Michael R. Peevey is the Assigned Commissioner, and Dorothy Duda is the assigned ALJ in this proceeding.
1. TURN has satisfied all the procedural requirements necessary to claim compensation in this proceeding.
2. TURN made a substantial contribution to D.06-03-025 as described herein.
3. TURN requested hourly rates for its representatives that are reasonable when compared to the market rates for persons with similar training and experience.
4. TURN requested related expenses that are reasonable and commensurate with the work performed.
5. The total of the reasonable compensation is $510,479.
6. The appendix to this opinion summarizes today's award.
1. TURN has fulfilled the requirements of Pub. Util. Code §§ 1801-1812, which govern awards of intervenor compensation, and is entitled to intervenor compensation for its claimed compensation incurred in making substantial contributions to D.06-03-025.
2. TURN should be awarded $510,479 for its contribution to D.06-03-025.
3. Per Rule 14.6(c)(6), the comment period for this compensation decision may be waived.
4. This order should be effective today so that TURN may be compensated without further delay.
ORDER
IT IS ORDERED that:
1. The Utility Reform Network (TURN) is awarded $510,479 as compensation for its substantial contributions to Decision 06-03-025.
2. Within 30 days of the effective date of this decision, Verizon California Inc. shall pay TURN the total award. Payment of the award shall include interest at the rate earned on prime, three-month commercial paper as reported in Federal Reserve Statistical Release H.15, beginning August 3, 2006, the 75th day after the filing date of TURN's request for compensation, and continuing until full payment is made.
3. The comment period for today's decision is waived.
This order is effective today.
Dated October 19, 2006, at Fresno, California.
MICHAEL R. PEEVEY
President
GEOFFREY F. BROWN
JOHN A. BOHN
RACHELLE B. CHONG
Commissioners
Commissioner Dian M. Grueneich, being necessarily absent, did not participate.
APPENDIX
Compensation Decision Summary Information
Compensation Decision: |
D0610043 |
Modifies Decision? N |
Contribution Decision(s): |
D0603025 | |
Proceeding(s): |
R9304003/I9304002 | |
Author: |
ALJ Duda | |
Payer(s): |
Verizon California Inc. | |
Intervenor Information
Intervenor |
Claim Date |
Amount Requested |
Amount Awarded |
Multiplier? |
Reason Change/Disallowance |
The Utility Reform Network |
5/19/06 |
$510,479 |
$510,479 |
No |
N/A |
Advocate Information
First Name |
Last Name |
Type |
Intervenor |
Hourly Fee Requested |
Year Hourly Fee Requested |
Hourly Fee Adopted |
Christine |
Mailloux |
Attorney |
The Utility Reform Network |
275 |
2002 |
275 |
300 |
2003 |
300 | ||||
325 |
2004-05 |
325 | ||||
Regina |
Costa |
Policy Expert |
The Utility Reform Network |
160 |
2000 |
160 |
200 |
2002 |
200 | ||||
215 |
2003 |
215 | ||||
230 |
2004-05 |
230 | ||||
Robert |
Finkelstein |
Attorney |
The Utility Reform Network |
395 |
2004-05 |
395 |
Robert |
Loube |
Economist |
The Utility Reform Network |
170 |
2003-05 |
170 |
Scott |
Kennedy |
Policy Expert |
The Utility Reform Network |
125 |
2003-05 |
125 |
Matthew |
Saltzer |
Computer Specialist |
The Utility Reform Network |
85 |
2003-05 |
85 |
(END OF APPENDIX)