I. Measuring Infrastructure Adequacy for
Natural Gas Utilities

"A more reasonable suggestion [for determination of the need of receipt point expansion] would be to monitor the utilization of SoCalGas receipt points. Then ... consider expanding only those where shippers consistently seek access above the available capacity, despite an overall system wide excess reserve margin, if the receipt point can be expanded at a reasonable cost. If the Commission should find that the benefits of expansion outweigh the cost, the utility should expand the point's capacity. Alternatively, if the Commission does not find that the benefits outweigh the costs, shippers should be given the opportunity to fund the receipt point expansion. If shippers are willing to make such a commitment, the utility would undertake the construction."22

"The mere fact that a particular receipt point may be constrained on occasion, or even over a fairly extended period, does not necessarily mean that an expansion is economically justified. As has often been observed in the context of electric resource planning, a certain level of congestion on the transmission system may in fact be economic, and new construction to relieve the constraint may not be cost-effective. This is especially true in an environment where the costs of different gas supply sources vary relative to each other over time. Just because the gas delivered at a particular receipt point is cheaper than other sources today does not necessarily mean that this condition will persist for a long enough period to justify the cost of system expansion."29

"Over the next several years, SoCalGas' existing storage facilities have sufficient capacity to meet customer needs. This can be demonstrated by (1) the fact that bundled core and balancing storage requirements can be accommodated with current storage facilities without significantly diminishing the size of the unbundled storage program, (2) the lack of long-term contracts for unbundled storage, (3) the modest level of market prices for short-term sales of SoCalGas' unbundled storage, and (4) the fact that there are many competitive alternatives to SoCalGas' unbundled storage service that can provide customers the same values as SoCalGas storage."36

"SCE appears to believe that the [electric generation] forecast should take into account every potential occurrence that might affect demand. This approach to ensuring system reliability and meeting customer demand is ill-advised, however. Planning backbone transmission facilities to meet all extreme conditions that might occur would result in a needless build-up of capacity and unnecessarily high rates."37

"SoCalGas characterizes its unbundled storage revenues as $47.4 million of which it shares 50 percent or $23.7 with ratepayers. Watson Direct at Table 8. A copy of SoCalGas' Response to SCGC DR 4.20 has been attached to this testimony as Attachment C, which shows the annual revenues for SoCalGas' unbundled storage program from 2000 to 2004. SoCalGas only bears 50 percent of the risk of the $21 million dollars allocated to the unbundled storage program, or a total of $10.5 million. Therefore, SoCalGas is making a return of $23.7 million while risking only $10.5 million. This amounts to a return of 226 percent on top of the return that SoCalGas otherwise earns on its storage facilities in rate base. This sort of return doesn't seem very modest at all." (Exhibit 50, p. 5.)

"Of the $26.4 million of `excess returns' in 2003, half were refunded to ratepayers through the Noncore Storage Balancing Account. Therefore, in 2003 SoCalGas shareholders earned $13.2 million over and above a $21 million allocated cost, or a 63 percent above-normal pre-tax return." (Exhibit 12, p. 4.)

"For non-constrained local transmission service areas, all noncore customers would be able to obtain firm transportation service by simply executing the standard two-year transportation agreement. For purposes of establishing the monthly contract quantity (MCQ), the following conditions would apply:

"MCQs shall be derived from historical daily consumption data based on the most recent 24 months for which data is available. The MCQ may not exceed the highest recorded peak day usage for a particular month times the number of operating days.

"Alternatively, customers may provide a forecast of consumption as the basis for their MCQ, provided those quantities do not exceed recorded historical usage.

"Customers may request higher MCQs by submitting a letter attesting to changes in their operation or equipment warranting adjustments to historical peak day usage (i.e., pursuant to condition 1) and the schedule timing for these changes. A load survey will be required documenting the increase as a result of adding new equipment or increasing load.

"Speculative or unsubstantiated requests for MCQ amounts will not be permitted.

"SoCalGas believes that these existing mechanisms are workable in areas where there does not appear to be any potential constraint based on historical load and customer projections of future load."41

"SoCalGas and SDG&E are prepared to expand transmission facilities as needed to serve core needs and firm commitments of noncore customers. Due to the wide geographic distribution of our system, and the nature of customer loads, local areas of the system can become constrained where demand for firm capacity can exceed the available firm capacity. Although there is a limit on the firm capacity in these areas, so far the available capacity has been sufficient to meet customer requests in the most recent open seasons except for some minor prorations in the Imperial Valley."42

18. Where there is a potential for constraint in the local transmission system, EG Tier 1 and G-30 customers demanding less than 20 MMcf/day that want to ensure delivery must commit to a 5-year use-or-pay arrangement for a specified capacity.

19. Faced with a similar potential constraint, customers in these classes with larger demand must commit to a 10-year firm daily capacity user-or-pay arrangement.

20. If such contractual commitments do not exceed firm local transmission capacity, the utilities will not expand the local transmission system.

21. Any resulting new investments would be treated as common transmission facility costs and included in general ratebase.

"[O]pen seasons that require customers to make binding commitments for firm service are superior to the utility relying solely on its internal demand forecasting. Since the bids require that the customer commit to a use-or-pay (UOP) provision, the bidding process provides better assurance that customers will bid the amount of firm service they really need. Although the demand forecast sponsored by Mr. Emmrich represents the utilities' best estimate of demand, his testimony notes a number of factors that could alter actual usage. Also, the forecast is a single point estimate of total demand, unlike requests for firm service. Moreover, customers and potential customers frequently express an interest in taking additional gas service at various locations in our service area. If we built out our local transmission system based on those expressions of interest, it would likely entail significant investments for facilities that might not actually be needed, raising all customers' rates unnecessarily. We believe basing expansion decisions on customer commitments is a more cost-effective method to ensure that expansions of the local transmission system meet customer requirements."55 (Emphasis added.)

"We authorize SDG&E to limit firm service to noncore customers to the firm capacity available, but, as discussed, we have also authorized a reliability standard of 1-in-10. This reliability standard, along with the service interruption credits, will serve as sufficient incentive to SDG&E to continue making investments in its system to meet the needs of its firm noncore customers and to avoid curtailments." (D.02-11-073 at 14.)

"SoCalGas can plan the timing and location of capacity additions through a combination of various mechanisms including a thorough analysis of the subscriptions to its open season, adherence to a system planning criteria of 1 in 10 for noncore customers and 1 in 35 for core customers for location [sic] transmission, and nonbonding [sic] expressions of interest in long-term agreements in the event customer commitments exceed available capacity in any of the 24 months of the open season." (D.02-11-073 at 37-38.)

II. Measuring Gas Infrastructure Adequacy
for Electric Utilities

... in order to more fully understand the adequacy of the California natural gas infrastructure and the impacts of current procurement practices, we have asked the Energy Division to examine electric utility plans to supply, transport and store natural gas for electric generation in those plants for which the utility is responsible to provide the gas. The Energy Division will then issue a report including any recommended actions for the Commission to take. The target date for release of the report is September 15, 2005. Comments on the report will be due October 17, 2005. The comments should address the merits of the Energy Division recommendations, and specifically identify any factual disputes related to the report that would suggest the need for evidentiary hearings prior to including the report in the record for this proceeding.

1) secure firm transportation contracts for baseloaded electric generation gas supplies:

    The electric utilities should consider assuring delivery of commodities purchased at the production basin by securing firm interstate capacity rights for the baseloaded utility-owned electric generation plants and for baseloaded plants under contract with DWR. Firm interstate pipeline capacity rights will ensure the reliable delivery of those supplies. Without such contracts, deliveries to California cannot be assured, even if the physical pipeline capacity to California exists.

    2) promote gas and electric end-use efficiency and conservation:

    These investments will have significant impacts on electricity and gas consumption. In addition to ensuring diverse access to supplies, including new supplies, California needs to take, and is taking, measures to limit natural gas demand.

    3) promote efficient electricity generation from gas:

    Since 2000, many old plants have been replaced with efficient new generators, resulting in a significant savings in gas use. This improvement is largely the result of plant owners seeking to become more cost competitive and has occurred without any mandates from governmental authorities.

    4) promote generation of electricity from non-gas resources:

    The Commission has adopted the Renewable Portfolio Standard, which will ensure that no later than 2017 at least 20% of California's electricity will be generated by non-gas resources. The Public Utilities Commission and the California Energy Commission have also adopted Energy Action Plan II, which envisions a 33% renewable portfolio by 2020.

    5) continue to allow for and encourage hedging, storing, and long-term commodity procurement, where effective or necessary:

    These tools are currently in use by the electric utilities procuring gas for generation. The utilities should be encouraged to use these tools prudently, guided by the Customer Risk Tolerance and market signals to reduce costs. Natural gas volatility could give rise to higher seasonal spreads in prices, making storage more valuable as a means by which to manage natural gas costs. Of course, if storage is seen as more valuable, the price of storage may increase as well.

    6) consider introducing an incentive mechanism for Electric Generation gas procurement:

    The cost-minimizing advantages of Performance Based Ratemaking need to be weighed against their disadvantages, including the tendency to encourage all short-term market purchases and to discourage certain kinds of hedging activity. Prior to going down this road, these pros and cons should be evaluated, and ways of avoiding typical pitfalls should be envisioned.

    7) provide access to new supplies, including LNG supplies:

    In D.04-09-022 the Commission recognized that LNG could be an important future component of California's gas resource base. Indeed, one of the thrusts of R.04-01-025 is to facilitate access to this resource on an equitable and safe basis. The creation of open access tariffs and standardized agreements and the development of new gas quality standards are two aspects of this effort to facilitate importation of LNG and access to new supplies.

    8) monitor the potential for intrastate and interstate pipeline congestion:

    One of the recommendations of D.04-09-022 was to establish an advisory committee comprised of natural gas utilities state agency officials, and other parties who would monitor the interstate pipeline capacity situation to ensure sufficiency. This recommendation is being implemented. The first meeting of natural gas utilities and state agencies has already taken place, and an expanded meeting of this group with other interested parties will be scheduled shortly.

III. Creating an Infrastructure Working Group

· Monitor natural gas market prices important to California consumers,

· Identify emerging issues that could potentially affect the above,

· Ensure that Working Group members have a common information set on these issues,

· Seek additional viewpoints and information that could benefit Working Group participants and California consumers,

· Establish a reporting system that provides timely alerts on near term issues, as needed, and

· Establish working relationships that encourage an open and informal exchange of information and discussion between the participants.

· Establish a California Natural Gas Infrastructure Stakeholders Working Group (NGWG+),

· Membership of the NGWG+ would be self-selected and composed of all stakeholders interested in California's natural gas supply and infrastructure,

· conduct informal discussion only and issue no summary report,

· determine additional structure for the working group after its initial meeting.

· California State Agencies

· California Air Resources Board

· California Energy Commission

· California Public Utilities Commission

· California State Lands Commission

· Department of Conservation, Division of Oil, Gas, and Geothermal Resources

· Department of General Services, Natural Gas Services Program

· Department of Water Resources, California Energy Resources Scheduling

· Office of Planning and Research

· Maintain the current monthly Natural Gas Working Group (NGWG) meetings ,

· Invite the California natural gas investor-owned utilities to attend the NGWG meetings on a quarterly basis,

· Hold these quarterly meetings in a month preceding each season in time to take last-minute action if needed to avert potential problems (e.g., April, July, October, and January),

· Keep the meetings informal and off-the-record,

· Use these meetings to explore possible problems with California's natural gas infrastructure and operations and potential solutions that benefit consumers,

· Establish a sunset date of July 2007, extendable as determined by the group, to consider the need to continue these meetings.

· The CEC offers to organize these new working groups and initially chair them, with the formal chair to be selected by each group on a permanent or rotating basis.

IV. Paying for and Gaining Access to New Facilities

"Adoption of Woodside's proposal could fundamentally undermine years of planning and investment in selecting the transportation routes, facilities and systems needed to move gas to market. In the case of the Energia Costa Azul facility in Baja, for example, some significant decisions have been made - and others must be made in the very near future - about how much gas to move via the Otay Mesa receipt point to the Southern California market versus how much gas to take east and north through the Bajanorte and North Baja pipelines. These decisions involve the design, permitting and construction of new transmission facilities in Mexico and the United States and necessarily have long lead times. Gas from the Energia Costa Azul facility is on schedule to begin to flow on or about January 1, 2008. If other projects in Baja come on line at a later time (whether one or two or three or more years later) and the Commission were to shift the costs of the upgrades needed to permit gas to flow into Otay Mesa from those projects to the original sponsors of the expansion, this would fundamentally alter the economics of the original sponsors' business investments."63

V. Interconnection and Operational Balancing Agreements

VI. Independent Storage Provider Direct Interconnection With California Producers, As Well As Electric Generators and Other Noncore Customers

"Should independent gas storage facilities be permitted to connect directly with other market participants such as California producers, electric generators, or other noncore customers, which Public Utilities Code sections are relevant to this issue, and should the Commission be concerned with bypass?

"Should the Commission determine in this proceeding whether the gas utilities' backbone transmission capacity is sufficient to accept maximum withdrawals from all gas storage facilities during peak periods...?"

VII. Gas Quality

VIII. NGC+ Report

IX. Discussion

X. Requirements of CEQA

1 Of the SoCalGas total backbone receipt capacity, 20-25% of that capacity would be unused during an average temperature year and under normal hydroelectric conditions. PG&E proposes that, under cold and dry conditions, demand would amount to 80-90% of the available firm backbone capacity on average. This is equivalent to saying 11-25% of the available backbone transmission capacity would be unused.

2 During the courses of the proceeding, after filing briefs on infrastructure adequacy, the Office of Ratepayer Advocates changed its name to the Division of Ratepayer Advocates.

3 Order Instituting Investigation Into the Adequacy of the SoCalGas and SDG&E Gas Transmission Systems to Serve the Present and Future Gas Requirements of SDG&E's Core and Noncore Customers

4 "MMcf/day" refers to "million cubic feet per day."

5 / SDG&E/SoCalGas/Hartman, Exh. 10, pp. 1-2 (emphasis added).

6 / SDG&E/SoCalGas OB, pp. 57-60.

7 / SCE/Pando, Tr. Vol. 4, p. 547.

8 / TURN/Florio, Exh. 43, p. 3 (emphasis in original).

9 / SCE suggests that the strain placed on the SDG&E/SoCalGas system during the 2000-2001 energy crisis is proof of the need to expand the transmission system in order to ensure that it is capable of handling extreme intra-year conditions. (SCE OB, pp. 8-9). In fact, the energy crisis highlights the folly of relying exclusively on flowing supply and makes clear that sensible reliability planning by noncore customers involves ensuring that adequate reserve supplies are held in storage. SCE witness Pando, in fact, admits that lack of storage withdrawals during the energy crisis harmed noncore customers. (SCE/Pando, Tr. Vol. 4, p. 535).

10 / SDG&E/SoCalGas/Hartman, Exh. 10, p. 3.

11 / The SDG&E gas transmission system is currently classified as a local transmission system in relation to the SoCalGas system, but functions as a backbone transmission system from the perspective of SDG&E. (SDG&E/SoCalGas/Bisi, Exh. 7, pp. 5-6).

12 / The term "slack capacity" was formerly used to describe the backbone capacity in excess of demand on the system. In order to achieve consistency with methodology and terminology used by PG&E, the term "reserve margin" is used herein.

13 / SDG&E/SoCalGas/Hartman, Exh. 8, p. 3 (internal references omitted).

14 / SDG&E/SoCalGas/Hartman, Exh. 8, p. 4.

15 / Id. at p. 5 (internal references omitted).

16 For physical and economic reasons, not all of the gas in a storage reservoir can be withdrawn at any given time. A storage operator must determine its reliable withdrawal capacity and assign rights for individual customers to withdraw gas at any given time. These rights are referred to as withdrawal rights.

17 It is common for all three utilities to assume more severe service conditions when examining the adequacy of core resources.

18 TURN also argues that if the system planning criteria are to take into account dry hydro conditions, then cost allocation to electric generation customers should be based on forecasted demand under the same dry hydro conditions that are used in system planning. While we note this concern, the issue is not before us in this proceeding.

19 Data submitted on February 24, 2004 in response to CPUC data request. See Question 1.

20 For SoCalGas and SDG&E, this is one event in 35 years for core customers and one event in ten years for firm noncore customers. For PG&E, the standard is one event in 90 years for core customers and one event in three years for the noncore.

21 Exh. 10 (SoCalGas -Hartman), p. 2, lines 8-11.

22 Id., p. 4, lines 14-22.

23 Tr. Vol. 3 (SoCalGas-Bisi), p. 279, line 27 to page 280, line 7. In a motion dated December 1, 2005, after the submission of reply briefs on this issue, SoCalGas offered updated cost data regarding some potential receipt point expansions. The motion is untimely and opposed. In addition, we do not need specific cost information for the purposes of this decision. For these reasons, the motion is denied.

24 Tr. Vol. 2 (SoCalGas-Bisi), p. 235, lines 27-28.

25 Tr. Vol. 3 (SoCalGas-Bisi) p. 282, line 22 to p. 283, line 2.

26 See discussion, Vol. 3, page 304, line 25 to page 305, line 13.

27 See SDG&E/SoCalGas Opening Brief, pp. 12-13.

28 SDG&E/SoCalGas/Hartman, Exh. 8, p. 9.

29 TURN/Florio, Exh. 43, pp. 1-2.

30 SDG&E/SoCalGas/Hartman, Tr. Vol. 1, pp. 61-65.

31 SDG&E/SoCalGas/Hartman, Exh. 8, p. 9.

32 PG&E Opening Brief, p. 7.

33 D.04-09-022, p. 68.

34 As part of a settlement between PG&E independent storage providers, to be discussed later, those parties stipulated that PG&E's backbone capacity is sufficient to deliver withdrawn gas during peak periods.

35 Injection and withdrawal capacity depends on physical inventory.

36 SDG&E/SoCalGas/Watson, Exh. 11, p. 1.

37 Reply Brief of SDG&E and SoCalGas, p. 27.

38 Tr. 82.

39 D.97-11-070, at p. 12.

40 D.02-11-073, supra note 13 at *46, Conclusions of Law Nos. 1 and 10 at *68-70; SDG&E/SoCalGas/Bisi, Exh. 7, pp. 13-14.

41 SDG&E/SoCalGas/Hartman, Exh. 8, p. 11.

42 SDG&E/SoCalGas/Morrow, Exh. 4, pp. 7-8.

43 During the most recent open season that concluded in March, 2005, the capacity of the Imperial Valley System was fully subscribed during the summer operating season, however excess capacity is available during the winter operating season. (SDG&E/SoCalGas/Bisi, Exh. 7, pp. 14-15.)

44 During the most recent open season that concluded in March, 2005, the capacity of the San Joaquin System was undersubscribed during both the summer and winter operating seasons. (Id. at p. 15.)

45 During the open season that concluded in May, 2005, the SDG&E system was fully subscribed during the winter operating season, while excess capacity was available during the summer operating season. (Id. at pp. 15-16.)

46 D.02-11-073, supra note 13 at *20-22, 47-49.

47 Id. at *21, 48-49.

48 Id. at *22, 49.

49 SDG&E/SoCalGas/Morrow, Tr. Vol. 2, pp. 161-162.

50 D.02-11-073, supra note 13 at *48.

51 If during any billing period, the customer's firm noncore usage is less than 75% of the customer's firm noncore MSQ, the customer will be assessed use-or-pay charges equal to 80% of the transmission charges multiplied by the difference between 75% of the customer's firm noncore MSQ and the customer's firm noncore usage for that month. (Special Condition 33, Rate Schedule GT-F).

52 The three tariff conditions specifying Full Requirements Service are:

(1) Customers may elect full requirements service under this schedule. Full requirements customers are not required to contract for a stated annual quantity.

(2) Full requirements customers are prohibited from using alternate fuels or bypass pipeline service (1) except in the event of curtailment, (2) to test alternate fuel capability, or (3) where the Utility has provided prior written authorization for the use of alternate fuels or bypass for temporary periods.

(3) In the event of any unauthorized alternate fuel use or bypass, customers must provide the Utility written notice thereof quantifying the extent to which alternate fuel or bypass use occurred. Such notice must be provided prior to the end of the month in which the usage took place. Any unauthorized alternate fuel or bypass use will be subject to a use-or-pay charge equal to 80% of the applicable transmission charge. No other use-or-pay charges are applicable to full requirements service. (Special Conditions 10, 11 and 12, SoCalGas Rate Schedule GT-F.)

53 SDG&E/SoCalGas/Hartman, Exh. 8, p. 13-14 (internal footnotes in original).

54 Id. at p. 15.

55 Id. at p. 12.

56 SDG&E/SoCalGas/Hartman, Exh.9 p.13.

57 Bypass refers to a customer electing to receive service from a provider other than the utility. In this instance, the service would be natural gas transmission.

58 Based on responses to data requests submitted by the Commission's Energy Division to California electric utilities.

59 SoCalGas/SDG&E Witness Bisi Exhibit 7 at 11, Table 5.

60 Id.

61 Id. at 12:3-5.

62 SoCalGas/SDG&E Witness Hartman Tr. at 67:23-69:13.

63 Sempra LNG Reply Brief, p. 5.

64 D.04-09-022, ordering paragraph 10.

65 SDG&E and SoCalGas referred to an Interconnection and Operational Balancing Account in the open access tariffs but, in compliance with Resolution G-3376, did not include a draft agreement in these advice letters.

66 On October 7, 2005, SDG&E and SoCalGas filed compliance advice letters 1474-G-B and 3413-B containing the approved Rule 39 and the three revised standardized tariffs. The Commission approved these as filed.

67 In theory, the IOBA agreements (and successor agreements) could apply to all California gas utilities. But in actuality, their main practical purpose has been to address connection with new LNG facilities, and all of the new LNG facilities currently being considered for California would interconnect with the SoCalGas/SDG&E grid. For this reason, the agreements being developed now are meant to be effective only for SoCalGas and SDG&E.

68 BHP Billiton, Coral Energy, El Paso, ExxonMobil, Independent Producers, Kern River, PG&E, SDG&E and SoCalGas, Sempra Global, Sound Energy Systems, Southern California Generation Coalition, and Transwestern filed comments on June 24, 2005.

69 The Energy Division had notified the utilities informally that the Commission was planning to defer the development of a standardized ICSUA to R.04-01-025. This was effectuated by Resolution G-3382.

70 Coral Energy, Indicated Producers, Kern River, Sound Energy Systems, and Transwestern filed comments on August 24, 2005.

71 Coral Energy Resources, Sempra Global, and Sound Energy Systems filed comments on December 2, 2005.

72 In A.04-08-018 the Commission is addressing the issue of standardized contracts for California-based gas suppliers.

73 This fact was also observed in the Energy Division's report of June 8, 2005, which summarized many of the terms of the existing interstate contracts.

74 See SoCalGas/SDG&E May 2, 2005 pre-workshop comments, p.6. During the May 11 workshop, SoCalGas/SDG&E argued that proximity allows less time to dispatch gas from other sources and allows fewer intervening connections with major pipelines and storage fields which otherwise could mitigate the impact of the supply disruptions.

75 SoCalGas/SDG&E noted during the May 11, 2005 technical workshop that they have seen this behavior especially from interconnecting entities that own the commodity they are supplying (these typically are California based suppliers), and have not observed this with the interstate entities, which typically do not own the commodity they are shipping.

76 Conclusion of Law 18.

77 Section 1.5 of the settlement reads as follows:

78 "SDG&E/SoCalGas" is used to describe the joint position of the two utilities. References to "SDG&E" or "SoCalGas" individually are intended to refer to just one of the two utilities.

79 SDG&E/SoCalGas Opening Brief, pp. 6-8.

80 Id., p. 17.

81 Id., p. 29.

82 Id., pp. 35-36.

83 SDG&E/SoCalGas Reply Brief, p. 6.

84 The NGC+ White Paper, which SDG&E/SoCalGas uses to support its recommendation, characterizes 1992 national "average" gas as having a Wobbe Number of 1345 (NGC+ White Paper, p. 26). SDG&E/SoCalGas proposes a Wobbe Number range that is plus or minus four percent of 1345.

85 SDG&E/SoCalGas Opening Brief, pp. 17-18.

86 Id., pp. 19-20.

87 Id., p. 10.

88 Id., p. 16.

89 SDG&E/SoCalGas Reply Brief, pp. 6-7.

90 SDG&E/SoCalGas Opening Brief, p. 12.

91 Id., pp. 13-14.

92 Id., p. 20.

93 Id., pp. 23-24.

94 Id., p. 21.

95 Id., p. 22.

96 Id., pp. 22-23.

97 Id., p. 28.

98 Id., p. 28.

99 SDG&E/SoCalGas Reply Brief, pp. 12-13.

100 SDG&E/SoCalGas Opening Brief, p. 28.

101 SDG&E/SoCalGas Reply Brief, pp. 11-12.

102 SDG&E/SoCalGas Opening Brief, p. 25.

103 Id., p. 26.

104 Id., p. 27.

105 Exhibit 105, SDG&E/SoCalGas Natural Gas Quality Testimony of Lee Stewart, pp. 5-6.

106 SDG&E/SoCalGas Reply Brief, p. 13.

107 SDG&E/SoCalGas Opening Brief, p. 46.

108 The South Coast Air Basin consists of all of Orange County and the urban portions of Los Angeles, Riverside and San Bernardino counties.

109 District Opening Brief, p. 3.

110 District Reply Brief, p. 6.

111 Id., p. 31.

112 District Reply Brief, p. 7.

113 District Opening Brief, p. 4.

114 Id., p. 4.

115 Id., p. 5-6.

116 Id., p. 8.

117 District Reply Brief, p. 12.

118 District Opening Brief, pp. 34-35, (emphasis in original).

119 Id., p. 37.

120 Id., p. 38-41.

121 District Reply Brief, pp. 24-27.

122 Id., p. 1.

123 District Opening Brief, pp. 12-17.

124 Id., p. 30.

125 Id., pp. 29-30.

126 District Opening Brief, pp. 11-12 and 47.

127 District Reply Brief, pp. 10-11.

128 BHP Opening Brief, p. 5.

129 Id., p. 6.

130 Id., pp. 7-8.

131 Id., p. 11.

132 Id.

133 Calpine Opening Brief, pp. 2-3.

134 Id., pp. 9-10.

135 Id., pp. 3-7.

136 Id., p. 18.

137 Id., p. 16.

138 Id., p. 10.

139 Id., pp. 11-12.

140 Calpine Reply Brief, p. 11.

141 Id., pp. 16-17.

142 Chevron Reply Brief.

143 Crystal Opening Brief.

144 Exxon Mobil Opening Brief, pp. 4-5.

145 Id., p. 6.

146 Id.

147 Id., p. 8.

148 Id., p. 12.

149 Id., p. 14.

150 Id., p. 7.

151 Id.

152 Id., p. 15.

153 Id., p. 36.

154 Id.

155 Id., p. 3.

156 Id., p. 21.

157 Id., p. 11.

158 Id., p. 11.

159 Id., p. 23.

160 Id.

161 Id., p. 30.

162 Id., p. 12.

163 Id., p. 12. (citing Gas Quality Workshop Tr. 20-21, February 12, 2005 (Stewart/SoCalGas))

164 Kern Opening Brief, p. 5.

165 Id., p. 9.

166 Id., pp. 6-7.

167 Kern Reply Brief, pp. 3-4.

168 Kern Opening Brief, p. 8.

169 Kern Reply Brief, p. 5.

170 PG&E Opening Brief, p. 2.

171 Id., p. 4.

172 Id., pp. 6-7.

173 Id., pp. 8-9.

174 Id., p. 14.

175 Id., p. 4.

176 Id., p. 13.

177 Id., pp. 16-17.

178 Id., p. 5.

179 Id., pp. 11-12.

180 Id., p. 9.

181 Id., p. 20.

182 Id., p. 23.

183 Id., p. 23.

184 Sempra Opening Brief, p. 3.

185 Id., p. 11, citing D.04-09-022 (Conclusion of Law 18) and the Energy Action Plan (at p. 10)

186 Sempra Opening Brief, p. 13.

187 Id., p. 6.

188 Id., p. 9.

189 Id., p. 10, citing Tr. Vol. 10 (Sempra LNG witness Bamburg) at p. 1260.

190 Id., p. 8.

191 Sempra Reply Brief, p. 13.

192 Sempra Opening Brief, p. 16.

193 Id., p. 10.

194 Id., p. 14.

195 Sempra Opening Brief, p. 4.

196 Id., p. 11.

197 Id., p. 10 and Sempra Reply Brief, p. 20.

198 Sempra Reply Brief, p. 20.

199 Sempra Reply Brief, pp. 23-24.

200 Id., pp. 15-16.

201 Shell Opening Brief, p. 9, citing Ex. 107, p.4.

202 Id., p. 12.

203 Shell Opening Brief, pp. 31-32.

204 Id., p. 16.

205 Id., pp. 16-18.

206 Id., p. 21.

207 Id., p. 37.

208 Id.

209 Id., p. 38.

210 Id., p. 39.

211 Id., p. 43.

212 Shell Reply Brief, p. 6.

213 Shell Opening Brief, pp. 45-46.

214 Shell Reply Brief, p. 13.

215 Shell Opening Brief, pp. 23-24

216 Shell Reply Brief, p. 14.

217 Id., p. 35.

218 Id., p. 32.

219 Shell Opening Brief, p. 52.

220 SCE Opening Brief, p. 6.

221 Id., p. 7.

222 Id., pp. 7 and 34.

223 Id., p. 36.

224 Id., pp. 9-10.

225 Id., pp. 12-13 and 17.

226 Id., p. 28.

227 Id., pp. 18-19.

228 Id., pp. 21-22.

229 Id., p. 23.

230 Id., pp. 24-26.

231 Id., p. 7.

232 The constituent percentages recommended by SCE are assumed to be molar percents, although SCE does not specify such in its comments.

233 SCE Opening Brief, pp. 28-29.

234 Id., p. 30.

235 Id., p. 33.

236 Id., pp. 14-15.

237 Id., pp. 42-43.

238 Id., p. 42.

239 Filed as Ex. 107, Attach B.

240 NGC+ White Paper, pp. 34-35.

241 Id., p. 3.

242 Id., p. 4.

243 Id., pp. 8-9.

244 Id., p. 9.

245 Id., pp. 12-13.

246 Id., p. 13.

247 Id., p. 13.

248 Id., p. 9.

249 Id., p. 22.

250 Experience has shown that using this plus/minus four percent formula in combination with the compositional limits will result in a local Wobbe range that is above 1,200.

251 Based on gross or higher heating value (HHV) at standard conditions of 14.73 psia, 60°F, dry, real basis.

252 Demonstrated experience refers to actual end use experience established by end-use testing and monitoring programs.

253 NGC+ White Paper, p. 27.

254 Id., p. 25.

255 Id., pp. 28-33.

256 Id., p. 21.

257 Policy Statement on Provisions Governing Natural Gas Quality and Interchangeability in Interstate Natural Gas Pipeline Company Tariffs, 115 F.E.R.C. P61,325 (FERC 2006), p. 13.

258 The District's proposal is for the South Coast Air Basin alone. However, as discussed below, we believe their proposed standard would have to be applied to the entire SoCalGas service territory.

259 The Energy Action Plan II was adopted by the CPUC and CEC on September 21, 2005.

260 See "Policy Statement on Greenhouse Gas Performance Standards" (October 6, 2005).

261 California Hydrogen Blueprint Plan, Volume 1 (May 2005), p. 15.

262 SCE did not support a maximum Wobbe Index of 1385.

263 The Producers are generally opposed to changes to the tariffs other than adopting a maximum Wobbe for SDG&E/SoCalGas.

264 The definition of historical California supplies is at Producers Opening Brief, p. 34, footnote 107.

265 Title 14 of the California Code of Regulations is cited herein as the "CEQA Guidelines".

266 See Simi Valley Recreation and Park Dist. v. Local Agency Formation Commission, 51 Cal.App.3d 648, 663 (1975), "CEQA was not intended to and cannot reasonably be construed to make a project of every activity of a public agency, regardless of the nature and objective of such activity."

Previous PageTop Of PageNext PageGo To First Page