In evaluating whether a customer made a substantial contribution to a proceeding we look at several things. First, did the ALJ or Commission adopt one or more of the factual or legal contentions, or specific policy or procedural recommendations put forward by the customer? (See §1802(i).) Second, if the customer's contentions or recommendations paralleled those of another party, did the customer's participation materially supplement, complement, or contribute to the presentation of the other party or to the development of a fuller record that assisted the Commission in making its decision? (See §§ 1802(i) and 1802.5.) As described in § 1802(i), the assessment of whether the customer made a substantial contribution requires the exercise of judgment.
In assessing whether the customer meets this standard, the Commission typically reviews the record, composed in part of pleadings of the customer and, in litigated matters, the hearing transcripts, and compares it to the findings, conclusions, and orders in the decision to which the customer asserts it contributed. It is then a matter of judgment as to whether the customer's presentation substantially assisted the Commission.2
Should the Commission not adopt any of the customer's recommendations, compensation may be awarded if, in the judgment of the Commission, the customer's participation substantially contributed to the decision or order. For example, if a customer provided a unique perspective that enriched the Commission's deliberations and the record, the Commission could find that the customer made a substantial contribution.3
With this guidance, we turn to the claimed contributions of each intervenor requesting compensation.
5.1. 280 Citizens
280 Citizens participated actively throughout the Jefferson-Martin proceeding. It protested PG&E's application, participated in the environmental review process, conducted and responded to discovery, submitted extensive prepared testimony, conducted cross-examination, filed briefs, and commented on the proposed and alternate decisions. 280 Citizens submits that it made a substantial contribution regarding several issues, including the route for the Jefferson-Martin project, the Commission's environmental review, need and timing for the project, EMF issues, community values, seismic issues, visual impacts, construction impacts, project costs, and biological impacts. We discuss 280 Citizens' contributions on specific issues below.
280 Citizens opposed both PG&E's proposed overhead route (Route 1A) and PG&E's underground alternative (Route 1B) for the southern portion of the Jefferson-Martin project. Commencing with scoping comments during the environmental review process, 280 Citizens identified a number of alternative routes and route segments aimed at reducing adverse impacts on residential areas, schools, and daycare facilities in the southern portion of the project area.
In its briefs, 280 Citizens stated that it supported the Partial Underground Alternative (PUA), developed by the Commission's environmental consultant, "or a variation thereof." During the evidentiary hearings, 280 Citizens expressed a preference for a Modified PUA (MPUA) that would have relocated part of the underground portion of the PUA up to 25 feet to the west to reduce EMF exposure on nearby residences.
One alternative route that 280 Citizens suggested during the scoping process, which it called the Underground to Trousdale Drive route, was the same, in essential respects, as the adopted hybrid underground/overhead route, which combines the southernmost part of underground Route 1B with the portion of the overhead Route 1A north of Trousdale Drive. The Draft Environmental Impact Report (DEIR) did not analyze all portions of this hybrid route combination. In particular, the DEIR did not analyze the needed transition west of Trousdale Drive between the underground and overhead route segments. However, the Final Environmental Impact Report (FEIR) provided the complete environmental analysis needed to allow us to approve this hybrid route. The Commission found that the adopted hybrid route avoids Route 1B's adverse effects along Trousdale Drive and El Camino Real and is more consistent with community values and wishes.
We find that 280 Citizens made a significant contribution on routing issues by assisting in development of a full evidentiary record on PG&E's proposed project and potential alternative routes. While not its preferred route, the Underground to Trousdale Drive route, which 280 Citizens suggested early in the environmental review process, led to the hybrid route adopted in D.04-08-046. 280 Citizens, along with other intervenors, opposed Route 1B due to traffic impacts, residential hazards, and emergency response times during construction, and also due to on-going EMF exposures. 280 Citizens' evidence and advocacy assisted the Commission in its decision to reject the portion of Route 1B along Trousdale Drive and El Camino Real even though the FEIR had identified that route as environmentally superior. We note that portions of the PUA and MPUA would have followed Route 1A, including the part of Route 1A included in the hybrid route adopted in D.04-08-046. Thus, while 280 Citizens did not prevail on the portion of the route south of Trousdale Drive, the Commission adopted the portion of 280 Citizens' recommended PUA/MPUA route north of Trousdale Drive.
PG&E asserts that 280 Citizens' support of routes after they had been rejected from full analysis in the EIR process did not make a substantial contribution to D.04-08-046. PG&E argues that such routes could not be adopted lawfully and therefore were irrelevant. PG&E's concern appears to be aimed primarily at 280 Citizens' support of the MPUA and, in its comments on the proposed decision, a West of Skyline (Boulevard) alternative to a portion of the hybrid route recommended in the proposed decision. For reasons stated below, we agree with PG&E that 280 Citizens did not substantially contribute to D.04-08-046 regarding certain MPUA and West of Skyline issues.
In D.04-08-046, we rejected the southernmost portions of both the MPUA and the PUA because of visual and biological impacts. While the MPUA would have reduced EMF exposure along the portion that deviated from the PUA--a concern not taken into account in the FEIR's determination not to analyze that portion of the MPUA--we did not find in D.04-08-046 that this portion of the MPUA warranted the further environmental analysis necessary before we could approve it in compliance with California Environmental Quality Act (CEQA). We find that 280 Citizens' advocacy of the portion of the MPUA that differed from the PUA did not make a substantial contribution to D.04-08-046.
280 Citizens characterized its West of Skyline alternative as a variation of a route segment that the FEIR declined to analyze fully. While this alternative would reduce EMF exposure to residents along Skyline Boulevard, in D.04-08-046 we determined that it would increase EMF levels to other residences. We did not accept 280 Citizens' request that the West of Skyline route alternative receive a full environmental assessment. We find that 280 Citizens' late advocacy of this route segment did not make a substantial contribution to D.04-08-046.
PG&E argues additionally that 280 Citizens did not make a contribution in that it continued to oppose Route 1A after PG&E no longer endorsed that route. As 280 Citizens points out, PG&E supported Route 1A in its prepared testimony and never withdrew its request for that route, and the DEIR, FEIR, and D.04-08-046 all evaluated Route 1A. We find that 280 Citizens' on-going opposition to Route 1A contributed to our assessment of that route in D.04-08-046.
280 Citizens participated throughout the Commission's environmental review process, arguing that PG&E failed to consider alternatives that could avoid or mitigate potentially significant adverse environmental effects. As described in Section 5.1.1, 280 Citizens suggested several alternative routes for the southern portion of the project, including an underground/overhead route identical in essential respects to the hybrid southern route approved in D.04-08-046. 280 Citizens' participation during the environmental review process enhanced the development and assessment of route alternatives and assisted the Commission in ensuring full compliance with CEQA. We find that 280 Citizens made a significant contribution to D.04-08-046 regarding the environmental review.
PG&E asserted that the Jefferson-Martin project would be needed by late 2005 for reliability purposes. 280 Citizens maintained that the project would not be needed until after 2012.
In D.04-08-046, the Commission found that the Jefferson-Martin project would be needed for reliability purposes in 2007, although we approved construction of the project sooner than 2007 in order to capture diversification, economic, and environmental benefits. The Commission agreed with 280 Citizens that PG&E's March 2003 demand forecast should be used to assess the timing and need for the Jefferson-Martin project, contrary to PG&E's position that earlier, higher demand forecasts should also be considered. While supporting closure of the Hunters Point power plant as soon as technically possible, the Commission also agreed with 280 Citizens that Hunters Point could operate beyond 2005 if needed. We find that 280 Citizens made a substantial contribution to D.04-08-046 regarding the above issues.
280 Citizens asserted that PG&E's Supplementary Guide grid planning criteria should not be applied in evaluating the Jefferson-Martin project. While it does not appear that the California Independent System Operator (ISO) is required by statute to use the Supplementary Guide, in D.04-08-046 we did not find sufficient basis to deviate from the ISO's conclusion that these planning criteria should be used. We find that 280 Citizens did not make a substantial contribution to D.04-08-046 regarding the planning criteria.
The Commission rejected inclusion of planned City and County of San Francisco (CCSF) combustion turbines in the resource mix used in the need analysis, contrary to the position of 280 Citizens and Office of Ratepayer Advocates (ORA)4. We also rejected 280 Citizens' position that the need analysis should assume that certain existing transmission lines in the area would be re-rated. 280 Citizens did not convince us to deviate from prior policies as articulated in D.02-12-066 regarding the treatment of resources that have not completed the regulatory approval process (the CCSF turbines) or are not planned (the transmission line re-rates), and we find that 280 Citizens did not make a substantial contribution to D.04-08-046 on the resource mix criteria.
The Commission found that PG&E reflected the near-term development of conservation, energy efficiency, and distributed generation satisfactorily in its load forecasting methodology. 280 Citizens and WEM described policies and programs established in recent years to increase reliance on these sources, and took issue with PG&E's omission of any explicit effect of these initiatives from its load forecasts. 280 Citizens did not provide any evidence, however, that the near-term development of such resources is sufficiently certain to be relied upon for transmission planning purposes. We find that 280 Citizens did not make a substantial contribution to D.04-08-046 on this forecasting issue.
In summary, we find that 280 Citizens made a substantial contribution to D.04-08-046 on some, but not all, aspects of project need and timing.
280 Citizens' routing recommendations were based, in part, on its concerns regarding EMF exposure to residences along PG&E's proposed route. 280 Citizens submitted scientific studies that reported an association between EMFs and certain diseases, provided an independent evaluation of magnetic field levels along several route alternatives, and presented testimony from residents along the route. It asked the Commission to adopt a standard that transmission-related magnetic field exposure should not exceed one milliGauss at residential property boundaries, to be achieved through either routing changes or undergrounding of the line.
As described in Section 5.1.1, the Commission adopted only a portion of the project route 280 Citizens recommended. However, as it notes, we agreed with it that EMF exposure from the project would significantly exceed what residents are likely to receive daily and that the risk of EMF exposure should be taken into account in determining the route for the project. However, we declined to adopt the numerical EMF exposure standard that 280 Citizens proposed.
Overall, we find that 280 Citizens made a significant contribution to the Commission's consideration of public concerns regarding potential health and safety risks of EMF exposure. 280 Citizens was instrumental in developing the record regarding EMF risks, the need to consider EMF exposure levels in routing the project, and the need to modify PG&E's proposed EMF Management Plan for the Jefferson-Martin project. In addition, 280 Citizens' advocacy contributed to the recommendation in the proposed decision that we open a new rulemaking to consider modifications to our EMF policies. We acted on that recommendation with our initiation of R.04-08-020.
The Commission adopted a hybrid route for the southern portion of the Jefferson-Martin project "in express consideration of the community values" expressed by intervenors including 280 Citizens regarding "the perceived importance of avoiding construction impacts and EMF exposure in populated areas along this portion of the route" (D.04-08-046, mimeo. at 125). We find that 280 Citizens made a substantial contribution to the Commission's decision in this regard.
280 Citizens cross-examined PG&E's seismic experts and introduced several exhibits during cross-examination that provided information regarding the impact of recent large earthquakes on electric utility facilities and seismic design approaches PG&E has used in the past to address seismic issues. 280 Citizens argued in briefs that seismic issues should not preclude Commission consideration of a Glenview Drive transition tower or a Sneath Lane transition station alternative for connecting a southern overhead portion of the Jefferson-Martin project to the northern underground segment. This argument countered PG&E's initial assertion that seismic concerns would preclude a transition station other than at San Bruno Avenue, a location that faced strenuous opposition by the City of San Bruno. 280 Citizens also asserted that the existence of earthquake faults that cross Trousdale Drive would drastically increase construction costs of the Trousdale Drive segment of Route 1B.
The Commission approved the Glenview Drive transition tower alternative. While this location is closer than the San Bruno Avenue location to the active trace of the San Andreas fault, the FEIR concluded that the seismic risk can be mitigated to a less-than-significant level. We rejected the Trousdale Drive segment of Route 1B, due to seismic and other concerns.
PG&E asserts that 280 Citizens did not make a substantial contribution on seismic issues since it did not present any testimony or evidence supported by a qualified expert. However, we find that 280 Citizens' participation contributed to development of the record on seismic issues and assisted the Commission in assessing alternative transition station locations and route options. Thus, we find that 280 Citizens made a substantial contribution to D.04-08-046 in this regard.
280 Citizens submits that it made a substantial contribution to the Commission's determination regarding visual impacts associated with the proposed project, in particular that it demonstrated that the proposed project would cause significant unmitigable impacts on residents living on Lexington Avenue in the San Mateo Highlands and on Black Mountain Road in Hillsborough. The FEIR and the Commission agreed that the proposed project would cause significant unmitigable visual impacts at these points.
PG&E argues that, since the MPUA advocated by 280 Citizens would have created significant unmitigable visual impacts, 280 Citizens did not make a substantial contribution regarding visual impacts. In D.04-08-046, the Commission rejected the southernmost portion of the proposed project and the PUA, and implicitly the MPUA, due in part to their significant, unavoidable, and permanent visual impacts. While 280 Citizens' preferred route had its own significant visual impacts, 280 Citizens nevertheless made a substantial contribution to D.04-08-046 because it enhanced the record regarding the visual impacts of the proposed project, which led the Commission to choose another alternative, the underground Route 1B, along that portion of the route.
280 Citizens states that it made a significant contribution to the Commission's consideration of construction impacts through San Mateo Highlands and Hillsborough, and in particular along Skyline Boulevard and Trousdale Drive. While the FEIR found Route 1B environmentally superior, the Commission adopted a hybrid route, in part because it avoids construction impacts on residences and businesses along Trousdale Drive. This determination was based in part on the record developed by 280 Citizens and the City of Burlingame regarding construction impacts. We find that 280 Citizens made a significant contribution to D.04-08-046 in this regard because it helped develop a full record on this issue, and the Commission adopted its position in this respect.
280 Citizens submits that it made a substantial contribution to the Commission's consideration of project costs. PG&E and 280 Citizens were the only parties to provide cost estimates for the proposed Jefferson-Martin project and alternative routes. 280 Citizens states that its cost analyses forced PG&E to develop more fully the basis for its own cost estimates. 280 Citizens maintains that the record it helped develop will serve the Commission and PG&E's ratepayers if PG&E returns to the Commission in the future seeking an increase in the cost cap.
As part of its opposition to Route 1B, 280 Citizens asserts that PG&E underestimated Route 1B costs due to the presence of underground utilities along Trousdale Drive and El Camino Real and also seismic faults along Trousdale Drive. In D.04-08-046, we rejected that portion of Route 1B, in part because of the identified construction and seismic concerns. In Sections 5.1.6 and 5.1.8 of today's decision, we find that 280 Citizens made a substantial contribution to D.04-08-046 on construction and seismic issues related to Route 1B. The associated cost impacts were an integral part of 280 Citizens' showing in opposition to Route 1B. Because 280 Citizens prevailed regarding this portion of Route 1B, we find that 280 Citizens' cost analysis of Route 1B made a contribution to D.04-08-046.
280 Citizens asserted that, while underestimating Route 1B costs, PG&E overestimated costs of the PUA and the MPUA. 280 Citizens provided a cost estimate of the MPUA, the route that it preferred during the evidentiary hearings. The MPUA differed from the PUA only in that portions of the underground segments of the PUA would be moved as much as 25 feet to reduce impacts on bordering residences. 280 Citizens estimated construction costs for the MPUA using an "all-in per-mile" approach and argued that PG&E's cost estimates were "artificially detailed" because engineering had not been performed. The hybrid route we adopted contains the northernmost portion of the PUA/MPUA. However, our determination of the "maximum cost determined to be reasonable and prudent" pursuant to § 1005.5(a) was based on PG&E's detailed cost estimates for the hybrid route. We find that 280 Citizens did not make a substantial contribution to D.04-08-046 regarding the cost of the PUA/MPUA.
280 Citizens maintains that it made a substantial contribution to the Commission's consideration of the biological impacts of alternative routes. 280 Citizens presented a rebuttal witness to counter PG&E's assertions that undergrounding segments of the line through serpentine soil-based habitats, as proposed in the PUA and the MPUA, would create significant biological impacts. The expert witness testified regarding the condition of serpentine soil-based habitats along potential project routes, the decades-long absence of the Bay Checkerspot Butterfly from the area in which the PUA or the MPUA would be constructed, and steps that could be taken to mitigate trenching impacts and restore the quality of the habitat.
PG&E submits that 280 Citizens did not make a substantial contribution on biological impacts because during the hearings it continued to advocate the MPUA, which had been rejected from consideration in the FEIR due in part to its adverse impacts on biological resources, and also because 280 Citizens' witness admitted that Route 1B would have less impact on biological resources.
280 Citizens' rebuttal testimony regarding the biological impacts of undergrounding applied to both the PUA--a route alternative that was analyzed fully in the FEIR--and the MPUA, and supplemented the FEIR's analysis in this regard. We find that 280 Citizens made a substantial contribution in that it helped develop the record regarding biological impacts of route alternatives.
5.2. CARE
CARE presented testimony, cross-examined witnesses, and filed briefs and comments on the proposed decisions. As a representative of low-income residents of the Bayview Hunters Point neighborhood, CARE states that it was uniquely positioned "to advocate primarily for the most expedient alternatives that avoid processing or potential construction delay, while at the same time choosing the environmentally superior option when the options were essentially equal with regard to delay."
CARE presented evidence concerning the current environmental impact of the Hunters Point and Potrero power plants and argued that the plants should be closed as soon as possible. CARE also submitted evidence and argument concerning potential delays and environmental impacts associated with certain route alternatives.
CARE's position aligned closely with that of PG&E and the ISO, i.e., that the Jefferson-Martin project should be built on the schedule proposed by PG&E and the ISO and along the route proposed by PG&E. However, CARE provided a unique perspective and supplemented the record regarding impacts of the Hunters Point units in the Bayview Hunters Point neighborhood and the interests of that community in closure of those units. In determining that the Jefferson-Martin project should be built at the earliest possible time, before it is needed for reliability purposes, the Commission gave "great weight to the community values of the Hunters Point and Bayview neighbors" (D.04-08-046, mimeo. at 125). For these reasons, we find that CARE provided a substantial contribution to D.04-08-046. Like 280 Citizens, CARE also made a substantial contribution because it helped develop the evidentiary record regarding potential biological impacts of route alternatives under consideration.
On March 3 and April 26, 2004, CARE submitted motions in which it requested that the record be reopened regarding the impacts of trenching on biological resources in serpentine grasslands. In its motions, CARE described a site visit undertaken on February 28, 20045 and requested an opportunity to present additional evidence based on that site visit. The ALJ denied CARE's request and in D.04-08-046 we affirmed the ALJ's ruling in that regard. CARE's February 2004 site visit and its subsequent motions did not make a substantial contribution to D.04-08-046, and CARE should not receive compensation for its efforts in this regard.
5.3. WEM
WEM presented testimony, cross-examined witnesses, and filed briefs. To further its stated goal of closing the Hunters Point power plant, WEM advocated that current transmission constraints south of the San Mateo substation and within San Francisco's 115 kV cable system could reduce or even eliminate the Jefferson-Martin project's ability to increase the load serving capability of the transmission system in the area. WEM entered as evidence several documents that, it asserted, raised questions regarding PG&E's and the ISO's portrayal of the capabilities of the existing transmission system and the date Hunters Point could be closed. It also cross-examined several witnesses regarding the load serving capability of the transmission system and the extent to which the Jefferson-Martin line would change the amount of power available to San Francisco. WEM addressed energy efficiency as an alternative for providing reliability in the affected area. WEM also questioned PG&E witnesses about a "potential conflict of interest in the preparation of cost estimates by a no-bid consultant that is also a potential bidder on the construction itself."
WEM maintains that its participation resulted in a more in-depth investigation that led to the Commission being satisfied that PG&E and the ISO are remedying the transmission constraints WEM highlighted. WEM concludes that its participation helped the Commission become better prepared to monitor progress toward closure of Hunters Point and to track the costs and benefits of the Jefferson-Martin project.
PG&E opposes WEM's compensation request, arguing that WEM did not make a substantial contribution to D.04-08-046 in any respect. PG&E asserts that WEM's prepared testimony provided no factual information, that WEM undertook inefficient, lengthy, and worthless cross-examination of witnesses, and that WEM's briefs misstated the evidentiary record.
PG&E argues that WEM misinterpreted PG&E and ISO reports, and that WEM erred in asserting that construction of the Jefferson-Martin project could impede, rather than assist, closure of the Hunters Point plant, since all of the other needed transmission upgrades already were contained in PG&E's 2003 transmission expansion plan. PG&E also maintains that WEM presented no evidence that conservation and renewable energy could be available in lieu of the Jefferson-Martin project, noting that, to the contrary, the FEIR and the Commission expressly found that these sources would not be sufficient to ensure reliable electric service in the affected area.
We find that WEM's scrutiny forced PG&E and the ISO to address more thoroughly the impact of Jefferson-Martin on the load serving capability of the transmission system. As an example, WEM cross-examined regarding PG&E's statement that the Jefferson-Martin project would add up to 351 megawatts (MW) of load serving capability to the San Mateo-Martin corridor compared to the ISO's testimony that the project would increase the transmission system's load serving capability by 230 MW. WEM's participation elicited that the 351 MW increase relied upon by PG&E assumed no transmission limitations either south of the San Mateo substation or north of the Martin substation. By contrast, as established by WEM cross-examination of an ISO witness (D.04-08-046, mimeo. at 37, ftn.18), the ISO recognized that transmission constraints exist in both areas and assumed that those constraints will be alleviated somewhat (but not completely) by other projects in PG&E's transmission expansion plan. We find that WEM's participation assisted the Commission in evaluating need for the Jefferson-Martin project and thus contributed substantially to the Commission's decision. However, as discussed in Section 6.3, WEM's compensation is reduced because of the inefficiency of its participation.
We find that WEM did not make a substantial contribution with respect to the treatment of energy efficiency and renewable energy in assessing need for the proposed project. As noted above, D.04-08-046 found that PG&E reflected these sources satisfactorily in its load forecasting methodology. We also find that WEM did not make a substantial contribution regarding costs. D.04-08-046 did not address WEM's vague assertions regarding potential conflicts of interest in PG&E's preparation of cost estimates.
On March 3, 2004, WEM submitted a motion to reopen the record "on the basis that the Commission should consider information regarding (1) a proposed merchant transmission line across San Francisco Bay, (2) ISO power flow studies which WEM asserts demonstrate that the Jefferson-Martin project may reduce load serving capability in the San Francisco area, and (3) the possibility of imminent global climate collapse due to failure of the `Ocean Conveyer' which drives ocean currents." The ALJ denied WEM's motion, and we affirmed that ruling in D.04-08-046. WEM's efforts related to this motion did not make a substantial contribution to D.04-08-046 and should not be compensated.
2 D.98-04-059, 79 CPUC2d 628 at 653.
3 See D.03-12-019, discussing D.89-03-063 (31 CPUC2d 402) (awarding San Luis Obispo Mothers for Peace and Rochelle Becker compensation in the Diablo Canyon Rate Case because their arguments, although ultimately unsuccessful, forced the utility to thoroughly document the safety issues involved.
4 The Commission's Office of Ratepayer Advocates is now the Division of Ratepayer Advocates (DRA). The change was effective January 1, 2006, pursuant to Senate Bill 608.
5 According to time records submitted with CARE's compensation request, the site visit may have occurred on February 26, 2004.