-10, increased the total by $500,000 compared to the Late-filed Update Ex. SDG&E-9 ($71.1 million less $70.6 million).

Wildfire Costs Including Update & Errata

   

CPUC

 

Total Cost

(FERC) Electric Transmission

Electric Distribution

Gas

Total

CPUC

O&M Expenses:

         

Pre-Update O&M

$ 18,032

$ 1,569

$ 15,865

$ 598

$ 16,463

Internal Labor

$ 11

1

$ 10

$ -

$ 10

Materials

4

(1)

5

-

5

Overhead

10

1

9

-

9

Vehicle Charges

(2)

-

(2)

-

(2)

External Labor

8

-

8

-

8

Services/Other

225

16

$ 208

1

209

Update & Errata

$ 256

$ 17

$ 238

1

239

Total O&M

$ 18,288

$ 1,586

$ 16,103

$ 599

$ 16,702

Capital Costs:

         

Pre-Update Capital

$ 48,395

$ 6,847

$ 41,445

$ 103

$ 41,548

Internal Labor

$ 47

-

$ 41

$6

47

Materials

19

-

17

2

19

Overhead

1,229

2

1,213

14

1,227

Vehicle Charges

30

-

29

1

30

External Labor

342

-

342

-

342

Services/Other

2,813

6

2,807

-

2,807

Update & Errata

4,480

8

4,449

23

4,472

Total Capital

$52,875

$ 6,855

$ 45,894

$ 126

$46,020

Updated Total

$ 71,163

$ 8,441

$ 61,997

$ 725

$ 62,722

According to SDG&E, the final difference is the result of approximately $0.3 million of O&M (primarily environmental costs and accounting adjustments) and $4.4 million of capital expenditures primarily incurred for the rebuilding of Circuit 7953 and the smaller amount spent on Circuit 176 that serves the eastern area of the city of Poway. As revised, $3.2 million of the additional costs recorded through December 31, 2004 are incremental Commission jurisdictional costs, and according to SDG&E, the balance of $1.5 million is non-incremental and should be excluded from the Wildfires Account.

Memo Account-Eligible Wildfire Costs
Including Update & Errata

 

Total (CPUC) (a)

Memo Account (b)

Current Rates (b)

Pre-Update O&M

Internal Labor

Materials

Overhead

Vehicle Charges

External Labor

Services/Other

Update & Errata

Total O&M

Capital Costs:

Pre-Update Capital

Internal Labor

Materials

Overhead

Vehicle Charges

External Labor

Services/Other

Update & Errata

Total Capital

Total Wildfire

$ 16,463

$ 12,056

$ 4,407

$ 10

-

$ 10

5

-

5

9

44

(35)

(2)

-

(2)

8

-

8

209

(17)

226

$ 239

$ 27

$ 212

$ 16,702

$ 12,083

$ 4,619

     

$ 41,548

$ 25,605

$15,943

$ 47

5

42

19

19

-

1,227

5

1,222

30

-

30

342

342

-

2,807

2,745

$62

$ 4,472

$ 3,116

$ 1,356

$ 46,020

$ 28,721

$ 17,237

$ 62,722

$ 40,804

$ 21,919

(a) Ex. SDG&E-10, attached Ex. D-1.

(b) Ex. SDG&E-10, attached Ex. D-2.

On February 9, 2004, ORA and UCAN filed comments on SDG&E's updated testimony and errata. ORA had no objections. UCAN was succinct: it questioned the late inclusion of $600,000 of costs incurred prior to May 31, 2004; and secondly, UCAN pointed out that the update and errata include $209,000 of environmental costs which it believes supports UCAN's contention that the environmental costs are connected with the cost of installation of a capital project and should be capitalized.54 UCAN does not convince us that SDG&E's earlier omission is somehow unrecoverable when included in an update. We know from SDG&E's testimony and ORA's review that SDG&E established reasonable accounting procedures to segregate and track the Wildfire costs. Corrections and updates are not innately unreasonable. We will not make this adjustment.

49 Filed on January 18, 2005.

50 "Circuit 79 is a 12 kV electric distribution line that traverses through Cuyamaca Rancho State Park. Circuit 79 was extensively damaged during the firestorm and as a result had to be rebuilt and relocated." (Ex. SDG&E-9. p. 1-2.)

51 Ex. SDG&E-9. p. 1.

52 Ex. SDG&E-10, p 2.

53 "Circuit 79 is a 12 kV electric distribution line that traverses through Cuyamaca Rancho State Park. Circuit 79 was extensively damaged during the firestorm and as a result had to be rebuilt and relocated." (Ex. SDG&E-9. p. 1-2.)

54 UCAN comments, p. 3.