4. Mitigation Measure V-3c

This mitigation measure requires SCE to avoid locating new roads in bedrock. SCE requests that this mitigation measure be modified to include the words, "to the extent feasible," in connection with this requirement, and to shorten the schedule for CPUC approval from 180 to 120 days. We agree that it is acceptable to shorten the schedule for CPUC approval and will make this change to the mitigation measure. We note that this modification does not change the substantive requirements of the mitigation measure and will not cause any significant environmental impacts itself. However, as to the "feasibility" language that SCE requests, we note that mitigation measures must, by definition, be feasible. Thus, if this measure cannot be feasibly implemented in certain locations, SCE should be able to present evidence supporting such a determination to CPUC and ANF staff. Thus, we see no need to change the mitigation measure to include the words, "to the extent feasible."