Word Document PDF Document

ENERGY/KPC/KOK/DLW/AML

Decision 06-05-029 May 25, 2006

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Application of SAN DIEGO GAS & ELECTRIC COMPANY (U-902-M) for Authority to Increase its Short-Term Borrowing Authorization to an Aggregate Amount not to Exceed $550,000,000 in Addition to that Amount Otherwise Authorized by Public Utilities Code Section 823(c).

Application 05-12-026

(Filed December 22, 2005)

OPINION

1. Summary

This decision grants San Diego Gas & Electric Company (SDG&E) the authority requested in Application (A.) 05-12-026 (Application).

Pursuant to §§ 816 through 830, SDG&E requests authority through December 31, 2010, to increase its current short-term borrowing authority of $400,000,000, granted by Decision (D.) 05-05-047, dated May 26, 2005, to an aggregate principal amount not to exceed $550,000,000. This $550,000,000 of requested short-term borrowing authorization is in addition to the 5 percent issuance of short-term debt that does not require Commission approval pursuant to § 823(c).1

2. Background

SDG&E is an electric and gas corporation organized and existing under the laws of the State of California, and is primarily engaged in the business of providing utility electric and gas service throughout San Diego County and public utility service in a portion of Orange County. SDG&E's current short-term financing request builds on financing authorizations issued beginning in 1992.

3. Notice and Protests

4. SDG&E's Application

SDG&E states, in its Application, that it continues to face a dynamic external and regulatory environment. As such, SDG&E believes it is prudent and necessary to increase its excess existing short-term borrowing authorization now in order to address in the future, and when needed: (1) higher planned infrastructure investments; (2) the impact of increased gas prices (and related Commission regulatory actions); and (3) the timing and size of potential collateral calls up to the proposed ceiling in its hedging program, as requested in SDG&E's Advice Letter 1745-E, filed November 16, 2005, as supplemented by AL 1745-E-A filed on March 22, 2006.

SDG&E's seeks authorization to increase its short-term borrowing authorization to an aggregate amount not to exceed $550,000,000 from the current $400,000,000, in addition to that amount otherwise authorized by

§ 823(c).

Notwithstanding the provisions of subdivision (b), no public utility as defined in Sections 201(e) of the Federal Power Act (49 Stat. 847, 16 U.S.C. 824) shall, without the consent of the commission, issue notes payable at periods of not more than 12 months after the date of issuance of the notes if such notes and all other notes payable at periods of not more than 12 months after the date of issuance of such notes on which such public utility is primarily or secondarily liable would exceed in aggregate amount 5 percent of the par value of the other securities then outstanding. In the case of securities having no par value, the par value for the purposes of this subsection shall be the fair market value as of the date of issue.

SDG&E points out that it intends to also use its short-term debt borrowing authorization for basically the same purposes as those indicated in D.05-05-047: (i) temporary financing for new utility infrastructure; (ii) balancing account undercollections; (iii) fuel inventories; (iv) temporary financing for the retirement and refunding of long-term debt and preferred stock; and (v) other short-term cash needs that may arise from time to time.

SDG&E's indicates that its capital plans, which are in response to its ongoing commitment to enhancing the energy infrastructure of California, have increased substantially. SDG&E points out that, investments are being made in new generation and transmission that are urgently needed as energy needs continue to increase. One of SDG&E's new infrastructure capital investments is the Sunrise Powerlink 500kV transmission line, an "energy superhighway", which will ramp up over 2006-2008, to improve the reliability of the region's electrical transmission grid and provide access to available and proposed electricity supplies from the region and beyond. SDG&E anticipates investing between $2.6 billion and $3.2 billion over the next three years, compared to its historical spending pattern of $350-$500 million per year. SDG&E points out that the temporary financing of these improvements with short-term debt will put additional demands on its short-term borrowing capacity.

SDG&E claims that it and its customers are experiencing the impact of dramatic increases in the price of natural gas. SDG&E points out that combined with SDG&E's re-entry into the electric generation business, which will also necessitate purchases of natural gas, its potential short-term financing needs for gas purchasing will be increasing.

SDG&E claims that approval of its increased short-term borrowing capacity is also a necessary element for the implementation of its updated electric procurement plan. Currently before the Commission is SDG&E's Advice Letter 1745-E, filed November 16, 2005, which updates its electric procurement plan in response to long-term electric procurement authority.3

In 2005, the Commission issued D.05-10-015, D.05-10-043 and D.05-10-044, taking several steps to mitigate the impact of high gas prices on California consumers. Among other things, these decisions increased the gas utilities hedging programs, expanded eligibility for energy low-income programs, prohibited utilities from shutting off winter residential customers who make minimum payments, and required a waiver of reconnection fees and deposits for certain qualified energy low-income customers. SDG&E believes that these steps will also increase its potential short-term financing needs.

5. Discussion

During times when market conditions make long-term financing unattractive, it may be necessary for a utility to issue short-term debt to finance its construction expenditures and cash requirements. Debt maturities, opportunities to redeem or repurchase securities at low cost, changes in cash flows, or other unexpected events may make it necessary or desirable to increase short-term borrowing temporarily to meet cash needs. However, short-term borrowing should be reduced when practicable.

Schedule VIII, attached to the Application, shows that, as of September 30, 2005, SDG&E had $1,608,926,000 of total capitalization, which is used to calculate the 5% § 823 allowance.

Short-Term Financing in Excess of CPUC Code § 823 Allowance

($ thousands)

September 30, 2005

Common Stock issued 371,076

Preferred and preference stock 97,225

Long-Term debt (excluding capital leases) 1,140,625

Total capitalization at September 30, 2005 1,608,926

5% allowed by CPUC Code §823 (c) 80,446

Maximum anticipated amount of short-term debt needed 630,446

Total excess financing authority requested in this

Application 550,000

Current Excess financing authority granted under

D.05-05-047 400,000

Additional financing authority requested in this

Application 150,000

SDG&E's authorized $400,000,000 excess short-term debt ceiling, in D.05-05-047, amounted to 29.38% of the utility's total capitalization of $1,361,426,000, as of September 30, 2004.4 The requested $550,000,000 excess short-term debt ceiling amounts to 34.18% of total current capitalization (an increase of only 4.8% from the 2004 percentage of capitalization, exclusive of the § 823 (c) allowance),5 while the capitalization during the same period increased by 18.18%.6

a. Balance Sheet

For the nine months ended September 30, 2005, SDG&E reported total operating revenue of $1,706,676,360 and net income of $194,243,575, as shown in its Statement of Income and Retained Earnings, included in Attachment B to the Application. SDG&E's balance sheet, shown also as part of Attachment B, as of September 30, 2005, is summarized as follows:

Net Utility Plant $3,475

Other Property and Investments 647

Current and Accrued Assets 552

Deferred Debits 1,981

SDG&E's forecasted estimated average capital expenditures, as shown in Schedule I in Attachment D to the Application, for calendar years 2006 through 2008, are as follows:

Components 2006 2007 2008 Total

Gas T&D, Elect Dist. And Generation $ 800 $ 450 $ 500 $1,750

Electric Transmission 300 225 500 1,025

Common/Other 50 50 50 150

Total cash required for construction $1,150 $ 725 $1,050 $2,925

c. Cash Requirements Forecast

SDG&E's Statement of Cash Requirements for 2006 through 2008 is as follows:

Uses of Cash 2006 2007 2008 Total

Funds for Construction

(Capital Expenditures) $1,150 $725 $1,050 $2,925

Maturities/Refinancings:

Maturities of Long-term Debt 66 66 - 132

Beginning of year cash

(short-term debt) balance (220) (5) (15) (240)

Subtotal $996 $786 $1,035 $2,817

Less: Estimated Cash Available

from Internal Sources (450) (550) (650) (1,650)

External funds required $546 $236 $385 $1,167

SDG&E's Statement of Cash Requirements for the three years, represented above, indicates that it will require additional funds from external sources amounting to approximately $1.2 billion. Subsequent to filing instant application 05-12-016, SDG&E filed application 06-02-017, in which it requested authority to issue $800 million of long term debt and $200 million of preferred and preference stock. We granted this authority on May 11, 2006 in decision 06-05-015. It appears from this forecast that SDG&E may need the addition to its current excess short-term borrowing authority to meet its external funding requirements. While the project expenditures are proper uses of funds, pursuant to § 817(b) and (g), the reasonableness of construction expenditures and refinancing costs are issues normally addressed in other proceedings and we will not address them here.

SDG&E's capital ratios as of September 30, 2005, are shown below as actual and pro-forma, showing the effect of increase in short-term borrowing:

Long-Term Debt $1,140,625 43.3 $1,140,625 35.0

Less: Unamortized expenses (19,233) (0.7) (19,233) (0.6)

Total Long-Term Debt $1,121,392 42.6 $1,121,392 34.4

Short-Term borrowing

Under PUC code §823(c) - 0.0 80,446 2.5

Short-Term Debt - 0.0 550,000 16.8

Total Debt $1,121,392 42.6 $1,751,838 53.7

Preferred Stock $ 97,225 3.7 $ 97,225 3.0

Common Equity9 1,412,615 53.7 1,412,615 43.3

Total $2,631,232 100.0 $3,261,678 100.0

6. Use of Proceeds

7. Approval of Short Term Borrowing

It appears that SDG&E's financing and short-term capital needs will increase due to, among other things, the temporary financing of capital improvements, higher gas prices, certain measures the Commission has taken to mitigate the impact on customers of higher gas prices (such as the Commission order to not shut-off service to gas customers this winter who make certain minimum bill payments), and to hedge gas costs for electric generation.

We conclude that it is in the public interest to grant SDG&E's uncontested request for authority to issue up to $550 million of excess short-term debt, in addition to the $80,446,000 in short-term debt that SDG&E may issue without Commission authorization, pursuant to

§823 (c). The health, safety, welfare, and prosperity of California depend on SDG&E having sufficient generation and transmission capacity to meet the needs of its customers.

SDG&E shall not use the short term debt authorized by this Decision to fund dividends, inter-corporate borrowing, or management fees paid to its parent company or other affiliates. Consistent with § 824, SDG&E shall maintain records to (1) identify the specific short-term debt issued pursuant to today's Decision, and (2) demonstrate that the proceeds from such debt have been used only for the purposes authorized by today's Decision.10

8. Category and Need for Hearings

In Resolution ALJ 176-3165, dated January 12, 2006, the Commission preliminarily categorized this proceeding as ratesetting and preliminarily determined that an evidentiary hearing would not be necessary. Based on the record of this proceeding, we affirm that this is a ratesetting proceeding and that a hearing is not necessary.

1 All statutory references are to the Public Utilities Code unless otherwise indicated.

2 This authority was in addition to the short-term debt that SDG&E may issue without Commission authorization pursuant to § 823(c).

3 SDG&E asserts that it may require a significant amount of short-term capital to fund the collateral requirements associated with its hedging program.

4 29.38% = $400,000,000/$1,361,426,000, and excludes $68 million of short-term debt pursuant to § 823(c).

5 34.18% = $500,000,000/$1,608,926,000, and excludes $80 million of short-term debt pursuant to § 823(c), based on the 2005 § 823 capitalization.

6 18.18% = $1,608,926,000-$1,361,426,000/$1,361,426,000

7 Amount includes Advances from Associated Companies.

8 Does not include any short term debt, pursuant to D.05-05-047.

9 Includes paid in capital, retained earnings and other comprehensive income.

10 Section 824 states: "The commission may require...utilities to account for the disposition of the proceeds of all sales of...bonds, notes, or other evidence of indebtedness, in such form and detail as it deems available, and may establish such rules as it deems reasonable and necessary to insure the disposition of such proceeds for the purposes specified in its order."

Top Of PageNext PageGo To First Page